IREN Limited (NASDAQ: IREN) (together with its subsidiaries, “IREN”
or “the Company”), today published its monthly update for February
2025.
February Highlights
- Resilient mining hardware profit margin (70%)
- Ramping up to 50 EH/s over the next 4 months
- AI Cloud Service nearing full utilization at end of Feb
- AI Data Center ‘Horizon 1’ customer diligence ongoing
- Commenced site-works at 1.4GW Sweetwater 1 project, on-track
for energization in Apr 2026
- Finalizing 600MW Sweetwater 2 connection agreement
Key Metrics |
Feb 25* |
Jan 25 |
Dec 24 |
Bitcoin Mining |
|
|
|
Average operating hashrate |
28.7 EH/s |
29.0 EH/s |
28.1 EH/s |
Bitcoin mined3 |
459 BTC |
521 BTC |
529 BTC |
Revenue (per Bitcoin) |
$95,570 |
$99,789 |
$98,524 |
Electricity cost (per
Bitcoin)1 |
($28,341) |
($24,683) |
($22,799) |
Revenue |
$43.9m |
$52.0m |
$52.1m |
Electricity costs1 |
($13.0m) |
($12.9m) |
($12.1m) |
Hardware profit2 |
$30.9m |
$39.2m |
$40.1m |
Hardware profit margin4 |
70% |
75% |
77% |
|
|
|
|
AI Cloud Services |
|
|
|
Revenue |
$1.2m |
$0.8m |
$0.8m |
Electricity costs1 |
($0.04m) |
($0.04m) |
($0.02m) |
Hardware profit2 |
$1.1m |
$0.8m |
$0.8m |
Hardware profit margin4 |
96% |
96% |
98% |
|
|
|
|
* Note: 10% less
days in the month (28 days vs. 31 days in Jan) |
|
Management Commentary
“Our core Bitcoin mining operations remain strong and resilient.
Despite market volatility, we expect our expansion to 50 EH/s over
the next four months to generate substantial annualized operating
cashflows of approximately $600m5 at current market economics,”
said Daniel Roberts, IREN Co-Founder and Co-CEO.
“We’re also seeing increased demand for our AI and HPC
offerings. Our AI Cloud Service approached full utilization by
month-end, driven by strong interest in NVIDIA H100/H200s and,
looking ahead, next-generation air-cooled Blackwells. Horizon 1
development is progressing well, with strong customer interest,
including single-tenant demand far exceeding its initial 75MW
capacity. Customer workstreams are advancing through technical due
diligence, pricing negotiations and letters of intent.”
“Our financing and investing strategy remains flexible, with a
continued focus on accretive capital deployment. We are actively
assessing market conditions and exploring alternative capital
sources, including project financing for AI colocation
opportunities.”
Technical Commentary
-
Strong and resilient margins, underpinned by low
electricity costs and sector-leading fleet efficiency
-
At a lower Bitcoin price of $80k, annualized
operating cashflows of ~$500m at 50 EH/s5
-
Bitcoin production declined in February due to 10%
less days in the month (28 days vs 31 days)
-
AI Cloud Services revenue increased 39% with new
contract wins in February, fleet nearing full utilization at the
end of February, with additional contracted revenue expected to
materialize in March
Events
- Q2 FY25
Results WebcastReplay available here
-
Cantor Tech Conference New York, Mar 11, 2025
-
Roth Investor ConferenceNew York, Mar 17 - 18,
2025
-
NVIDIA GTCSan Jose, Mar 17 - 20, 2025
UNBC Career Fair, Prince George (Mar 2025)
Project Update
Horizon 1 (H2 2025)
-
75MW Liquid-Cooled Childress Data Center
-
Designed to support 200kW rack density (including NVIDIA Blackwells
and next-generation GPUs)
-
Strong customer interest exceeding initial 75MW capacity and
customer workstreams advancing
1.4GW Sweetwater 1 (April
2026)
-
General site-works now commenced
-
Prioritizing whole-of-site, single tenant
opportunities which continue to progress
600MW Sweetwater 2
-
Finalizing 600MW grid-connection agreement
-
>500 acres of land secured, ~28 miles from Sweetwater 1 and
~39 miles from Abilene
-
Design work underway for direct fiber loop between
Sweetwater 1 & 2 for the 2GW Sweetwater data center hub
Childress Construction (Mar 2025)
Sweetwater 1 Construction (Mar 2025)
Childress Project Status
Assumptions and Notes
- Electricity costs are presented on a net basis and calculated
as IFRS electricity charges, ERS revenue (included in other income)
and ERS fees (included in other operating expenses). Figures are
based on current internal estimates and exclude REC purchases.
