TSX: SIL | NYSE American: SILV
VANCOUVER, BC, Sept. 14,
2022 /PRNewswire/ - SilverCrest Metals Inc.
("SilverCrest" or the "Company") is pleased to provide an update on
commissioning activities at the Company's Las Chispas Mine ("Las
Chispas" or the "Mine") located in Sonora, Mexico. All currency amounts herein
are presented in United States
Dollars, unless otherwise stated.
Highlights
- Processing plant metallurgical recovery and daily throughput
are trending ahead of Feasibility Study* ramp-up projections; For
August 2022, actual average recovery
of 96.2% gold ("Au") and 85.6% silver ("Ag"), or 90.7% silver
equivalent ("AgEq")** and average tonnage throughput of 784 tonnes
per day ("tpd") were achieved
- Project fully energized by grid power; reliability not at
steady state but expected to improve in Q4, 2022
- Underground in-vein and waste development continue to track
Feasibility Study projections, production stoping underway and
ramping up
- Underground mine ramping up to 600 to 700 tpd by end of 2022
compared to 750 tpd in the Feasibility Study; continued focus on
dilution and ore recovery
- First metal sale expected in Q3, 2022, commercial production on
schedule for Q4, 2022
- Community efforts advanced with key 2022 projects approaching
completion
- Well-funded ahead of first full year of production in 2023
- Updated Technical Report remains on schedule for H1, 2023
* NI 43-101
Technical Report & Feasibility Study on The Las Chispas
Project dated January 4, 2021 ("Feasibility Study")
|
** AgEq is based on the
2021 Feasibility Study Mineral Resource and Reserve gold to silver
ratio of 86.9:1 calculated using US$1,410/oz Au and US$16.60/oz
Ag
|
Pierre Beaudoin, COO, remarked,
"Starting up a new mining operation is a dynamic period, and our
team and contractors continue to navigate and address mostly
typical ramp-up issues. Overall, we are pleased with the
performance of the processing plant to date. Metal recoveries,
plant throughput and the availability of the plant itself have
generally tracked favorably when compared to the expectations
outlined in the Feasibility Study. The project continues to benefit
from the sizable surface stockpiles which have allowed the
underground operation to be ramped up at a measured pace."
N. Eric Fier, CPG, P.Eng, and
CEO, stated, "We are extremely proud of how our team and
contractors having navigated the construction process and
transition to commissioning, which remains on track at Las Chispas.
We remain focused on managing risk and are happy to have the
financial flexibility to address the challenges and opportunities
that will come our way".
Processing Plant and
Stockpile
During the first three months of commissioning, the Las Chispas
processing plant has performed in-line or ahead of the design curve
on all metrics. Throughput, recoveries, and plant availability have
all shown month over month improvements.
A total of 53,600 tonnes of material have been processed since
start-up with August 2022 average
throughput of 784 tpd, up 46% from July
2022 as shown in Figure 1. It is still expected that the
design plant throughput of 1,250 tpd will be reached in Q4, 2022.
Grades to the plant have remained low during the initial months of
processing as most ore continues to be intentionally sourced from
historic low-grade stockpiles.
Recoveries are tracking ahead of the planned ramp-up projections
as shown in Figure 2 with August 2022
recoveries averaging 96.2% Au and 85.6% Ag or 90.7% AgEq as
compared to the August 2022 ramp-up
projection of 81.5% AgEq.
Plant availability has continued to increase since the start of
commissioning (Figure 3), with availability in August 2022 of 81%, up from 65% in June 2022.
While the processing plant ramp-up has generally been trending
favorably when compared to the Feasibility Study ramp-up
projections, minor modifications have been required to the circuit
to address lower dissolved oxygen than planned. Temporary
modifications were implemented in late August 2022 and have addressed the initial
challenges encountered. The permanent modifications, while minor,
are more intrusive, and will be implemented during planned
down-time before the end of 2022.
Ore feed continues to be sourced primarily from the historic
lower grade stockpiles as the processing plant and underground
production continue to ramp-up. The stockpile at the end of
August 2022 is estimated at 300,000
tonnes and is comprised of the historic low-grade stockpile and
pre-production stockpiles which have been generated from mining,
since 2019. The stockpiles will continue to represent the bulk of
the processing plant feed in 2022, but underground ore will also be
used to start focused batch grade reconciliation with the process
plant.
As underground ore begins to be a source of processing plant
feed, the focus will be on determining the reconciliation of the
reserve mined grades to the processing plant. It is expected that
when the processing plant feed is sourced more consistently from
the underground, the results from these reconciliation efforts,
including grades, will be available in greater detail.
Plant grades and produced ounces will be announced with
quarterly production results in Q4, 2022.
Power
The construction of the 55 kilometre ("km") powerline managed by
SilverCrest was completed in Q2, 2022 and as of August 2022 was 100% operational inclusive of all
required supporting equipment (Harmonic Filters and Power Factor
Correctors). The Las Chispas operation is connected to the Comision
Federal de Electricidad ("CFE") grid but at a capacity limited to
6.4 MW via a temporary CFE bypass. This limited grid power
connection is adequate to support all major elements of the
operation, however, the stability has been below target which has
resulted in some minor production delays and disruptions. The final
connection (7.6 MW) to the refurbished CFE Power line (now at 80%
completion) is scheduled for Q4, 2022 and is expected to improve
the stability of the connection.
The temporary diesel deneration system has now been disconnected
and demobilized from Las Chispas. The processing plant and the Mine
are equipped with Emergency Diesel Power generation systems.
Underground Mining
In 2022, an additional 5.1 km of underground development has
been completed at the Mine, bringing the total to 22.6 km. In-vein
drifting represents 5.5 km of this total. A total of 109,000 tonnes
of ore have been mined from development and stoping activities in
2022 up to the end of August 2022,
approximately 9% below the Feasibility Study target.
The ramp up of underground stoping continues to progress. As
stated in the Feasibility Study, the focus during production
ramp-up is the refinement of mining methods and implementation of
grade control procedures. These procedures involve the collection
and use of detailed geological, geotechnical and operational data
to adjust mine plans and stope designs to minimize dilution and
maximize ore recovery.
The Company now anticipates ramping-up the underground mine to
between 600 and 700 tpd by the end of Q4, 2022, lower than the 750
tpd stated in the Feasibility Study.
Safety, COVID-19, and
Community
Safety has remained a top priority at Las Chispas. With the
commencement of production, our team has focused its attention on
the changing nature of the risks encountered in the stoping
processes and interaction with our main underground contractor.
COVID-19 prevention measures remain in place and there have been no
outbreaks that have impacted production efforts.
The Company is progressing work related to the potential impacts
of climate change for both Las Chispas and the local community. The
initial results for the physical risk assessment portion of the
work related to the Task Force for Climate Related Financial
Disclosures ("TCFD") are expected in Q4, 2022 along with a water
stewardship plan that will include and consider the findings of the
TCFD data. Work to address the risks and opportunities from
our findings has already begun.
Our community efforts have continued in earnest in 2022, with
the focus being execution of a multi-year major water
infrastructure project that is focused on improving the sewage
system and the water infrastructure for the local community and
ranching, and farming industries. This investment includes
upgrades to three main infrastructure areas which were considered
priorities in discussion with the local community. Further
details will be provided in the inaugural TCFD and water
stewardship report. These initiatives were in addition to the
completion of an assay lab built by SIlverCrest in Arizpe, a nearby community, to create a
long-term employment opportunity for the region.
Well-Funded Ahead of First Full
Year of Production in 2023
As of August 31, 2022, SilverCrest
had cash and cash equivalents of $101.6
million. Given the strong financial position, the Company
will not draw the remaining $30.0
million under its $120.0
million Credit Facility, and the availability of this amount
has now expired.
While production of silver and gold has been ongoing since first
pour on June 30, 2022, the first sale
and resulting revenue from the Mine is expected in Q3, 2022. As
projected in the Feasibility Study, it is expected that revenue
will be limited and operating costs elevated through the end of
2022 as the mine and processing plant are ramped up and the
processing plant is commissioned using lower grade material.
Updated Technical Report
SilverCrest continues to advance the work required to complete
the Updated Technical Report in H1, 2023. This report will
include additional infill and delineation drilling, further in-vein
drifting, initial months of stoping, processing data, and
reconciliation completed since the Feasibility Study. This report
will incorporate updated resources and reserves, updated
metallurgical results, reconciliation (mine, stockpile and plant)
including comparison to the 2021 Feasibility Study resource
estimate, a revised mine plan, and updated operating and sustaining
costs arising from any potential changes to the mine plan, the new
outsourcing regulations and the impact of inflation from the Q3,
2020 cost base used in the Feasibility Study.
2022 Exploration Update
Las Chispas exploration in 2022 has mainly continued to support
the transition to production through further infill and delineation
drilling of planned mining stopes and updated resource modelling.
Results of drilling completed to the end of July 2022 will be included in the planned Updated
Technical Report.
Picacho exploration in 2022 has continued with focus on
expansion and infill drilling of current areas for potential
resources. As of August 2022, one
surface drill rig was operating.
Exploration has also focused on mapping and sampling unexplored
areas around Las Chispas and Picacho to generate new drill targets.
Limited drilling has been completed outside of the known
mineralized zones, as SilverCrest remains focused on prudent
capital allocation during ramp-up.
The Qualified Person under National Instrument 43-101 Standards
of Disclosure for Mineral Projects for this news release is N.
Eric Fier, CPG, P.Eng, and CEO for
SilverCrest, who has reviewed and approved its contents.
ABOUT SILVERCREST METALS
INC.
SilverCrest is a Canadian precious metals exploration and
development company headquartered in Vancouver, BC, that is focused on new
discoveries, value-added acquisitions and near-term production in
Mexico's historic precious metal
districts. The Company's top priority is on the high-grade,
historic Las Chispas mining district in Sonora, Mexico, where it has completed
construction of its Las Chispas Mine and is proceeding with
commissioning. SilverCrest is the first company to successfully
drill-test the historic Las Chispas Property resulting in numerous
high-grade precious metal discoveries. The Company is led by a
proven management team in all aspects of the precious metal mining
sector, including taking projects through discovery, finance, on
time and on budget construction, and production.
FORWARD-LOOKING
STATEMENTS
This news release contains "forward-looking statements" and
"forward-looking information" (collectively "forward-looking
statements") within the meaning of applicable Canadian and
United States securities
legislation. These include, without limitation, statements with
respect to: the strategic plans, timing and expectations for the
Company receiving revenue in Q3, 2022, completing commissioning and
ramp up and achieving commercial production of the processing plant
in Q4, 2022, reaching 1,250 tpd throughput at the plant by end of
Q4, 2022, results of TCFD in Q4, 2022, ramp-up of u/g mine at a
rate of 600 tpd – 700 tpd by the end of Q4, 2022, final connection
of the power line in Q4, 2022, and completing a technical report
update by the end of H1, 2023 . Such forward looking statements or
information are based on a number of assumptions, which may prove
to be incorrect. Assumptions have been made regarding, among other
things: gold and silver prices, impact of the COVID-19 pandemic;
the reliability of mineralization estimates, mining and development
costs, the conditions in general economic and financial markets;
availability of skilled labour; timing and amount of expenditures
related to rehabilitation and drilling programs; and effects of
regulation by governmental agencies. The actual results could
differ materially from those anticipated in these forward-looking
statements as a result of risk factors including: uncertainty as to
the impact and duration of the COVID-19 pandemic; the timing and
content of work programs; results of exploration activities; the
interpretation of drilling results and other geological data;
receipt, maintenance and security of permits and mineral property
titles; environmental and other regulatory risks; project cost
overruns or unanticipated costs and expenses; fluctuations in gold
and silver prices and general market and industry conditions.
Forward-looking statements are based on the expectations and
opinions of the Company's management on the date the statements are
made. The assumptions used in the preparation of such statements,
although considered reasonable at the time of preparation, may
prove to be imprecise and, as such, readers are cautioned not to
place undue reliance on these forward-looking statements, which
speak only as of the date the statements were made. The Company
undertakes no obligation to update or revise any forward-looking
statements included in this news release if these beliefs,
estimates and opinions or other circumstances should change, except
as otherwise required by applicable law.
N. Eric Fier, CPG, P.Eng
Chief Executive
Officer
SilverCrest Metals Inc.
View original content to download
multimedia:https://www.prnewswire.com/news-releases/silvercrests-las-chispas-commissioning-on-track-nearing-first-metal-sale-301623928.html
SOURCE SilverCrest Metals Inc.