Asante Gold Corporation (CSE:ASE | GSE:ASG |
FRANKFURT:1A9 | U.S.OTC:ASGOF) (“Asante” or the
“Company”) is pleased to provide an update on its operations and
corporate activities.
Operations Update – Bibiani
Mine
The Bibiani process and mine facilities are
operating on a 24 hour per day basis with throughput of
approximately 3.0M tonnes per year. Completion of critical plant
upgrades and other capital initiatives, as outlined below, are
expected to enable material increases in throughput, gold recovery
and production levels with a commensurate decrease in all-in
sustaining costs per ounce in Q4 2023. The Company continues to
advance near-term funding initiatives to provide the required
capital to achieve these initiatives.
Recent achievements and planned initiatives at
Bibiani include:
- Exploration of
near mine targets proved to be successful with the Grasshopper
satellite pit coming into production in Q2 2023. At the South
Russel deposit, a starter pit is planned to be developed during Q4
with delivery of mineralized material expected to occur by January
2024;
- The gravity
plant was upgraded prior to start of production in July 2022 and
continues operation achieving 25 – 35% gold recovery, as planned.
The installation of a scalping screen is planned to increase
gravity gold recovery by 5% with expected completion in late
October 2023;
- The oxygen
plant, installed on schedule, has been providing oxygen to the
process plant from September 2023. Installation of a Mach-reactor
to increase oxygen utilization will be completed this week;
- A pebble crusher
has been ordered and will be installed in the coming months to
increase process plant throughput capacity from 3.0 million to 3.4
million tonnes per year;
- The Sulphide
Recovery Plant long lead items are expected to ship in September
2023. Construction of the plant is planned to be five months from
the time of delivery to site. When in operation, the Sulphide
Recovery Plant is expected to improve gold recovery to over
90%;
- Construction of
the planned detour road is nearly complete allowing the highway to
be cut and providing access to higher grade mineralized material
from the main pit by early 2024; and
- Other cost saving and productivity
improvement initiatives have started with implementation planned
over the coming months.
For the fiscal year ending January 31, 2024, the
Company expects production of approximately 80,000 to 90,000 ounces
gold at Bibiani. Subject to receipt of the requisite funding and
completion of capital projects as outlined above, Asante expects
Bibiani to produce approximately 180,000 ounces of gold for the
fiscal year ending January 31, 2025 with all-in sustaining costs of
$1,325/oz. See footnote 1 below for assumptions.
Operations Update – Chirano
Mine
The Chirano process and mine facilities are
operating on a 24 hour per day basis at a current throughput of
approximately 3.6M tonnes per year.
Recent achievements and planned initiatives at
Chirano include:
- Gravity plant
design, procurement and installation is advanced, with completion
expected in October 2023 to increase gold recovery at Chirano by
5%;
- Oxygen addition
to the CIL (carbon-in-leach) plant is proceeding and the oxygen
plant is planned for installation prior to November 30, 2023;
- A pebble crusher
was procured and installed on schedule in May 2023 increasing plant
throughput from 3.4 million to 3.6 million tonnes per year;
- Further primary
grinding upgrades are planned to be operational late this year to
increase process plant throughput from 3.6 million to 4.0 million
tonnes per year;
- Relocation of
minor infrastructure and facilities planned to provide access to
and expansion of the Akoti South open pit and the second cutback at
the Sariehu open pit is progressing well;
- Mining from the
Mamnao central and south pits is expected to be completed during Q3
2024. This production is expected to be replaced by Sariehu and
Mamnao north pits. These initiatives would provide access to
incremental resources and sustained gold production;
- Studies and
associated initiatives are progressing on schedule to be finalized
late 2024, with design to improve the current material handling
systems and to deliver mineralized material to the process plant at
lower cost;
- Initiatives to
capture synergies to yield benefits related to the supply of
principal consumable materials between the Bibiani and Chirano
mines are being advanced with an overall objective of saving
approximately $10 million per year;
- Other cost
saving and productivity improvement initiatives have advanced, with
results expected to be achieved later this year;
- Development of
Obra, Suraw and the lower Tano underground mines have been
accelerated facilitating earlier than planned underground mining at
the Obra mine which supplements plant feed and has improved the
grade from 1.2 g/t to 1.6 g/t for the year to date; and
- Exploration projects such as the
Suraw mine, Obra mine and open pit mining life extension projects
at the Sariehu/Mamnao area are progressing as planned to support a
robust mining program and extend the mining life.