- Hardware profit is calculated as revenue less electricity
costs. Hardware profit is a non-IFRS financial measure and is
provided in addition to, and not as a substitute for, measures of
financial performance prepared in accordance with IFRS. Refer to
the Forward-Looking Statements disclaimer.
- Bitcoin and Bitcoin mined in this investor update are presented
in accordance with our revenue recognition policy which is
determined on a Bitcoin received basis (post deduction of mining
pool fees).
- Hardware profit margin for Bitcoin Mining and AI Cloud Services
is calculated as revenue less electricity costs, divided by revenue
(for each respective revenue stream) and excludes all other
costs.
- Illustrative Operating Cashflow = illustrative mining revenue
less assumed net electricity costs, overheads and REC costs, and
does not include working capital movements. Source: CoinWarz
Bitcoin Mining Calculator. Illustrative calculations and inputs
assume hardware operates at 100% uptime, $90k and $80k Bitcoin
price scenarios, 800 EH/s global hashrate, $0.035/kWh electricity
costs, 3.125 BTC block reward, 0.1 BTC transaction fees and 0.13%
pool fees. 50 EH/s scenario: 765MW (power consumption), $104m
(overheads), $16m (REC costs). Illustrative Operating Cashflow is
for illustrative purposes only and should not be considered
projections of IREN’s operating performance. Inputs are based on
assumptions, including historical information, which are likely to
be different in the future and users should input their own
assumptions. There is no assurance that any illustrative outputs
will be achieved within the timeframes presented or at all, or that
mining hardware will operate at 100% uptime. The above should be
read strictly in conjunction with the forward-looking statements
disclaimer in this press release.
Contacts
MediaJon Snowball Sodali & Co+61 477 946
068+61 423 136 761Gillian RobertsAircover Communications+1 818 395
2948gillian.roberts@aircoverpr.com |
InvestorsLincoln Tan IREN+61 407 423
395lincoln.tan@iren.com |
To keep updated on IREN’s news releases and SEC filings, please
subscribe to email alerts
at https://iren.com/investor/ir-resources/email-alerts.
Forward-Looking Statements
This press release includes “forward-looking
statements” within the meaning of the Private Securities Litigation
Reform Act of 1995. Forward-looking statements generally relate to
future events or IREN’s future financial or operating performance.
For example, forward-looking statements include but are not limited
to the Company’s business strategy, expected operational and
financial results, and expected increase in power capacity and
hashrate. In some cases, you can identify forward-looking
statements by terminology such as “anticipate,” “believe,” “may,”
“can,” “should,” “could,” “might,” “plan,” “possible,” “project,”
“strive,” “budget,” “forecast,” “expect,” “intend,” “target”,
“will,” “estimate,” “predict,” “potential,” “continue,” “scheduled”
or the negatives of these terms or variations of them or similar
terminology, but the absence of these words does not mean that
statement is not forward-looking. Such forward-looking statements
are subject to risks, uncertainties, and other factors which could
cause actual results to differ materially from those expressed or
implied by such forward-looking statements. In addition, any
statements or information that refer to expectations, beliefs,
plans, projections, objectives, performance or other
characterizations of future events or circumstances, including any
underlying assumptions, are forward-looking.
