Q1 2019 Asanko Gold Mine Highlights
(100% basis)
- Produced 60,425 ounces of gold, on track to meet 2019 guidance
of 225,000 – 245,000 ounces
- Generated EBITDA1 of $10.1 million and operating cash flows
before working capital changes of $10.5 million
- Held unaudited cash of $16.3 million on hand, $7.1 million in
receivables from gold sales and $7.1 million in gold on hand, as at
March 31, 2019
- All-in sustaining cost (“AISC”)1 of $1,123/oz, with 2019
guidance of $1,040 – $1,060/oz maintained
- Net loss after tax of $14.1 million including a loss of $13.3
million associated with adjustments to the carrying value of ore
stockpile inventory
Q1 2019 Quarterly Consolidated
Financials for Asanko Gold Inc.
- Net loss of $5.3 million including proportional adjustment to
net realizable value of the ore stockpiles at the AGM of $6.0
million
- Adjusted EBITDA1 of $3.1 million
- Held $8.8 million in cash as of March 31, 2019, with the final
$20 million cash payment related to the Gold Field’s transaction
expected no later than December 31, 2019
Commenting on the Q1 2019 performance, Greg
McCunn, Chief Executive Officer, said: “The Asanko Gold Mine
delivered a solid operational performance producing 60,425 ounces,
in line with our guidance for 2019. Costs for the quarter were
impacted by higher trucking costs as we initiated mining operations
at the large scale Esaase deposit. Commercial trucking contracts
are now in place and we expect oxide ore from Esaase to represent
25-30% of the mill feed on an ongoing basis. In addition, we
continued with the waste stripping of Cut 2 at Nkran. This is
nearing completion and as the pushback comes to a conclusion in Q3,
we forecast AISC to decline and maintain our full-year AISC
guidance of $1,040 – $1,060/oz.
After a thorough review of our current
operations in my first month as CEO, I can see that we are in the
final stages of a two year capital investment program, which
included a mill expansion from 3Mtpa to 5Mtpa, a major pushback of
the Nkran pit and the initial development of Esaase.
We are now well positioned to start harvesting
the benefits of these major investments as we shift our focus to
maximizing cashflow generation from the AGM over the next 18-24
months while we work with our JV partner on formulating the
long-term development plan for Esaase and optimal life of mine plan
for the AGM complex.”
|
Summary of Q1 2019 Asanko Gold Mine Operational and
Financial Results |
|
AGM (100% Basis) |
Q1 2018 |
Q4 2018 |
Q1 2019 |
Waste mined (‘000t) |
11,976 |
8,370 |
6,584 |
Ore mined (‘000t) |
853 |
1,370 |
1,505 |
Strip ratio (W:O) |
15.7 |
6.1 |
4.4 |
Average gold grade mined (g/t) |
1.3 |
1.5 |
1.4 |
Mining costs ($/t mined) |
3.23 |
4.13 |
4.48 |
Ore treated (‘000t) |
1,269 |
1,238 |
1,224 |
Gold feed grade (g/t) |
1.3 |
1.6 |
1.6 |
Gold recovery (%) |
93 |
95 |
93 |
Processing costs ($/t treated) |
11.17 |
12.39 |
11.93 |
Gold production (oz) |
48,229 |
59,823 |
60,425 |
Gold sales (oz) |
48,899 |
61,821 |
53,421 |
Average realized gold price ($/oz) |
1,314 |
1,215 |
1,292 |
Operating cash costs1 ($/oz) |
571 |
811 |
878 |
Total cash costs1 ($/oz) |
637 |
872 |
943 |
All-in sustaining costs1 ($/oz) |
1,226 |
1,072 |
1,123 |
All-in sustaining margin1 ($/oz) |
88 |
143 |
169 |
All-in sustaining margin1 ($m) |
4.3 |
8.8 |
9.0 |
Revenue ($m) |
64.4 |
74.2 |
67.0 |
Income (loss) from mine operations ($m) |
19.5 |
(0.8) |
(11.9) |
Net income (loss) after tax ($m) |
4.7 |
(3.1) |
(14.1) |
EBITDA1 |
32.3 |
17.4 |
10.1 |
Cash provided by operating activities |
20.1 |
12.9 |
8.8 |
|
Key Operational Highlights of the AGM
(on a 100% basis)
- No lost time injuries (“LTI”) were reported during the quarter,
and the AGM has now achieved over 24 months and more than 12.3
million employee hours worked without a single LTI.
