TORONTO, Aug. 23, 2011 /CNW/ -- TORONTO, Aug. 23, 2011 /CNW/ -
Noront Resources Ltd. ("Noront" or the "Company") (TSX Venture:
NOT) is pleased to announce the results of an updated National
Instrument 43-101 - Standards of Disclosure for Mineral Projects
("NI 43-101") compliant Pre-Feasibility Study ("PFS") for a stand
alone nickel, copper, platinum group element ("Ni-Cu-PGE") mine and
mill complex exploiting the Company's 100% owned Eagle's Nest
deposit (the "Project"), McFaulds Lake, James Bay Lowlands,
Ontario, effective August 23, 2011. The results of the independent
study, completed by Independent Consultants(1) under the
supervision of Micon International ("Micon"), concluded that the
previously defined Eagle's Nest mineral resource is economic and
can be classified as a mineral reserve. PRE-FEASIBILITY STUDY
HIGHLIGHTS: The Project economics, based on the Assumed Metal
Prices(2) are: -- Proven and probable mineral reserves of 11.1 M
tonnes averaging: o 1.68% Ni, 0.87% Cu, 0.89 g/t Pt, 3.09 g/t Pd
and 0.18 g/t Au; -- After tax NPV at a 6.0% discount factor of
approximately $560 million; -- After tax IRR exceeding 20%; --
Estimated initial capital investment of $734 million split as
follows: o Mine site infrastructure and development capital of $500
million o Shared infrastructure and slurry pipeline capital of $234
million (1) -- Estimated life of mine sustaining capital estimated
to be $143 million; -- Estimated operating costs of $75 - $80 per
tonne or $2.75 per pound nickel equivalent; -- Estimated free cash
flow of approximately $175 million per year; -- Estimated mine life
of 11 years with a 3 year capital payback period. Wes Hanson, CEO
of Noront states: "Establishing the first mineral reserve in this
evolving mining camp is a milestone development that we believe
will accelerate meaningful discussion on the infrastructure
necessary to support development of this very exciting district. It
positions the Company to begin negotiating downstream agreements
that will provide future funding for continued development of the
Project without excessive shareholder dilution. The estimated
capital and operating costs compare very favourably to other
advanced nickel projects being considered for development." Mr.
Hanson adds: "With established inferred resources at depth offering
immediate economic upside, robust exploration potential within our
existing land package, the continuing challenges facing nickel
laterite projects and the strong projected growth in stainless
steel production, Noront represents a compelling investment
opportunity as we continue the transition to nickel producer. We
are targeting the first quarter of 2012 to have a completed
Feasibility Study for Eagle's Nest that will allow the Company to
begin arranging project financing with the objective of commercial
production by 2016." MINERAL RESERVES AND RESOURCES FOR
EAGLE'S NEST DEPOSIT: The following table summarizes the estimated
mineral reserves and resources. tonnes Nickel Copper Platinum
Palladium Gold (x (%) (%) (g/tonne) 1,000) (g/tonne) (g/tonne)
Mineral Reserves Proven 5,264 2.02 1.04 1.01 3.45 0.19 Probable
5,867 1.38 0.72 0.78 2.76 0.18 Proven and 11,131 1.68 0.87 0.89
3.09 0.18 Probable Mineral Resources (exclusive of Mineral
Reserves) Inferred 8,966 1.10 1.14 1.16 3.49 0.30 OVERVIEW:
The objectives of the PFS were: -- To establish the economics of
the Eagle's Nest deposit on a stand-alone basis; -- To confirm the
economics of the October 2010 Preliminary Assessment on Eagle's
Nest (the "PA"); and -- To address the technical and environmental
challenges of developing a mine in the McFaulds Lake region. The
PFS was based on recent metallurgical test work, revised mine
design, updated field work and review of site conditions. Based on
the revised design criteria and updated field work, the mine,
process and infrastructure designs were advanced to a level
sufficient to allow Micon to develop capital and operating cost
estimates for the Project. PROJECT DESCRIPTION: The Project, as
defined in the PFS, is summarized as: -- 1.0 million tonne per year
throughput rate; -- Metallurgical recoveries based on recent test
work; -- 9.0 million tonnes of inferred resource was not included
in the mineral reserve; -- Underground mining of the Eagle's Nest
deposit; -- All major mining facilities (including the mill) would
be located underground; -- All tailings would be stored underground
as cemented fill; -- The existing winter road from Pickle Lake to
Webequie would be upgraded to an all-season road; -- A diesel power
plant would be located near Webequie and a transmission line would
provide power to the mine site; -- A slurry pipeline would be used
to transport concentrate from site to a filter plant located near
Webequie; -- Initial mine production would be from an internal
ramp; and -- Production ramps will be developed after year three to
access the lower levels of the deposit. As previously assumed in
the PA, common mine infrastructure including the all-season road,
power lines, and construction winter roads would benefit other
companies and the local communities. The PFS economic analysis
assumes that 25% of the cost of the all season road, 50% of the
power line cost and 50% of the winter road cost are included in the
capital cost of the Project. Micon also completed an economic
analysis that confirmed that the Project can support 100% of the
related infrastructure costs. Under this scenario, the Project
demonstrated an after-tax NPV of $494 million (6% discount factor)
and an after tax IRR of 19.2%. The proposed Project minimizes
surface disturbance and the Company's environmental footprint.