These forward-looking statements are based on
management’s current expectations and beliefs. These statements are
neither promises nor guarantees, but involve known and unknown
risks, uncertainties and other important factors that may cause
IREN’s actual results, performance or achievements to be materially
different from any future results performance or achievements
expressed or implied by the forward looking statements, including,
but not limited to: Bitcoin price and foreign currency exchange
rate fluctuations; IREN’s ability to obtain additional capital on
commercially reasonable terms and in a timely manner to meet its
capital needs and facilitate its expansion plans; the terms of any
future financing or any refinancing, restructuring or modification
to the terms of any future financing, which could require IREN to
comply with onerous covenants or restrictions, and its ability to
service its debt obligations, any of which could restrict its
business operations and adversely impact its financial condition,
cash flows and results of operations; IREN’s ability to
successfully execute on its growth strategies and operating plans,
including its ability to continue to develop its existing data
center sites, including to design and deploy direct-to-chip liquid
cooling systems, and to diversify and expand into the market for
high performance computing (“HPC”) solutions it may offer
(including the market for cloud services (“AI Cloud Services”) and
potential colocation services; IREN’s limited experience with
respect to new markets it has entered or may seek to enter,
including the market for HPC solutions (including AI Cloud Services
and potential colocation services); expectations with respect to
the ongoing profitability, viability, operability, security,
popularity and public perceptions of the Bitcoin network;
expectations with respect to the profitability, viability,
operability, security, popularity and public perceptions of any
current and future HPC solutions (including AI Cloud Services and
potential colocation services) that IREN offers; IREN’s ability to
secure and retain customers on commercially reasonable terms or at
all, particularly as it relates to its strategy to expand into
markets for HPC solutions (including AI Cloud Services and
potential colocation services); IREN’s ability to manage
counterparty risk (including credit risk) associated with any
current or future customers, including customers of its HPC
solutions (including AI Cloud Services and potential colocation
services) and other counterparties; the risk that any current or
future customers, including customers of its HPC solutions
(including AI Cloud Services and potential colocation services), or
other counterparties may terminate, default on or underperform
their contractual obligations; Bitcoin global hashrate
fluctuations; IREN’s ability to secure renewable energy, renewable
energy certificates, power capacity, facilities and sites on
commercially reasonable terms or at all; delays associated with, or
failure to obtain or complete, permitting approvals, grid
connections and other development activities customary for
greenfield or brownfield infrastructure projects; IREN’s reliance
on power and utilities providers, third party mining pools,
exchanges, banks, insurance providers and its ability to maintain
relationships with such parties; expectations regarding
availability and pricing of electricity; IREN’s participation and
ability to successfully participate in demand response products and
services and other load management programs run, operated or
offered by electricity network operators, regulators or electricity
market operators; the availability, reliability and/or cost of
electricity supply, hardware and electrical and data center
infrastructure, including with respect to any electricity outages
and any laws and regulations that may restrict the electricity
supply available to IREN; any variance between the actual operating
performance of IREN’s miner hardware achieved compared to the
nameplate performance including hashrate; IREN’s ability to curtail
its electricity consumption and/or monetize electricity depending
on market conditions, including changes in Bitcoin mining economics
and prevailing electricity prices; actions undertaken by
electricity network and market operators, regulators, governments
or communities in the regions in which IREN operates; the
availability, suitability, reliability and cost of internet
connections at IREN’s facilities; IREN’s ability to secure
additional hardware, including hardware for Bitcoin mining and any
current or future HPC solutions (including AI Cloud Services and
potential colocation services) it offers, on commercially
reasonable terms or at all, and any delays or reductions in the
supply of such hardware or increases in the cost of procuring such
hardware; expectations with respect to the useful life and
obsolescence of hardware (including hardware for Bitcoin mining as
well as hardware for other applications, including any current or
future HPC solutions (including AI Cloud Services and potential
colocation services) IREN offers); delays, increases in costs or
reductions in the supply of equipment used in IREN’s operations;
IREN’s ability to operate in an evolving regulatory environment;
IREN’s ability to successfully operate and maintain its property
and infrastructure; reliability and performance of IREN’s
infrastructure compared to expectations; malicious attacks on
IREN’s property, infrastructure or IT systems; IREN’s ability to
maintain in good standing the operating and other permits and
licenses required for its operations and business; IREN’s ability
to obtain, maintain, protect and enforce its intellectual property
rights and confidential information; any intellectual property
infringement and product liability claims; whether the secular
trends IREN expects to drive growth in its business materialize to
the degree it expects them to, or at all; any pending or future
acquisitions, dispositions, joint ventures or other strategic
transactions; the occurrence of any environmental, health and
safety incidents at IREN’s sites, and any material costs relating
to environmental, health and safety requirements or liabilities;
damage to IREN’s property and infrastructure and the risk that any
insurance IREN maintains may not fully cover all potential
exposures; ongoing proceedings relating to the default by two of
the Company’s wholly-owned special purpose vehicles under limited
recourse equipment financing facilities; ongoing securities
litigation relating in part to the default, and any future
litigation, claims and/or regulatory investigations, and the costs,
expenses, use of resources, diversion of management time and
efforts, liability and damages that may result therefrom; IREN's
failure to comply with any laws including the anti-corruption laws
of the United States and various international jurisdictions; any
failure of IREN's compliance and risk management methods; any laws,
regulations and ethical standards that may relate to IREN’s
business, including those that relate to Bitcoin and the Bitcoin
mining industry and those that relate to any other services it
offers, including laws and regulations related to data privacy,
cybersecurity and the storage, use or processing of information and
consumer laws; IREN’s ability to attract, motivate and retain
senior management and qualified employees; increased risks to
IREN’s global operations including, but not limited to, political
instability, acts of terrorism, theft and vandalism, cyberattacks
and other cybersecurity incidents and unexpected regulatory and
economic sanctions changes, among other things; climate change,
severe weather conditions and natural and man-made disasters that
may materially adversely affect IREN’s business, financial
condition and results of operations; public health crises,
including an outbreak of an infectious disease and any governmental
or industry measures taken in response; IREN’s ability to remain
competitive in dynamic and rapidly evolving industries; damage to
IREN’s brand and reputation; expectations relating to
Environmental, Social or Governance issues or reporting; the costs
of being a public company; the increased regulatory and compliance
costs of IREN ceasing to be a foreign private issuer and an
emerging growth company, as a result of which we will be required,
among other things, to file periodic reports and registration
statements on U.S. domestic issuer forms with the SEC commencing
with our next fiscal year, and we will also be required to prepare
our financial statements in accordance with U.S. GAAP rather than
IFRS, and to modify certain of our policies to comply with
corporate governance practices required of a U.S. domestic issuer;
that we do not currently pay any cash dividends on our ordinary
shares, and may not in the foreseeable future and, accordingly,
your ability to achieve a return on your investment in our ordinary
shares will depend on appreciation, if any, in the price of our
ordinary shares; and other important factors discussed under the
caption “Risk Factors” in IREN’s annual report on Form 20-F filed
with the SEC on August 28, 2024 as such factors may be updated from
time to time in its other filings with the SEC, accessible on the
SEC’s website at www.sec.gov and the Investor Relations section of
IREN’s website at https://investors.iren.com.
These and other important factors could cause
actual results to differ materially from those indicated by the
forward-looking statements made in this investor update. Any
forward-looking statement that IREN makes in this investor update
speaks only as of the date of such statement. Except as required by
law, IREN disclaims any obligation to update or revise, or to
publicly announce any update or revision to, any of the
forward-looking statements, whether as a result of new information,
future events or otherwise.
Preliminary Financial Information
The financial information presented in this
investor update is not subject to the same closing procedures as
our unaudited quarterly financial results and our audited annual
financial results, and has not been reviewed or audited by our
independent registered public accounting firm. The preliminary
financial information included in this investor update does not
represent a comprehensive statement of our financial results or
financial position and should not be viewed as a substitute for
unaudited financial statements prepared in accordance with
International Financial Reporting Standards. Accordingly, you
should not place undue reliance on the preliminary financial
information included in this investor update.
Non-IFRS Financial
Measures
This investor update includes non-IFRS financial
measures, including electricity costs (presented on a net basis),
hardware profit and illustrative operating cashflow. We provide
these measures in addition to, and not as a substitute for,
measures of financial performance prepared in accordance with IFRS.
There are a number of limitations related to the use of non-IFRS
financial measures. For example, other companies, including
companies in our industry, may calculate these measures
differently. The Company believes that these measures are important
and supplement discussions and analysis of its results of
operations and enhances an understanding of its operating
performance.
Electricity costs are calculated as our IFRS
Electricity charges, ERS revenue (included in Other income) and ERS
fees (included in Other operating expenses), and excludes the cost
of RECs.
Hardware Profit is calculated as revenue less
electricity costs (excludes all other site, overhead and REC
costs).
Illustrative Operating Cashflow is calculated as
illustrative mining revenue less assumed net electricity costs,
overheads and REC costs, and does not include working capital
movements.
Photos accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/6bb52524-b545-4804-832a-5f3703579b87
https://www.globenewswire.com/NewsRoom/AttachmentNg/2931dd87-dc65-45bb-80e3-d15cd89cc551
https://www.globenewswire.com/NewsRoom/AttachmentNg/03d50aeb-b529-4c36-98c2-206e7e16bbc8
https://www.globenewswire.com/NewsRoom/AttachmentNg/dfe7ebf5-31d9-46b5-a2db-c962933a9bdd
https://www.globenewswire.com/NewsRoom/AttachmentNg/53aeca97-d3dd-4e1a-9c61-7db3f434e574
https://www.globenewswire.com/NewsRoom/AttachmentNg/4e948a2c-963c-4494-94b3-514eb0a978fb
IREN (NASDAQ:IREN)
Historical Stock Chart
From Feb 2025 to Mar 2025
IREN (NASDAQ:IREN)
Historical Stock Chart
From Mar 2024 to Mar 2025