- Waste stripping of the Cut 2 pushback at Nkran advancing
towards final stages, expected to be complete in Q3 2019.
- Achieved steady state levels of production at Esaase in
February 2019, with ore mining rates averaging 147,500 tonnes per
month over February and March at an average grade of 1.3 g/t.
- Trucking costs for the quarter were elevated as contractors at
Esaase transitioned from road construction activities to ore
haulage activities. Effective April 1, 2019, commercial contracts
in place and ore haulage costs expected to reduce to planned levels
of $7.00-$7.50 per tonne hauled.
- Notice of the JV’s intention to halt mining activities at
Akwasiso was initiated during the quarter.
JV Financial Performance
- The AGM incurred operating cash costs per ounce1 of $878, total
cash costs per ounce1 of $943 and AISC1 of $1,123 in Q1 2019. These
costs include a $248/oz impact associated with adjustments to the
carrying value of ore stockpile inventory and a $32/oz impact due
to the Ghanaian Government’s 5% non-refundable levy on certain
goods and services.
- Cash costs were higher in Q1 2019, compared to Q1 2018, partly
due to fewer waste tonnes being capitalized to stripping costs.
During the quarter, only $2.9 million of stripping costs were
deferred compared to Q1 2018 when the Eastern portion of Cut 2 at
Nkran was underway, which resulted in $26.1 million of stripping
costs being deferred and excluded from cash costs.
- Cash costs for the quarter were also impacted by unusually high
trucking rates at Esaase as contractors were transitioning from
road construction activities to ore haulage activities. These
factors were partially offset by higher gold sales volumes which
decreased fixed production costs on a per unit basis.
- AlSC for Q1 2019 were lower compared to Asanko’s AISC for Q1
2018 predominantly due to a $479/oz reduction in capitalized
stripping costs, associated with the Eastern portion of Cut 2 at
Nkran, and higher gold sales volumes which decreased fixed costs on
a per unit basis, partly offset by the previously described higher
cash costs. While there are no comparative AISC metrics reported
for the AGM on a standalone basis in Q1 2018, Asanko’s AISC for Q1
2018 included corporate G&A costs of $33/oz.
- Q1 2019 gold sales of 53,421 ounces at an average realized gold
price of $1,292/oz generating gold sales of $69.0 millon. Gold
sales were impacted by a change in the reporting period, which
shortened the quarter to 83 days instead of the normal 90 days.
This is a once-off timing adjustment. Revenue in Q1 2019 amounted
to $67.0 million and includes by-product sales of $0.2 million and
is reported net of $2.2 million of gold sales that were capitalized
in relation to Esaase pre-production activities in January
2019.
- Total cost of sales (including depreciation and depletion and
royalties) amounted to $78.9 million, an increase of $34.0 million
from Q1 2018. The increase in production costs was primarily driven
by an adjustment to the carrying value of the AGM’s stockpile
inventory to reflect the net realizable value of stockpiled ore, a
one-time contract termination fee relating to one of the JV’s
mining contractors, the introduction of ore trucking from Esaase to
the processing facility, as well as higher gold ounces sold.
Additionally, depreciation and depletion during Q1 2019 accounted
for $10.1 million of the increase in cost of sales, compared to Q1
2018, primarily due to the depletion of mineral interests related
to Esaase, which commenced commercial operations in February 2019,
while depreciation of right-of-use assets commenced in Q1 2019
following the capitalization of mining contractor leases in
accordance with IFRS 16 – Leases.
- Generated cash flow from operations of $8.8 million and $10.5
milion before working capital changes.
- The JV generated EBITDA1 of $10.1 million in Q1 2019.
- The AGM’s net loss after tax for the quarter amounted to $14.1
million, compared to net income of $4.7 million in Q1 2018. The
reduction in net income was due mainly to lower mine operating
earnings in Q1 2019 as discussed above, partially offset by a
reduction in deferred income tax expense and interest expense, the
latter resulting from the settlement of the Red Kite debt in July
2018.