Aggregate will be sourced from waste rock mined underground during
mine development. The submerged slurry pipeline and power
transmission line will greatly reduce traffic between Webequie and
the Project site, eliminating the need for all season road access.
The Company believes that all construction materials can be
transported to site utilizing a winter road network and critical
spares can continue to be transported by air. The cost estimate
includes operating costs to operate the mine and process plant,
selling of a bulk concentrate, environmental monitoring and
management of the proposed operation. Closure costs are included in
the cash flow analysis. Of the estimated operating cost of $75-$80
per tonne approximately 42% was attributed to underground mining,
approximately 42% attributed to on-site processing (including power
costs) and 16% related to general and administrative ("G&A").
Mine production was estimated based on a mining recovery rate of
95% of the measured and indicated resource defined in Micon's
technical report titled "Technical Report on the Updated Mineral
Resource Estimate, McFaulds Lake Project, James Bay Lowlands,
Ontario, Canada" (effective March 4. 2011). Mining dilution of 5%
at zero grade was included in the estimation of proven and probable
reserves. Metallurgical recoveries were based on recent test work,
as described in the Company's press release dated July 7, 2011. The
PFS did not include the 9.0 million tonnes of inferred resources
that have been identified at depth at Eagle's Nest. These inferred
resources represent a significant opportunity to increase the
project life and improve the economics, potential that would be
unlocked through an underground diamond drill program at a later
date. OPERATIONS UPDATE The Company is currently completing its
planned drill program targeting resource growth at the Blackbird
chromite discovery. Approximately 80% of the planned 12,000 metre
program has been completed to date. Two drills continue to
operate at Blackbird with the objective of significantly increasing
the global resource. Assay results form this drill program are
pending. The Company continues to prioritize targets proximal to
the Eagle's Nest discovery with the intent of initiating a follow
up drill campaign to test the most promising targets once drilling
of the Blackbird chromite deposit is completed. The Company is
actively engaged in the public consultation process, sponsoring a
series of meetings at various First Nations communities in the Ring
of Fire area to review and discuss the Company's Project
Description. The Company maintains a strong cash position and has
sufficient funding in place to complete the work planned for the
fiscal year currently underway. FUTURE TECHNICAL STUDIES The next
phase of the Project will include finalizing the design concepts
and the project execution plan and producing a final feasibility
study sufficient to support debt financing for the Project. The
main items to address include: -- Incorporate comments from the
project review and consultation program; -- Negotiate Impact
Benefit Agreements ("IBA") with the various stakeholders; --
Complete metallurgical test work including variability analysis; --
Incorporate design into an Environmental Assessment report; --
Conduct various trade-off studies on: o Slurry pipeline design and
costs; o Road construction design and costs; and o Establishing
grid power into site. -- Establish business and out-sourcing
opportunities based on the IBA discussions; -- Develop financing
plan for shared infrastructure which will include First Nation
communities, Provincial and Federal governments; and -- Develop
project financing plan for the mining project. The NI 43-101
compliant PFS will be available on SEDAR and on the Company's
website within 45 days from the date hereof. INDEPENDENT QUALITY
CONTROL AND ANALYTICAL PROTOCOL A thorough quality control program
has been in effect for the McFaulds Lake Project, which includes
grouping samples into batches of 35 into which are added 2
certified reference material standards. 2 field and pulp duplicates
also form part of the quality control program. It can be said with
confidence that all assays have passed the strict quality control
guidelines established by Noront's Qualified Person. Activation
Labs ("Actlabs)" of Ancaster, Ontario completed all the assaying
work. The samples submitted to Actlabs were analyzed for
multi-elements, including Ni and Cu using a four acid digestion and
by ICP analysis. The samples that received base metal values
greater than the upper limit for the method underwent further
analysis using ICP-OES. For the Au, Pd and Pt, the assay
methodology was Fire Assay on a 30 gram aliquot with an ICP
finish. Silver was analyzed using a 3-acid digest with an ICP
analysis. For more information on assay methodology please
visit the Actlabs website at http://www.actlabsint.com. For further
information on quality control and quality assurance and data
verification procedures please reference the Company's NI 43-101
compliant technical report "Technical Report on the Updated Mineral
Resource Estimate, McFaulds Lake Project, James Bay Lowlands,
Ontario, Canada" (effective March 4. 2011) available on the
Company's website and at www.sedar.com. The preparation of this
press release has been supervised by Noront's senior management
including Mr. W. Hanson, P.Geo., President and CEO and Mr. R.
