TIDMLOND

RNS Number : 8087G

London Mining Plc

12 May 2014

London Mining Plc

Quoted on London AIM (LOND LN)

("London Mining" or the "Company")

12 May 2014

Q1 2014 PRODUCTION REPORT AND INTERIM MANAGEMENT STATEMENT

2014 production guidance reiterated

Rescheduling of Marampa capital programme to increase financial flexibility

Potential for strategic partnership to reduce debt and fund accelerated growth plans

Highlights

Marampa, Sierra Leone (100% owned)

Operations

   --      Q1 production of 900kwmt, a 17% increase on Q4 2013 
   --      2014 production guidance of 4.9 to 5.4Mwmt/a reiterated 
   --      Plant upgrades in operation with design rates achieved on a more regular basis 
   --      4 months of ROM stocks in place ahead of the wet season in accordance with plan 

Rescheduled capital programme

   --      USD175 million of "Life of Mine" extension capital programme to be deferred by two years by prioritisation of mining and processing of weathered ore through modified plant 

-- 6.5Mwmt/a production capacity maintained post tailings depletion with minimal effect on all-in unit cost reduction

   --      40 year "Life of Mine" extension capital programme moved from 2016 to 2019 

Potential for strategic partnership to reduce debt and fund accelerated growth plans

-- Process being initiated to secure a strategic partner for a minority interest at the Marampa asset level in 2014 to reduce debt and fund accelerated growth plan

-- Potential for Life of Mine extension to achieve 8Mwmt/a for incremental capital cost of around USD110 million delivering higher Net Asset Value and further unit operating cost reduction

Commenting on the results Graeme Hossie, CEO, said: "The plant upgrades installed in Q4 are now operating and achieving design throughput rates although not yet with the full consistency we would like. However, Q1 production was in line with our expectations during commissioning with volumes continuing to increase and grade now improving. We reiterate our production guidance of 4.9 to 5.4Mwmt for 2014.

As part of an ongoing expenditure review in the current weak iron ore pricing environment, we have decided to improve financial flexibility by deferring USD175 million of capital expenditure for two years. This plan extends the mine life after depletion of tailings through processing of weathered ore, maintaining a 6.5Mwmt/a rate and continues to lower Marampa's unit operating cost. We expect that the increased free cash flow generated from this capital deferral will allow us to reduce debt and interest costs.

Our options for growth however remain open and we have identified a further high return improvement option to the Life of Mine extension which would establish a 8Mwmt/a operation for low additional capital intensity. The resultant life of mine unit operating costs would be expected to fall below the USD39 to 42/wmt estimated in the September 2013 Life of Mine feasibility study. In order to de-lever and fund our growth plans the Board has decided now is the right time to secure a strategic partner at the Marampa asset level and we are beginning a process to identify the right partner and financing options for London Mining. We aim to conclude this process by the end of the year.

The Board and management team remain focussed on balancing investment needs with shareholder returns and reducing risk in this current uncertain commodity pricing environment."

Operations

Q1 2014 summary

 
                                                   Q1 2014   % change   Q4 2013   Q1 2013 
------------------------------------------------  --------  ---------  --------  -------- 
 Concentrate produced (wmt)                            900        +17       770       706 
 Sales (wmt)                                           877        -25     1,162       589 
 Average concentrate grade sold (Fe%)                 63.1          0      63.1      63.5 
 Average concentrate moisture content sold (%)         8.9       +0.1       8.8       7.1 
 Average FOB price * including hedges (USD/dmt)         80         -5        84       104 
 Average freight (USD/wmt)                              34          0        34        35 
------------------------------------------------  --------  ---------  --------  -------- 
 

*Free on board ("FOB") prices are net of freight and grade premium as at loading, but exclude marketing related fees

Production

Production of 900kwmt in Q1 2014, an increase of 17% on the previous quarter, was in line with expectations during commissioning and production guidance for 2014 of 4.9 to 5.4Mwmt is reiterated. Design capacity is being achieved on an increasingly regular basis although average grade remained flat during the quarter at 63.1% Fe due to the continued commissioning process. Return to the design grade of 64 to 65% Fe is expected as ramp up is completed. Building of the ROM stockpile is progressing well with 4 months of stocks now in place to provide buffer feed to the plant during the wet season. Q2 2014 production is expected to show increased volume following consistent availability and operation of the spirals and milling circuits with significantly increased volume expected to be achieved from Q3 when programmes to maximise plant availability are fully embedded. Logistics continue to improve according to plan with the first of the new fleet of pusher barges having arrived in Freetown and commenced operations. Lower cost benefits from the more efficient barging format will be realised from Q2 2014 as increased production volumes from the 5.4Mwmt/a plant come online with further incremental export capacity added as plant capacity builds to 6.5Mwmt/a.

