Cimic Maintains Fiscal Year Guidance Despite Financial Hit From Troubled Tunnel -- Update
December 16 2021 - 5:50PM
Dow Jones News
By Stuart Condie
SYDNEY--Cimic Ltd. maintained its full-year guidance despite
forgoing profit margin on a troubled multi billion-dollar tunnel
project in Australia's Victoria state.
The engineering and construction group on Friday said it had
reached a settlement following a dispute over the West Gate Tunnel
project, where costs had spiraled due to the unexpected expense of
dealing with contaminated soil dug out during tunneling.
Cimic said a settlement ruled that the total contract value of
the project to its 50-50 joint-venture with China Communications
Construction Co.-owned John Holland had increased to 8.57 billion
Australian dollars (US$6.15 billion) from an original contract
value of A$4.99 billion.
Cimic said its JV, which entered arbitration after seeking to
declare force majeure in 2020, agreed to reduce its revenue from
the project by A$600 million and to forgo profit margin. It expects
the financial impact of the settlement and other project risks to
be offset by existing provisions and other non-recurring gains.
Cimic maintained its net profit guidance of A$400 million-A$430
million for 12 months through December. It anticipates the same
figure on an underlying basis.
"The settlement resolves a long-standing legacy issue that has
absorbed significant management time and attention over recent
years," Cimic said in a statement. "Cimic is pleased to have
achieved this settlement, avoiding further potential legal and
other costs, while being able to maintain guidance."
The settlement includes Victoria state contributing A$1.9
billion and toll-road operator Transurban contributing A$2.0
billion to ensure the completion of the project, Cimic said.
Tunneling work will start in early 2022 and complete in late 2025,
Cimic said.
Transurban, which had opposed the contractors' attempt to
declare force majeure, said the JV had sought construction costs
significantly higher than those in the settlement.
"We recognize this situation has been disappointing, however we
believe this agreement represents the best path forward to deliver
the West Gate Tunnel project in the interests of all stakeholders,"
Transurban Chief Executive Scott Charlton said.
Transurban said $3 billion of its original capital contribution
had been deployed so far, with the remainder and A$1.7 billion of
its latest contribution not commencing until its 2023 fiscal
year.
The other A$300 million costs relate to site activation,
insurance and direct project management, it said.
Write to Stuart Condie at stuart.condie@wsj.com
(END) Dow Jones Newswires
December 16, 2021 17:35 ET (22:35 GMT)
Copyright (c) 2021 Dow Jones & Company, Inc.
Transurban (ASX:TCL)
Historical Stock Chart
From Nov 2024 to Dec 2024
Transurban (ASX:TCL)
Historical Stock Chart
From Dec 2023 to Dec 2024