For the fiscal year ending January 31, 2024, the
Company expects production of between 145,000 and 155,000 ounces of
gold at Chirano. With the execution of the foregoing initiatives,
the Company is projecting production of approximately 180,000
ounces of gold for the fiscal year ending January 31, 2025 at
all-in sustaining costs of approximately $1,250/oz. See footnote 2
below for assumptions.
Corporate and Financing
Update
The Company continues to focus on the execution
of its near-term growth plans and financing initiatives, including
discussions with potentially interested parties regarding strategic
alternatives. Any proposals, if received, will be reviewed by the
Company, in consultation with its financial and legal advisors. The
Company does not undertake any obligation to provide any updates
with respect to any proposals, except as required under applicable
law.
The Company is also pleased to report that Malik
Easah has accepted the role of Executive Chairman. Mr. Easah was
previously an Executive Director of the Company. Mr. Douglas
MacQuarrie has stepped down from the Non-Executive Chairman role
while remaining a non-executive Director of the Company. The Board
thanks Mr. MacQuarrie for his service.
The Company is also pleased to report that it
has entered into an agreement (the “Agreement”) with a strategic
financial institution (the “Purchaser”) for the forward sale of
gold which will provide US$40 million of financing to the Company
on a revolving basis over a two-year period. Under the
Agreement, a subsidiary of the Company will deliver 4,000 ounces of
refined gold per month to the Purchaser for 24 months, commencing
in October 2023.
As an advance deposit (the “Deposit”) towards
future gold deliveries, the Purchaser will pay the equivalent of
US$40 million in local currency to a subsidiary of the Company
shortly after execution of the Agreement. Deliveries will be
credited against the Deposit and funds will be re-advanced, at the
Company’s election, on each fifth monthly anniversary of execution
of the Agreement.
The Company continues to pursue other near-term,
non-dilutive financing initiatives to support capital investments
and working capital requirements.
Dave Anthony, President and CEO of Asante,
stated,
“It’s an exciting and busy time at Asante with
several near-term catalysts on the horizon, most notably the
completion of high-return capital projects that are expected to
transform the production and cost profile at both of our
operations. With the receipt of funding to backstop near-term
liquidity requirements and other near-term financing initiatives
well underway, we are confident in our ability to execute on our
business plans.
On behalf of the Management Team, I would also
like to thank Douglas MacQuarrie for his service to the Company as
Non-Executive Chairman of the Board for the past 18 months. We are
pleased that he has agreed to continue to serve as a Director of
the Company and that Malik Easah has agreed to assume the role of
Executive Chairman.”
Footnotes
- The current production guidance at
Bibiani as at September 2023 is derived from the current life of
mine operating plan on the basis of mineral reserves associated
with the property. Material factors and assumptions underlying the
production figures derived from the mine plan are a realized gold
price of US$1,802, gold recoveries of 91.5%, average cash costs of
US$929 per ounce, all in sustaining costs of US$1,397 per ounce,
all in costs of US$1,494 per ounce and exchange rates of
C$1/US$0.74, C$1/8.6 Ghanaian Cedi and US$1/11.5 Ghanaian
Cedi.
- The current production guidance at
Chirano as at September 2023 is derived from the current life of
mine operating plan on the basis of mineral reserves associated
with the property. Material factors and assumptions underlying the
production figures derived from the mine plan are a realized gold
price of US$1,800, gold recoveries of 91%, average cash costs of
US$1,165 per ounce, all in sustaining costs of US$1,246 per ounce,
all in costs of US$1,368 per ounce and exchange rates of
C$1/US$0.74, C$1/8.6 Ghanaian Cedi and US$1/11.5 Ghanaian
Cedi.
Qualified Person Statement
Scientific and technical information contained
in this news release has been reviewed and approved by Kwamina
Ackun-Wood, a member of the Australasian Institute of Mining and
Metallurgy, and the Exploration Manager for Mensin Gold Bibiani
Ltd. and by Daniel Apau, a member of the Australasian Institute of
Geoscientists, and the Exploration Manager for Chirano Gold Mines
Limited, and by Dave Anthony, P.Eng., Mining and Mineral
Processing, President and CEO of Asante, all of whom are “qualified
persons” under NI 43-101.
About Asante Gold
Corporation
Asante is a gold exploration, development and
operating company with a high-quality portfolio of projects and
mines in Ghana. Asante is currently operating the Bibiani and
Chirano Gold Mines and continues with detailed technical studies at
its Kubi Gold Project. All mines and exploration projects are
located on the prolific Bibiani and Ashanti Gold Belts. Asante has
an experienced and skilled team of mine finders, builders and
operators, with extensive experience in Ghana. The Company is
listed on the Canadian Securities Exchange, the Ghana Stock
Exchange and the Frankfurt Stock Exchange. Asante is also exploring
its Keyhole, Fahiakoba and Betenase projects for new discoveries,
all adjoining or along strike of major gold mines near the centre
of Ghana’s Golden Triangle. Additional information is available on
the Company’s website at www.asantegold.com.