Sales

Sales volumes were 877kt, 25% less than Q4 2013 following full draw down of concentrate stockpiles in December 2013. Bulk freight rates remained consistent with 2013 levels in Q1 2014 but loading of our first baby cape vessels (90 - 120kt) in the inner harbour in March, combined with lower panamax rates of around USD27/wmt is expected to result in lower freight rates in Q2. A dredging programme is planned to allow loading of larger cape size vessels in the inner harbour by the end of 2014, which is expected to result in a structural lowering of seaborne freight costs.

Realised pricing was impacted by premium decrease and related penalty charges due to lower iron content, demurrage and the negative impact of hedging. However, two spot sales undertaken in Q1 realised a USD7/dmt premium to existing offtake pricing. 0.56Mdmt of Q1 sales were hedged at USD119/dmt CFR. At the end of March, 1.01Mdmt of 2014 sales remain hedged at an average price of USD118/dmt CFR. Reported pricing on a quarterly basis will have the potential to be impacted by the actual realised price for the portion of sales which are priced based on the CFR iron price two months post loading.

In March, London Mining agreed a five year offtake agreement with Cargill for 1Mwmt/a of Marampa concentrate which will realise materially higher net pricing for 64 to 65% Fe product due to London Mining gaining full Platts Fe premiums and incurring no marketing fees. The agreement also provides USD20million of additional liquidity in the form of a prepayment facility. Deliveries into the Cargill offtake contract will commence in H2 2014. Further pricing improvements are expected as grade improves and from reduced demurrage as volumes stabilise post ramp-up.

Health and safety

We continue to see an improvement in health and safety following the implementation of improved safety systems and training. We are now employing the All Injury Frequency Rate to monitor safety performance.

 
                                    Q1 2014  Q4 2013   Q1 2013 
---------------------------------  --------  -------  -------- 
 Fatalities                            0        0         0 
                                   --------  -------  -------- 
 LTI                                   1        0         0 
                                   --------  -------  -------- 
 All Injuries                         18       30         7 
                                   --------  -------  -------- 
 LTIFR (12mth rolling average)       0.33     0.21      0.94 
--------------------------------- 
 AIFR (12 month rolling average)      8.2      8.4       9.8 
---------------------------------  --------  -------  -------- 
 

Rescheduled capital programme

Due to continued uncertainty in the short and medium outlook for iron ore pricing, a revised development plan is being implemented. In the short term, some early works to deliver 6.5Mwmt/a have been delayed in 2014 to achieve delivery in H2 2015. In the medium term, London Mining will upgrade the processing plant to enable processing of 100% weathered ore following depletion of the tailings portion of the reserve in 2016. This allows deferral of USD175 million of the USD240 million Life of Mine extension capital programme for two years whilst maintaining 6.5Mwmt/a production capacity for five years from H2 2015 and continuing the downward operating cost trajectory from current levels towards the USD39 to 42/wmt level envisaged for the 40 year Life of Mine extension. The revised plan is based on existing feasibility work, operating performance data of current crushers and ball mills and incorporates the expanded licence area granted by the Government of Sierra Leone during the quarter which allows for greater mining flexibility and efficiency.

In order for Marampa to maintain the nominal production rate of 6.5Mwmt/a post tailings depletion, the plant will be reconfigured in 2016 to incorporate a new crushing and screening circuit at a capital cost of USD35 million. Regrind mills previously scheduled as part of the Life of Mine programme, will also be installed in 2016 at a cost of USD30 million. The regrind mills will be incorporated into the Life of Mine flow sheet for unweathered ore after depletion of the weathered ore. A power requirement of 18MW (an increase of 6MW from currently installed capacity of 12MW) is anticipated, significantly less than the 50MW required for the processing of unweathered ore. Increased stripping is required during the weathered ore period (average 0.65:1 over 3 years) but will revert to the 0.5:1 life of mine average.

New mine life extension plan timing and capex

 
                               Resource                Process          Concentrate      Installed    Capital Estimate 
                                                                          (Mwmt/a)          Date           (USDm) 
------------------------  -----------------  -------------------------  -----------  ---------------  ---------------- 
        Installed              Tailings/         Magnetic separation        1.6          Dec 2011           340 
                             weathered ore          (first plant)                                          (spent) 
------------------------  -----------------  -------------------------  -----------  ---------------  ---------------- 
                                                 Magnetic separation        4.0          Jan 2013 
                                                    (second plant) 
------------------------  -----------------  -------------------------  -----------  ---------------  ---------------- 
                                               Addition of spirals and      5.4           Q4 2013 
                                                    ball milling 
------------------------  -----------------  -------------------------  -----------  ---------------  ---------------- 
                               Tailings/        Additional WHIMS and 
   Low cost expansion        weathered ore             spirals              6.5           2014/15            15 
------------------------  -----------------  -------------------------  -----------  ---------------  ---------------- 
                             Weathered ore     Additional crushing and 
 Life Of Mine extension        (to 2019)            regrind mills           6.5        2015 and 2016         90 
------------------------  -----------------  -------------------------  -----------  ---------------  ---------------- 
    All ore types        Addition of primary crusher, SAG mill and 
      (to 2055)                         regrind mills                       6.5            2019             190 
 -----------------  --------------------------------------------------  -----------  ---------------  ---------------- 
 