Gowans, P.Eng., Micon's Project Manager, both of whom are Qualified
Persons under Canadian Securities Administrators guidelines. Note 1
Independent Consultants The PFS was completed by Micon and included
technical input from SNC Lavalin, Cementation Ltd., Knight Piesold,
Penguin ASI and Golder Associates. The PFS was based on the
proposed mining and processing of the Eagle's Nest resource
previously defined by Micon in a NI 43-101 compliant technical
report entitled. "Technical Report and Updated Mineral Resource
Estimate For The Eagle's Nest Property", dated effective March 4,
2011 (the "Eagle's Nest Resource Estimate"). For further
information on Eagle's Nest, please refer to the Eagle's Nest
Resource Estimate which is available on the Company's website and
SEDAR. Note 2 Metal Price Assumptions: The PFS economic analysis is
based on the following metal prices derived on a three year
trailing average basis: Nickel $8.62 per pound Copper $3.08 per
pound Platinum $1,432 per ounce Palladium $ 446 per ounce Gold
$1,130 per ounce The PFS assumes a Canadian to US foreign exchange
rate of 1.073. About Noront: Noront Resources Ltd. is focused
on its significant and multiple, high-grade
nickel-copper-platinum-palladium, chromite, gold and vanadium
discoveries in an area known as the "Ring of Fire", an emerging
multi-metals district located in the James Bay Lowlands of Ontario,
Canada. Noront is the dominant land holder at the Ring of Fire and
continues to delineate and prove up its discoveries with NI 43-101
technical and economic reports and an aggressive and well financed
drill plan for 2010. All material information on Noront can be
found on the Company's website at www.norontresources.com or at
SEDAR at www.sedar.com Wesley (Wes) Hanson President & Chief
Executive Officer FORWARD LOOKING STATEMENTS This release contains
"forward-looking statements" within the meaning of applicable
Canadian securities legislation, including predictions, projections
and forecasts. Forward-looking statements include, but are
not limited to, statements that address activities, events or
developments that the Company expects or anticipates will or may
occur in the future, including such things as future business
strategy, competitive strengths, goals, expansion, growth of the
Company's businesses, operations, plans and with respect to
exploration results, the timing and success of exploration
activities generally, permitting time lines, government regulation
of exploration and mining operations, environmental risks, title
disputes or claims, limitations on insurance coverage, timing and
possible outcome of any pending litigation and timing and results
of future resource estimates or future economic studies. Often, but
not always, forward-looking statements can be identified by the use
of words such as "plans", "planning", "planned", "expects" or
"looking forward", "does not expect", "continues", "scheduled",
"estimates", "forecasts", "intends", "potential", "anticipates",
"does not anticipate", or "belief", or describes a "goal", or
variation of such words and phrases or state that certain actions,
events or results "may", "could", "would", "might" or "will" be
taken, occur or be achieved. Forward-looking statements are
based on a number of material factors and assumptions, including,
the result of drilling and exploration activities, that contracted
parties provide goods and/or services on the agreed timeframes,
that equipment necessary for exploration is available as scheduled
and does not incur unforeseen break downs, that no labour shortages
or delays are incurred, that plant and equipment function as
specified, that no unusual geological or technical problems occur,
and that laboratory and other related services are available and
perform as contracted. Forward-looking statements involve
known and unknown risks, future events, conditions, uncertainties
and other factors which may cause the actual results, performance
or achievements to be materially different from any future results,
prediction, projection, forecast, performance or achievements
expressed or implied by the forward-looking statements. Such
factors include, among others, the interpretation and actual
results of current exploration activities; changes in project
parameters as plans continue to be refined; future prices of gold;
possible variations in grade or recovery rates; failure of
equipment or processes to operate as anticipated; the failure of
contracted parties to perform; labour disputes and other risks of
the mining industry; delays in obtaining governmental approvals or
financing or in the completion of exploration, as well as those
factors disclosed in the Company's publicly filed documents.
Although Noront has attempted to identify important factors that
could cause actual actions, events or results to differ materially
from those described in forward-looking statements, there may be
other factors that cause actions, events or results not to be as
anticipated, estimated or intended. There can be no assurance that
forward-looking statements will prove to be accurate, as actual
results and future events could differ materially from those
anticipated in such statements. Accordingly, readers should not
place undue reliance on forward-looking statements. Neither TSX
Venture Exchange nor its Regulation Services Provider (as that term
is defined in the policies of the TSX Venture Exchange) accepts
responsibility for the adequacy or accuracy of this release. To
view this news release in HTML formatting, please use the following
URL:
http://www.newswire.ca/en/releases/archive/August2011/23/c5698.html
p Wes Hanson, President and CEO at (416) 367-1444, or visit
Noront's website at: a
href="http://www.norontresources.com"http://www.norontresources.com/a.
/p
Copyright
Noront Resources (TSXV:NOT)
Historical Stock Chart
From Oct 2024 to Nov 2024
Noront Resources (TSXV:NOT)
Historical Stock Chart
From Nov 2023 to Nov 2024