DOW JONES NEWSWIRES
The following table lists unplanned and planned production
outages at U.S. refineries as reported by Dow Jones Newswires. The
information is compiled from both official and unofficial refining
sources and doesn't purport to be a comprehensive list.
Chevron Corp. (CVX) reported an upset April 11 at the sulfur
recovery unit at its refinery in El Segundo, Calif., according to a
government filing.
Valero Energy Corp. (VLO) on April 10 said its oil refinery in
Meraux, La., is in restart mode following a brief power outage
earlier in the day. The alkylation unit will remain shut for
turnaround maintenance and the FCCU will be off line until the
alkylation unit returns to service.
Planned turnaround maintenance under way since early March
continues at Valero Energy Corp.'s (VLO) Memphis refinery crude
distillation unit. The plant filed a report to NRC in anticipation
of possible flaring or emissions as the crude unit at Memphis, and
other units, begin the restart process following the turnaround,
however the crude unit turnaround is still under way, the company
said on April 10.
Planned crude, coker and reformer maintenance has concluded at
ConocoPhillips' San Francisco-area refinery in Rodeo, California,
company spokesman Rich Johnson said on April 9. Traders doing
business in the region said the work well underway in early March;
published reports said the turnaround began in mid-Feb.
The Wood River Refinery, a joint venture owned by ConocoPhillips
(COP) and Cenovus Energy (CVE), in Roxana, Illinois, said emissions
of sulfur dioxide were routed to the plant's safety flare stack on
Saturday evening after an ultralow-sulfur diesel hydrotreater had
tripped off line. No other details were provided.
HollyFrontier Corp. (HFC) on April 5 said an FCCU at its Navajo
refinery in Artesia, New Mexico cracking unit will be shut down for
10 to 15 days for unscheduled mechanical repairs. HollyFrontier
said the downtime will reduce crude throughput by approximately
800,000 barrels.
ExxonMobil Corp. (XOM) on April 4 confirmed the shutdown of
Crude Unit B, a coker unit and corresponding units for several
weeks of planned maintenance at it's refinery in Beaumont, Texas.
Minimal impact to production is expected and all contractual
commitments will be met, the company said.
For more detailed information, search Dow Jones Newswires using
the code N/REF.
Operator Refinery Capacity Description Restart
(in 000s
bbl/day)
UNPLANNED
CANADA
CARIBBEAN
EAST COAST
MIDWEST
CVR Wynnewood 70.0 Power snag forces SRU off-line
Energy OK on Apr 2, a filing to the NRC
said.
GULF COAST
Holly Artesia, NM 100.0 FCCU shut for 10-15 days unplan-
Frontier ned maintenance on April 5.
Pasadena Pasadena TX 100.0 Coker unit damanged by on Dec 10
Refining fire. Fire contained; no other
units affected, the co. said
on Dec. 12. On Jan 27, the co.
said there was no change since
the Dec. 12 statement; no re-
start timing.
Valero Meraux LA 135.0 Refinery in restart after brief
power outage on Apr 9. Alky Unit
still shut for turnaround and
FCCU shut until that work is done.
MIDWEST
Exxon Channahon 240.0 Gas compressor unit shut at
Mobil IL catalytic hydrodesulfuriza-
tion unit on Mar 12. No other
details provided.
WRB Roxana 306.0 Ultralow-sulfur diesel hydro-
Refining IL treater trips off-line on Apr
7 - filing. No further details
were provided.
ROCKIES
WEST COAST
BP Ferndale, 230.0 Refinery idled after Feb. 17 End
WA fire at crude unit. Repairs
expected to go on through April.
PLANNED
CANADA
Husky Saskatchewan 21-days maintenance set in 1stH
Upgrader first half 2012 at hydrogen 2012
plant, the co. said on Feb 9.
Husky Saskatchewan Major turnaround to take place Spring
Refinery in spring of 2013. Plant-wide 2013
shutdown for inspection and
equipment repairs.
CARIBBEAN
HOVENSA St. Croix 350.0 Refinery shutdown completed, the Feb 21
co. said on Feb. 21. The facility 2012
will be operated as a products
storage terminal.
Valero Aruba 235.0 Operations will be suspended
at the end of March due to eco-
nomics, the co. said on Mar 19.
EAST COAST
Conoco Trainer, PA 185.0 Crude processing halted;
operations winding down,
on Sept. 30.
The refinery will be
shuttered at end-May if
not sold.
Sunoco Philadelphia 335.0 Refineries up for sale on July
Marcus Hook 190.0 Sept. 6; Marcus Hook shut 2012
Dec. 1 ahead of schedule
due to poor refining econo-
mics. Phila. to shut in July.