Old and revised guidance

 
                   Expansion capital programme     Operating cost (USD/wmt) 
                              (USDm) 
 Year                Old           Revised            Old          Revised 
---------------  ----------  ------------------  -------------  ------------ 
                                                  At or under    At or under 
 2014                40              15                50             50 
                 ----------  ------------------  -------------  ------------ 
 2015 and 2016       240             90           No guidance      42 - 47 
                 ----------  ------------------  -------------  ------------ 
 2017 to 2019         -              190            39 - 42        39 - 42 
                 ----------  ------------------  -------------  ------------ 
 2020 onwards         -               -                           39 to 42 
---------------  ----------  ------------------  -------------  ------------ 
 

Potential for strategic partnership at the asset level to reduce debt and accelerate growth plans

A further low cost incremental expansion to 8Mwmt/a has been identified as part of the Life of Mine extension optimisation programme using existing logistics infrastructure and expansion of the 6.5Mwmt/a plant for around an estimated additional USD110 million (approximately USD70 per annual tonne of capacity) by installing a secondary crushing circuit, additional spirals and wet high intensity magnetic separation capacity. This is expected to deliver a further reduction in operating cost below the USD39-42/wmt estimated by the September 2013 feasibility study and a significant increase in NAV. The expansion to 8Mwmt/a could be accelerated to late 2016 resulting in significant capital and operating cost savings.

In view of ongoing pricing volatility and the potential now identified to deliver increased production and reduced operating cost with further investment, London Mining's board considers that it is the right time to consider the involvement of a strategic investor for a minority interest at the Marampa asset level to reduce debt and accelerate growth plans. London Mining is exploring interest from potential strategic partners and expects to complete this process by the end of 2014.

In the near term, following the fall in the iron ore price and with pricing environment uncertain, the company considers it prudent to increase liquidity and to this end, as previously advised, is in discussions with IFC, offtakers and other providers of finance.

Webcast and conference call

There will be a webcast and conference call for analysts and investors hosted by Graeme Hossie (CEO), Benjamin Lee (CFO) and Jim North (COO) at 8.30am BST today.

The presentation will be available via a live webcast, a link to the webcast can be found on London Mining's website here: http://www.londonmining.com/investors/reports-and-presentations/.

The webcast will include audio from the conference call and synchronised power point slides. You will not be able to post questions through the webcast.

Please use the following numbers and conference ID to dial in to the conference call:

 
 Country                  Number 
 International dial-in    +44(0)20 3427 0503 
 UK Toll Free             0800 279 5004 
 USA Toll Free            1877 280 2342 
 
 Confirmation code        7220022 
 

There will be a replay facility available on London Mining's website after the webcast.

For more information, please visit www.londonmining.com or contact:

 
 London Mining Plc 
  Graeme Hossie, Chief Executive Officer 
  Benjamin Lee, Chief Financial Officer 
  Thomas Credland, Head of Investor Relations     +44 (0)20 7408 7500 
 Liberum Capital (Nominated Adviser/Broker) 
  Richard Crawley / Tom Fyson / Ryan de Franck    +44 (0)20 3100 2000 
 J.P. Morgan Cazenove (Broker) 
  Ben Davies / Ignacio Borrell                    +44 (0)20 7742 4000 
 Brunswick Group LLP 
  Carole Cable / David Litterick                  +44 (0)20 7404 5959 
 

About London Mining

London Mining is an expanding producer of high specification iron ore concentrate for the global steel industry and is focused on identifying, developing and operating sustainable mines. London Mining commenced sales from its 100% owned Marampa Mine in Sierra Leone in 2012 producing 3.4Mwmt/a in 2013 and expanding to a capacity of 6.5Mwmt/a over the next few years. Marampa has sufficient resources to support a staged expansion to up to 20Mwmt/a. London Mining has also completed bankable feasibility studies outlining plans for a further 20Mwmt/a of iron ore production by developing mines in Greenland and Saudi Arabia. The Company listed on AIM in London on 6 November 2009. It trades under the symbols LOND.L (Reuters) and LOND LN (Bloomberg). More information about London Mining can be found at www.londonmining.com.

This information is provided by RNS

The company news service from the London Stock Exchange

END

IMSGGUBCAUPCPUG

London Mining (LSE:LOND)
Historical Stock Chart
From Jun 2024 to Jul 2024 Click Here for more London Mining Charts.
London Mining (LSE:LOND)
Historical Stock Chart
From Jul 2023 to Jul 2024 Click Here for more London Mining Charts.