About the Bibiani Gold Mine
Bibiani is an operating open pit gold mine
situated in the Western North Region of Ghana, with previous gold
production of more than 4.5 million ounces. It is fully permitted
with available mining and processing infrastructure on-site
consisting of a newly refurbished 3 million tonne per annum process
plant and existing mining infrastructure. Asante commenced mining
at Bibiani in late February 2022 with the first gold pour announced
on July 7, 2022. Commercial production was announced November 10,
2022.
For additional information relating to the
mineral resource and mineral reserve estimates for the Bibiani Gold
Mine, please refer to Asante’s press releases dated July 18, 2022
and September 1, 2022 and the technical report filed on its SEDAR
profile (www.sedarplus.ca) on September 1, 2022.
About the Chirano Gold Mine
Chirano is an operating open pit and underground
mine located in the Western Region of Ghana, immediately south of
the Company’s Bibiani Gold Mine. Chirano was first explored and
developed in 1996 and began production in October 2005. The mine
comprises the Akwaaba, Suraw, Akoti South, Akoti North, Akoti
Extended, Paboase, Tano, Obra South, Obra, Sariehu and Mamnao open
pits and the Akwaaba and Paboase underground mines.
For additional information relating to the
mineral resource and mineral reserve estimates for the Chirano Gold
Mine, please refer to Asante’s press releases dated October 15,
2022 and May 15, 2023 and the technical report filed on its SEDAR
profile (www.sedarplus.ca).
For further information please
contact:
Dave Anthony, President & CEOFrederick
Attakumah, Executive Vice President and Country Director
info@asantegold.com+1 604 661 9400 or +233 303
972 147
Cautionary Statement on Forward-Looking
Statements
Certain statements in this news release
constitute forward-looking statements, including but not limited
to, production and all-in sustaining costs forecasts for the
Bibiani and Chirano Gold Mines, estimated mineral resources,
reserves, exploration results and potential, development programs
and increases in mine-life, starter pit development and potential
synergies between Chirano and Bibiani. Forward-looking statements
involve risks, uncertainties and other factors that could cause
actual results, performance, prospects, and opportunities to differ
materially from those expressed or implied by such forward-looking
statements. Factors that could cause actual results to differ
materially from these forward-looking statements include, but are
not limited to, variations in the nature, quality and quantity of
any mineral deposits that may be located, the Company’s inability
to obtain any necessary permits, consents or authorizations
required for its planned activities, the Company’s inability to
raise the necessary capital or to be fully able to implement its
business strategies, and the price of gold. The reader is referred
to the Company’s public disclosure record which is available on
SEDAR (www.sedarplus.ca). Although the Company believes that the
assumptions and factors used in preparing the forward-looking
statements are reasonable, undue reliance should not be placed on
these statements, which only apply as of the date of this news
release, and no assurance can be given that such events will occur
in the disclosed time frames or at all. Except as required by
securities laws and the policies of the securities exchanges on
which the Company is listed, the Company disclaims any intention or
obligation to update or revise any forward-looking statement,
whether as a result of new information, future events or
otherwise.
Cautionary Note Regarding Non-GAAP
Financial Measures
Alternative performance measures in this news
release such as “AISC” are furnished to provide additional
information. These non-GAAP performance measures are included in
this news release because these statistics are used as key
performance measures that management uses to monitor and assess
performance of Bibiani and Chirano, and to plan and assess the
overall effectiveness and efficiency of mining operations. These
performance measures do not have a standard meaning within
International Financial Reporting Standards (“IFRS”) and,
therefore, amounts presented may not be comparable to similar data
presented by other mining companies. These performance measures
should not be considered in isolation as a substitute for measures
of performance in accordance with IFRS.
All-In Sustaining Cost (“AISC”) - AISC
includes cash costs and sustaining capital and exploration
expenses. The Company believes that this measure is useful to
external users in assessing operating performance and the Company’s
ability to generate free cash flow from current operations.
LEI Number: 529900F9PV1G9S5YD446. Neither IIROC
nor any stock exchange or other securities regulatory authority
accepts responsibility for the adequacy or accuracy of this
release.
Asante Gold (TG:1A9)
Historical Stock Chart
From Nov 2024 to Dec 2024
Asante Gold (TG:1A9)
Historical Stock Chart
From Dec 2023 to Dec 2024