- At quarter end, the JV had unaudited cash of $16.3 million on
hand, $7.1 million in receivables from gold sales and $7.1 million
in gold on hand.
|
Asanko
Gold Inc. – Summary Q1 2019 Financial Results |
|
Consolidated |
Q1 2018 |
Q4 2018 |
Q1 2019 |
Net income (loss) attributable to common shareholders ($m) |
2.1 |
(0.9) |
(5.3) |
Net income (loss) per share attributable to common
shareholders |
$0.01 |
($0.00) |
($0.02) |
Adjusted EBITDA1 ($m) |
30.9 |
6.1 |
3.1 |
|
|
|
|
- The Company reported a net loss of $5.3 million in Q1 2019
compared to net income attributable to common shareholders of $2.1
million in Q1 2018. The reduction in net income for Q1 2019 was
predominantly the result of the reduction in mine operating
earnings of the AGM, resulting in the JV reporting a net loss of
$14.1 million, of which the Company recognized its share of $6.4
million. This was partly offset by the recognition of $1.1 million
in service fees (net of withholding tax) earned as operators of the
JV and $2.4 million of finance income relating to the fair value
adjustment of the Company’s preferred share investments in the
JV.
- Reported Adjusted EBITDA1 of $3.1 million for Q1 2019 compared
to $30.9 million in Q1 2018. The decrease in Adjusted EBITDA1 was
primarily a result of the higher cash costs incurred by the AGM, as
well as a reduction in the Company’s interest in the AGM from 100%
to 45%. These factors were partly offset by an increase in the
AGM’s revenue.
2019 OutlookThe Asanko Gold
Mine is on track to meet 2019 guidance of 225,000 – 245,000 ounces
at AISC1 of $1,040 – $1,060/oz.
Since the announcement of the JV transaction,
Asanko’s technical team, together with input from Gold Fields, have
been reviewing the current Life of Mine plan. This includes a
number of scenarios for the long-term development of the Esaase
deposit, utilizing knowledge gained from the recent initiation of
minining operations, as well as the exploration potential of the
AGM’s land package, particularly the highly prospective South Camp
tenements. The JV partners are currently considering an optimal
work plan and timing required to deliver an updated Life of Mine
plan for the AGM and expect to update the market further in H2
2019.
This news release should be read in conjunction with Asanko’s
Management’s Discussion and Analysis and the Condensed Consolidated
Interim Financial Statements for the three months ended March 31,
2019, which are available at www.asanko.com and filed on
SEDAR. |
Notes:1 Non-GAAP
Performance MeasuresThe Company has included certain
non-GAAP performance measures in this press release. These non-GAAP
performance measures do not have any standardized meaning.
Accordingly, these performance measures are intended to provide
additional information and should not be considered in isolation or
as a substitute for measures of performance prepared in accordance
with GAAP. Refer to the Non-GAAP Measures section of Asanko’s
Management Discussion and Analysis for an explanation of these
measures and reconciliations to the Company’s reported financial
results in accordance with IFRS.
- Operating Cash Costs per ounce and Total Cash Costs per
ounceOperating cash costs are reflective of the cost of
production, adjusted for share-based payments and by-product
revenue per ounce of gold sold. Total cash costs include
production royalties of 5%.
- All-in Sustaining Costs Per Gold
Ounce The Company has adopted the reporting of
“all-in sustaining costs per gold ounce” (“AISC”) as per the World
Gold Council’s guidance. AISC include total cash costs, corporate
overhead expenses, sustaining capital expenditure, capitalized
stripping costs and reclamation cost accretion per ounce of gold
sold.
- Adjusted net income attributable to common
shareholdersThe Company has included the non-GAAP
performance measures of adjusted net income (loss) attributable to
common shareholders and adjusted net income (loss) per common
share. Neither adjusted net income nor adjusted net income
per share have any standardized meaning and are therefore unlikely
to be comparable to other measures presented by other
issuers. Adjusted net income excludes certain non-cash items
from net income or net loss to provide a measure which helps the
Company and investors to evaluate the results of the underlying
core operations of the Company and its ability to generate cash
flows and is an important indicator of the strength of our
operations and the performance of our core business.
