Turquoise Hill Resources Ltd. (“Turquoise Hill” or the
“Company”) today announced first quarter 2022 production and
provided an Oyu Tolgoi LLC (“Oyu Tolgoi” or “OT”) mine and
corporate update.
Q1 2022 Highlights
- As planned, Q1 2022 copper and gold production from the open
pit and underground was lower vs Q1 2021 due to lower copper and
gold head grade.
- Copper production of 30.3 thousand tonnes of copper in
concentrate, a decrease of 33% vs Q1 2021 and a decrease of 22% vs
Q4 2021
- Gold production of 59 thousand ounces of gold in concentrate, a
decrease of 60% vs Q1 2021 and a decrease of 25% vs Q4 2021
- Copper production guidance for 2022 remains within the range of
110,000 to 150,000 tonnes. Gold production guidance has been
revised from a range of 115,000 – 165,000 ounces to 135,000 –
165,000 ounces and is trending toward the higher end of the
range.
- Expenditures on property, plant and equipment for 2022 are now
expected to be approximately $155 million to $185 million for
open-pit operations due to schedule changes impacting the timing of
spend. This is compared to the Company’s original guidance of $170
million to $200 million.
- Mill throughput of 9.58 million tonnes in Q1 2022 was 9% lower
than Q4 2021 and 2% lower than Q1 2021 in line with expectations
due to planned maintenance.
COVID-19
Safety continues to be the Company’s top priority and controls
remain in place at site to protect our people.
During Q1 2022, COVID-19 cases identified at Oyu Tolgoi have
trended downward. Consequently, onsite workforce numbers over the
quarter increased to approximately 90% of plan with mobilisation of
personnel across multiple work-fronts. COVID-19 related
restrictions for international arrivals to Mongolia have been
lifted.
The total cumulative increase to the Definitive Estimate
underground development capital cost due to the impacts of COVID-19
through the end of Q1 2022 increased by $20 million to $195
million. This increase includes the currently known, incremental,
time-related costs of COVID-19 restrictions. The underground mine
cost and schedule review and update is underway and is still
expected to be completed in Q2 2022.
Open Pit Operations and Underground Development
During Q1 2022, the combined open pit and underground operations
produced 30.3 thousand tonnes of copper in concentrate and 59
thousand ounces of gold in concentrate. This was a planned
reduction from Q4 2021 due to lower throughput and a reduction in
both copper and gold head grades.
The mill feed for Q1 2022 included approximately 262 thousand
tonnes @ 0.52% Cu and 0.25g/t Au of underground development
material. The remaining 9.32 million tonnes of mill feed was
sourced from open pit low grade stockpiles and supplemented with
higher grade material from Phase 4B and Phase 5. Mining in Phase 4B
was completed in March 2022. Mill head grades will remain low
through to the end of the year as mined material direct mill feed
will continue to be supplemented by low grade stockpiles.
As previously disclosed, the open pit optimisation opportunities
to reduce the impact of the previously forecast metal deferral are
improving in definition. Related work is still expected to be
incorporated into an updated mine plan in Q3 2022.
During Q1 2022, the underground project achieved several
significant milestones including the commencement of the undercut
and commissioning of both the Material Handling System 1 and the
first on-footprint truck chute. Despite the commencement of the
undercut a month later than expected, the timing of first drawbell
remains aligned with the previously disclosed timing in Q3 2022.
Undercut blasting and on footprint construction work, including
roadways and steel set construction, continues to progress well
ahead of the first drawbell blast. Infrastructure to support
production ramp up also progressed during the quarter, including
completion of the conveyor to surface decline mining and transfer
chamber mass excavation. Shaft 3 headframe was commissioned and
sinking commenced on March 31 with the cumulative sinking level now
at 83 metres below ground level. Shaft 4 sinking re-started on
March 25 after work was interrupted on February 17 due to an
electrical fault. