2 September 2024
88 Energy
Limited
Half-Year
Financial Report
88 Energy Limited (ASX:88E, AIM:88E,
OTC:EEENF) (88 Energy or the Company) is pleased to advise of the release of its financial results
for the half-year ending 30 June 2024.
A copy of the Company's Half-Year
Financial Report, extracts from which are set out below, has been
lodged on the ASX and is also available on the Company's website at
www.88energy.com .
Media and Investor Relations:
88
Energy Ltd
Ashley Gilbert, Managing
Director
|
|
Ashley Gilbert, Managing
Director
|
|
Tel: +61 (8)9485 0990
Email:investor-relations@88energy.com
|
|
|
|
Fivemark Partners, Investor and
Media Relations
|
|
Michael Vaughan
|
Tel: +61 (0)422 602 720
|
|
|
EurozHartleys Ltd
|
|
Dale Bryan
|
Tel: +61 (8)9268 2829
|
|
|
Cavendish Capital Markets
Limited
|
Tel: +44 (0)207 220 0500
|
Derrick Lee
|
Tel: +44 (0)131 220 6939
|
Pearl Kellie
|
Tel: +44 (0)131 220 9775
|
OPERATING AND FINANCIAL
REVIEW
During the period, the Group
continued its principal exploration and appraisal activities in
Alaska, complemented by a 75% owned, non-operated working interest
in onshore Texas Permian Basin production assets. The Group also
farmed-in and subsequently received transfer approval for a 20%
working interest in Petroleum Exploration Licence (PEL 93), Onshore
Namibia.
Project Phoenix
Project Phoenix is an oil-bearing
conventional reservoir play identified during the drilling and
logging of Icewine-1 and Hickory-1 and adjacent offset drilling and
testing. Project Phoenix is strategically located on the Dalton
Highway with the Trans-Alaskan Pipeline System (TAPS) bisecting the
acreage.
Hickory-1 Discovery Well
The Hickory-1 discovery well was
drilled in February 2023 and flow tested the following Alaskan
winter season in Q1/Q2 2024. The testing operations focussed on the
two shallower primary targets, the Slope Fan System (SFS) and Shelf
Margin Deltaic (SMD) reservoirs. Of the SFS series of reservoirs,
the Upper SFS (USFS) reservoir was targeted to be flow tested as it
had not been previously tested, whereas the Lower SFS has
previously been flow tested and therefore, the producibility of
that reservoir, confirmed on adjacent acreage. The USFS was
followed by a targeted testing of the SMD-B reservoir. Each zone
was independently isolated, stimulated and flowed to surface using
nitrogen lift to assist in an efficient clean-up of the
well.
Successful outcomes from the
Hickory-1 flow test delivered a platform for monetisation of
Project Phoenix, justifying further advancement, with key benefits
including:
· Potential capital-light modular Early Production
System;
· Production from horizontal wells typically produce 6-12 times
higher flow rates than vertical wells; and
· An
ability to produce concurrently from multiple reservoirs in a
single development scenario.
UPPER SFS Flow Test
Results
The USFS produced at a peak flow
rate of ~70 bopd. Oil cuts increased throughout the flow back
period as the well cleaned up, reaching a maximum of 15% oil cut.
The Company expects that oil rates and cut would have likely
increased further should the test period have been extended. The
well produced at an average oil flow rate of ~42 bopd during the
natural flow back period, with instantaneous rates ranging from
~10-77 bopd with average rates increasing through the test
period. Importantly, the USFS zone flowed oil to
surface under natural flow, with flow back from other reservoirs in
adjacent offset wells only producing under nitrogen assisted
lift.
Multiple oil samples were recovered
with measured oil gravities of between 39.9 to 41.4 API
(representing a light crude oil).
For full details in relation to the
USFS test results please refer to the ASX announcement dated 2
April 2024.
SMD-B Flow Test Results
The SMD-B produced at a peak flow
rate of ~50 bopd. Oil cuts varied throughout the flow back period,
reaching a maximum of 10% oil cut. The well produced at an average
oil cut of 4% following initial oil to surface, with instantaneous
rates observed during the 16-hour period as the well continued to
clean up. Unlike flow tests on adjacent acreage where multiple gas
lift mandrels and valves were used in completions designs, and
nitrogen was unloaded in the tubing in stages up the well bore,
Hickory-1 utilised a single gas lift mandrel where nitrogen was
introduced via one valve at the deepest section. This is viewed as
positive indication for future potential rates and
performance.
Multiple oil samples were recovered,
with measured oil gravities of between 38.5 to 39.5 API,
representing a light crude oil.
Importantly, the SMD-B zone flowed
oil to surface with little to no measurable gas, representing a low
GoR production rate.
For full details in relation to the
SMD-B test results please refer to the ASX announcement dated 15
April 2024.
Post-Flow Testing and Next
Steps
Pressurised oil samples collected
during both the USFS and SMD tests were transported to laboratories
for further analysis. The analyses are expected to verify the
reservoir fluid characteristics.
Following completion of the lab
analyses, 88 Energy will commission an Independent Contingent
Resource assessment for the Upper SFS, Lower SFS and SMD-B. This
assessment is expected to be completed in Q4 2024.
Results from the post-flow test
analyses will assist 88 Energy in the optimisation and design of
the next phase of advancement at Project Phoenix. The Company,
together with its Project Phoenix Joint Venture partner, are
currently assessing locations for the drilling of a horizontal
well, including the Franklin Bluffs gravel pad location (previously
utilised for the Icewine 1 and 2 unconventional test wells), where
a long-term flow test of either the SFS or SMD reservoirs may be
undertaken.
Table below is an indicative
timeline for Project Phoenix development
Project Leonis [100% WI]
In June 2024, the Company reported a
maiden internal Prospective Resource net mean estimate of 381
million barrels (MMbbls) of recoverable oil in the newly named Tiri
Prospect (Upper Schrader Bluff (USB) Formation) for Project Leonis.
(Unrisked net 3U (high) of 671 MMbbls, 2U (best) of 338 MMbbls and
1U (low) of 167 MMbbls.1,2
The initial Prospective Resource
estimate followed a review period of an extensive data suite that
included 3D and 2D seismic data, well logs from Hemi Springs Unit-3
and Hailstorm-1, as well as nearby wells adjacent to the Project
Leonis acreage, along with extensive petrophysical analysis and
mapping.
Importantly, the USB formation is
the same proven producing zone as nearby Polaris, Orion and West
Sak oil fields to the north-west as shown on Figure 2.
These proven USB producers served as
important calibration points for the Leonis petrophysical model.
The Leonis USB prospect has been fully delineated and mapped
following a review of reprocessed 3D seismic data and a 3rd party
dedicated fault mapping study to assist in prospect
definition.
Forward Program
88 Energy has engaged Hickory-1
project Management Company, Fairweather LLC, to assist in planning
and permitting for the newly named Tiri-1 exploration well. The
well will be designed to drill, log and test the Tiri Prospect in
the USB formation. The company intends to utilise the existing
gravel pad at the Hemi Springs Unit-3 well shown in Figure 3, to
reduce costs.
Timing for the drilling of the
Tiri-1 exploration well is dependent on securing a successful
farm-out partner and the Company has secured Stellar Energy
Advisors Limited (Stellar) in London to manage the farm-out
process, who have been engaged with multiple parties in advancing
the assessment of the farm-out opportunity. The process is
ongoing.
Namibia PEL 93 (20% WI)
In November 2023 88 Energy, via its
wholly-owned Namibian subsidiary, executed a three-stage farm-in
agreement (FOA) for up to a 45% non-operated working interest in
the onshore Petroleum Exploration Licence (PEL 93) covering
18,500km2 of underexplored acreage within the Owambo Basin in
Namibia.
In February 2024, the Company
announced the successful 20% working interest (WI) transfer by
operator Monitor Exploration Limited (Monitor) to 88 Energy as part
of Stage 1 of the FOA; this transfer has been approved by the
Namibian Ministry of Mines and Energy. Monitor now holds a 55% WI
with the remaining 25% shared across local entities, Legend Oil
Namibia Pty Ltd and NAMCOR. The current and potential future PEL 93
Joint Venture partners and working interests are as
follows:
Entity
|
Pre
Farm-in
|
Stage 1 -
Current
(Past
costs & 2D)
|
Stage
2
(1st Well)
|
Stage
3
(2nd Well)
|
Monitor
|
75.0%
|
55.0%
|
37.5%
|
30.0%
|
Legend
|
15.0%
|
15.0%
|
15.0%
|
15.0%
|
NAMCOR
|
10.0%
|
10.0%
|
10.0%
|
10.0%
|
88
Energy
|
-
|
20.0%
|
37.5%
|
45.0%
|
Stage 1 schedule to earn a 20%
working interest in the Licence is complete and
comprises:
· 1st
instalment: US$0.28 million paid in cash on signing for partial
payment of back costs;
· 2nd
instalment: US$1.25 million paid in 88 Energy shares on signing for
part payment of 2D seismic carry;
· 3rd
instalment: US$1.25 million paid in 88 Energy shares upon approval
of PEL 93 WI transfer by the Namibian government, as final payment
in relation to the 2D seismic carry; and
· 4th
Instalment: US$0.9 million paid in 88 Energy shares for final back
costs payment and 2024 work-program carry.
Namibia has been identified as one
of the last remaining under-explored onshore frontier basins and
one of the World's most prospective new exploration zones. PEL 93
is more than 10 times larger than 88 Energy's Alaskan portfolio and
more than 70 times larger than Project Phoenix.
Recent drilling results on nearby
acreage has highlighted the potential of a new and underexplored
conventional oil and gas play in the Damara Fold belt, referred to
as the Damara Play. It is currently the subject of exploration
drilling by ReconAfrica in their nearby PEL 73 block. Historical
assessment utilised a combination of techniques and interpretation
of legacy data to identify the Owambo Basin, as having significant
exploration potential. Monitor utilised a range of geophysical and
geochemical techniques to assess and validate the significant
potential of the acreage since award of PEL 93 in 2018, identifying
ten (10) independent structural closures from airborne geophysical
methods and partly verified these using existing 2D seismic
coverage.
In May 2024, the Company announced
that Polaris Natural Resources Development Ltd (Polaris) was
awarded, the 2D seismic acquisition program contract. Polaris
mobilised vibroseis units and recording equipment to location in
late June 2024 and the program was completed in July 2024. The
fully funded 2D Seismic acquisition program acquired ~200-line km
of 2D data with data processing now underway and anticipated to be
finalised in Q4 2024.
Results of the new 2D seismic
acquisition will be integrated with existing historical exploration
data to refine current prospect interpretation. Anticipated
outcomes include:
· Validate up to 10 independent structural closures
· Maiden
certified prospective resource estimate
· Identification of future potential drilling locations
targeting the Damara play
Project Longhorn (~65%
WI)
The joint venture (Bighorn JV),
which comprises Longhorn Energy Investments LLC a 100% wholly owned
subsidiary of 88 Energy with 75% ownership and Lonestar I, LLC
(Lonestar or Operator) with the remaining 25% ownership, agreed to
a development program that included five workovers in 1H
2024.
During the quarter, the Bighorn JV
successfully executed four of the planned five workovers within
Budget with results below:
· First
workover production commenced in mid-April;
· Second
and third workovers commenced production in mid-May;
· Fourth
workover production began in the final week of June 2024;
and
· The
final workover encountered a tubing fish not recorded in the well
file. The operator tried several tools but could only clean out 75
feet of the anticipated 1,500 feet of the tubing fish recovered.
The Bighorn JV decided to suspend operations and P&A the
workover with sunk CAPEX capped at A$0.5M compared to a budget of
A$1.2M.
Completion of the workovers
increased gross production from 328 BOE per day (average Q1 2024)
to 395 BOE per day (average Q2 2024) with production for June
averaging 456 BOE per day (~63% oil). The production volume
declines of the four successfully completed workovers are currently
lower than initially forecast.
Project Longhorn continued to
provide strong cash flows towards lease and corporate costs with
the Company receiving cash flow distributions of A$1.2M during H1
2024, post-workover expenditure.
Prior to commencement of the 2024
capital development program, the Bighorn JV executed a a ~10%
sell-down (gross, ~7% net to 88 Energy) of the 2023 acquired
acreage, in order to re-disk and accelerate development
opportunities. The transaction realised net to 88E, acquisition
payments of ~A$0.3M and the non-operated partners contributed their
share of the five workover capital development costs coupled with a
25% carry of their ownership share of the five workovers. For full
details refer to page 6-7 the Q1 2024 Quarterly ASX announcement on
18 April 2024 including reserves update and cautionary
statement.
Focused Alaskan Strategy
In Alaska, 88 Energy has a strategic
focus on infrastructure-led opportunities which benefit from
proximity to services at Prudhoe Bay, the Trans-Alaskan Pipeline
System (TAPS) and other key infrastructure. 88 Energy is focused on
advancing Project Phoenix and Project Leonis. Following Hickory-1
successfully flowing light oil to surface, the Company is aiming to
drill horizontal production wells and generate cash flow within the
next 24 months from Project Phoenix as well as unlocking Project
Leonis' potential through an appraisal well program.
Following proposed new regulations
governing the management of surface resources in the National
Petroleum Reserve-A, 88 Energy successfully requested from the
Bureau of Land Management Alaska initial 12-month suspensions for
Project Peregrine to December 2024 and the Umiat Unit to 30 June
2025. The suspensions allow 88 Energy to benefit from a reduction
in lease costs and to focus its efforts on unlocking value from its
key strategic acreage positions - these are adjacent to
infrastructure that should accelerate commercialisation of the
projects.
Acreage that was deemed non-core to
88 Energy was relinquished during 1H 2024, including all of Icewine
East (~23k acres/16 blocks) due to geographical challenges
near/over the SAG river, lack of prospectivity and an 8-year
primary term that expired on 31 May 2024 without being unitised.
Additionally, 36 blocks at Icewine West covering ~51k acres with
it's 8-year primary term also expiring in May 2024 were
relinquished. The Company has reviewed the remaining Icewine West
acreage and although it noted prospectivity across a group of
leases including Charlie-1, a combination of the Company's focus
being on assets that are adjacent to infrastructure, and the annual
'holding' rental costs of acreage means there are no immediate
plans for further drilling at Icewine West. 88 Energy has requested
relinquishment of the remaining Icewine West acreage from the
Department of Natural Resources and approvals are expected in Q3
2024.
Corporate
Placement
On 24 April 2024, the Company
successfully completed an oversubscribed share placement to
domestic and international institutional and sophisticated
investors to raise gross A$9.7 million (approx. £5.17 million)
before costs (the Placement). 3,231,974,839 new fully paid ordinary
shares in the Company (the New Ordinary Shares) were issued at an
issue price of A$0.003 (£0.0016) per New Ordinary Share (the Issue
Price). The net proceeds augmented the Company's existing cash
balance to fund:
· Hickory-1 discovery well flow test operations at Project
Phoenix, post-well studies, securing a contingent resource estimate
for the SFS and SMD reservoirs and other costs associated with
commercialising Project Phoenix;
· Exploration activities including lease rentals across Alaskan
and Namibian acreage;
· Permit and planning costs for Tiri-1 exploration well at
Project Leonis; and
· Securing farmout partners to advance projects at Project
Phoenix and Project Leonis.
Euroz Hartleys Limited (Euroz
Hartleys) acted as Sole Lead Manager and Bookrunner to the
Placement. Cavendish Capital Markets Ltd (Cavendish) acted as
Nominated Adviser and Sole Broker to the Placement in the United
Kingdom. Inyati Capital Pty Ltd (Inyati) acted as Co-Manager to the
Placement. Commission for the Placement was 6% (plus GST) of total
funds raised across Euroz Hartleys, Inyati and Cavendish. In
addition, and subject to shareholder approval, the Company will
issue a total of 75,000,000 Unlisted Options (exercisable at
A$0.0055 on or before the date which is 3 years from the date of
issue) to Euroz Hartleys, Cavendish and Inyati.
The New Ordinary Shares were issued
under the Company's available placement capacity pursuant to
Listing Rule 7.1 and are not subject to shareholder approval. The
Ordinary Shares ranked pari passu with the existing ordinary shares
in the Company and the Ordinary Shares were admitted to trading on
AIM.
PEL 93 - Farm-In
Following approval by the Namibian
Ministry of Mines and Energy of the 20% working interest transfer
by Monitor to 88 Energy in relation to PEL 93, under the farm-in
agreement, the Stage 1, third instalment payment of US$1.25 million
was paid by issuing 397,947,229 new ordinary shares in the Company
to Monitor at an issue price of A$0.0048 per share on 22 February
2024.
Monitor also agreed to receive 88
Energy shares as settlement for the fourth and final Stage 1
instalment of the farm-in agreement, as announced to the ASX on 13
November 2023. This instalment covers the final back costs and the
2024 work program carry of US$0.92 million through the issuance of
476,634,546 new ordinary 88 Energy Shares at an issue price
of A$0.003 per share on 24 April 2024.
General Meetings
The Company held a General Meeting
on 15 January 2024 and all eleven (11) resolutions were
passed.
The Company held its Annual General
Meeting on 13 May 2024 and all six (6) resolutions were
carried.
Events after the period
Other than as disclosed below, there
were no significant events occurring after balance date requiring
disclosure.
Project Phoenix
Burgundy Xploration, LLC (Burgundy)
met its 2023 financial obligations and signed the Hickory-1 flow
test Authority For Expenditure (AFE) on 15 February 2024. Under a
standstill agreement executed in December 2023 with 88E's
subsidiary, Accumulate Energy Alaska, Inc (88E-Accumulate),
Burgundy was due to pay its share of the AFE cost (approximately
US$3 million) by no later than 15 August 2024, through either a
public listing or a private capital raise. If the obligation
remained unpaid, Burgundy was to transfer 50% of its working
interest in the Toolik River Unit leases to
88E-Accumulate.
As announced on 19 August 2024 on
the ASX, 88E understands that Burgundy's plans for a public listing
are progressing well including the recent recruitment of a board
and senior oil and gas executive with significant public company
(AIM, TSX, and US markets) experience and success to facilitate the
company's potential public listing. After an extensive internal and
third-party review of the latest Project Phoenix data by Burgundy,
advanced discussions are underway in relation to a potential
transaction whereby Burgundy would provide a carry to 88E across an
anticipated 2025/26 work program to include (but not be limited to)
the drilling, completion and extended flow testing of a horizontal
well on the Dalton Highway in return for additional working
interest in the Project. Any carry would be subject to Burgundy
raising the capital required. Accordingly, at this stage
there is no guarantee that a transaction with Burgundy will be
completed.
Given the deadline on the previous
December 2023 standstill agreement, Burgundy has committed to a
payment of US$0.35 million in the near term in return for the
Company extending the December 2023 standstill agreement for
outstanding Flow Test AFE costs until December 31, 2024.
Given this commitment, Burgundy's intentions to proceed with a
listing public listing, as well as the ongoing negotiations with
the Company for a horizontal well carry, 88E has agreed to a
further extension of the standstill arrangement.
Should Burgundy fail to meet its
obligations by the revised deadline, the Company retains its rights
under the joint operating agreement to enforce its terms if
necessary.
Umiat Unit
88 Energy was successful in
receiving a suspension for Project Peregrine on 1 December 2023 for
an initial period of 12 months due to the proposed new regulations
governing the management of surface resources in the National
Petroleum Reserve-A (NPR-A). On 25 June 2024, the Company applied
for suspension to Umiat Unit and leases on the same basis as
Project Peregrine suspension, requesting an initial 1-year
suspension that will be reviewed as required. On 31 July 2024
The Bureau of Land Management Alaska approved a 12-month suspension
of the Umiat Unit and leases from 1 July 2024 to 30 June
2025.
During the suspension period, 88
Energy will continue the refinement of internal geological and
geophysical models/interpretations. The suspension will relieve 88
Energy of the obligation to pay lease rentals during the suspension
period of ~A$0.1 million due in Q4.