- Adjusted EBITDAEBITDA provides an indication
of the Company’s continuing capacity to generate income from
operations before taking into account the Company’s financing
decisions and costs of amortizing capital assets. Accordingly,
EBITDA comprises net income (loss) excluding interest expense,
interest income, amortization and depletion, and income taxes.
Adjusted EBITDA adjusts EBITDA to exclude non-recurring items and
to include the Company’s interest in the adjusted EBITDA of the JV.
Other companies and JV partners may calculate EBITDA and Adjusted
EBITDA differently.
Qualified Person StatementFrederik Fourie
(Pr.Eng), Asanko Senior Mining Engineer, is the Asanko Qualified
Person, as defined by Canadian National Instrument 43-101
(Standards of Mineral Disclosure), who has approved the preparation
of the technical contents of this news release.
About Asanko Gold Inc.Asanko’s
flagship project, located in Ghana, West Africa, is the jointly
owned Asanko Gold Mine with Gold Fields Ltd, which Asanko manages
and operates. The Company is strongly committed to the highest
standards for environmental management, social responsibility, and
health and safety for its employees and neighbouring communities.
For more information, please visit www.asanko.com.
Forward-Looking and other Cautionary
InformationThis release includes certain statements that
may be deemed "forward-looking statements". All statements in this
release, other than statements of historical facts, that address
estimated resource quantities, grades and contained metals,
possible future mining, exploration and development activities, are
forward-looking statements. Although the Company believes the
forward-looking statements are based on reasonable assumptions,
such statements should not be in any way construed as guarantees of
future performance and actual results or developments may differ
materially from those in the forward-looking statements. Factors
that could cause actual results to differ materially from those in
forward-looking statements include market prices for metals, the
conclusions of detailed feasibility and technical analyses, the
timely renewal of key permits, lower than expected grades and
quantities of resources, mining rates and recovery rates and the
lack of availability of necessary capital, which may not be
available to the Company on terms acceptable to it or at all. The
Company is subject to the specific risks inherent in the mining
business as well as general economic and business conditions. For
more information, investors should review the Company's Annual Form
40-F filing with the United States Securities Commission and its
home jurisdiction filings that are available at www.sedar.com.
Neither Toronto Stock Exchange nor the
Investment Industry Regulatory Organization of Canada accepts
responsibility for the adequacy or accuracy of this release.
Cautionary Note to US Investors
Regarding Mineral Reporting Standards:Asanko has prepared
its disclosure in accordance with the requirements of securities
laws in effect in Canada, which differ from the requirements of US
securities laws. Terms relating to mineral resources in this press
release are defined in accordance with National Instrument 43-101 -
Standards of Disclosure for Mineral Projects under the guidelines
set out in the Canadian Institute of Mining, Metallurgy, and
Petroleum (the “CIM Council”) Standards on Mineral Resources and
Mineral Reserves (the “CIM Definition Standards”). The
Securities and Exchange Commission (the “SEC”) has adopted
amendments to its disclosure rules to modernize the mineral
property disclosure requirements for issuers whose securities are
registered with the SEC. As a result of the adoption of the SEC
Modernization Rules, SEC will now recognize estimates of “measured
mineral resources”, “indicated mineral resources” and “inferred
mineral resources” that are “substantially similar” to the
corresponding terms under the CIM Definition Standards. In
addition, the SEC has amended its definitions of “proven mineral
reserves” and “probably mineral reserves” to be “substantially
similar” to the corresponding CIM Definitions. United States
investors are cautioned that while the above terms are
“substantially similar” to CIM Definitions, there is no assurance
any mineral reserves or mineral resources that the Company may
report as ”proven reserves”, “probable reserves”, “measured mineral
resources”, “indicated mineral resources” and “inferred mineral
resources” under NI 43-101 would be the same had the Company
prepared the reserve or resource estimates under the standards
adopted under the SEC Modernization Rules.
Enquiries:
Alex Buck – Investor & Media Relations
Toll-Free (N.America): 1-855-246-7341
Telephone: +44 7932 740 452
Email: alex.buck@asanko.com
Gold Fields (NYSE:GFI)
Historical Stock Chart
From Aug 2024 to Sep 2024
Gold Fields (NYSE:GFI)
Historical Stock Chart
From Sep 2023 to Sep 2024