GULF COAST
BP Texas City 406.6 FCCU No. 3 and Alkylation unit down
TX for routine maintenance that began
around Jan. 5 continues, a person
familiar with the refinery said on
Apr 5. Restart estimate not available.
Conoco Belle Chasse 247.0 Refinery up for sale a
Phillips LA Nov. 29 Bloomberg News
report said.
Exxon Baytown 560.6 Two months turnaround work got Feb
Mobil TX under way on Feb. 1 at an alky- 24
lation unit and FCCU.
Exxon Beaumont 345.0 Crude Unit B, Coker Unit and
Mobil TX associated units shut for plan-
ned maintenance on Apr 1. Work
will continue for several weeks.
Holly Artesia, NM 100.0 Crude runs will be reduced by Early
Frontier 50% during 30 days of major turn- 2012
maintenance in early 2012, the Co.
said on Aug. 5.
Valero McKee TX 170.0 5 week FCCU turnaround began on May 5
March 31 weekend, the co. said
on Apr 2.
Vacuum unit turnaround planned in
first half of 2012, company said.
Expansion project announced
March 2011 to increase crude oil
throughput by 25,000 b/d to
195,000 b/d.
Valero Meraux, LA 135.0 FCCU will be shuttered during
alkylation unit turnaround main-
tenance that began wk of Jan 2.
Work continues the co. said on
Apr 10.
Valero Houston,TX 88.0 Seven weeks of FCCU maintnance end-March
starting in Feb. 2012 the Co.
said on Nov. 1, 2011.
Valero Norco, LA 185.0 Co. on Jan. 31 said 10-weeks of April
planned crude/coker unit mainte- 2012
will get under way in Feb.
Hydrocracker project will pro- 2013
ceed and be completed in late
2013, the co. said on 7/27/10.
Upgrade project to build 2012
a new diesel hydrotreater
unit moved from 2010 to
4Q 2012.
Valero Port Arthur 325.0 Hydrocracker project will pro- 2012
TX ceed and be completed in late
2012. Hydrocracker remains shut
for catalyst change, the co.
said on Apr 6.
MIDWEST
CVR Coffeyville 115.7 Final phase of turnaround work Q1
KS will begin Feb 28 at crude unit 2012
No. 2, coker, vacuum unit No. 2,
hydrotreater for 4-5 weeks. First
two phases concluded in Nov 2011.
CVR Wynnewood 54.0 30-40 days maintenance planned Q3
OK in 3rd Q 2013, the co. said on 2013
Nov. 3, 2011.
Holly Tulsa, OK 125.0 The entire refinery will be shut Late
Frontier while West Plant section under- 2012
goes major turnaround maintenance
in late 2012, the Co. said on
Aug. 5, 2011.
Husky Lima, OH 160.0 15-days of maintenance at diesel 4Q
Energy hydrotreater; 29-day at aromatics 2012
unit set for 4Q 2012, the co.
on Feb 9.
New 20,000-b/d kerosene hydro- 1stH
treater will start up in 1st 2013
half 2013, to co. said on Feb 9,
2012.
45-days of major turnaround sched-
uled in 2014; 70% of units involved.
Remaining 30% will under go major
turnaround in 2015, the co. said
on Feb 9, 2012.
Husky Toledo, OH 140.0 Minor turnaround planned in mid-
Energy 2012; the partial outage will
last about 21 days, the co. said
on Feb. 9.
Tesoro Mandan, ND 58.0 Total crude-oil processing capa- 2nd Q
city to increase by 17% to 68,000 2012
b/d by 2nd quarter 2012.
Valero Memphis, TN 180.0 Five weeks of maintenance on early-April
crude unit starting in March. 2012
2012, co. said on Nov. 1, 2011.
ROCKIES
WEST COAST
Alon Bakersfield 14.5 Refining operations halted for
CA at least one month for econo-
mic reasons, a local news re-
port said on Jan 15.
BP Carson, CA 265.0 Planned CDU maintenance begins Mar 26
on Mar 13; flaring and emissions
are expected through Apr 6.
BP Ferndale, 230.0 Refinery idled after Feb. 17 End
WA fire at crude unit. Planned April
maintenance advanced; plant
will remain shut through April.
Conoco Ferndale 100.0 Turnaround maintenance under way Apr 7
WA on Mar 10 at unspecified unit or or 14
units, co. said. Traders said
work will last 5-6 weeks.
Conoco San Francisco 120.2 Planned turnaround maintenance Apr 8
ended the co. said on Apr 8.
Traders said CDU, reformer, coker
turnaround was well under way
on Mar 9; published reports said
the work started in mid-Feb.
Tesoro West Coast N/A Q4 2011 maintenance at West
Coast refineries delayed until
2012. Further details not pro
vided.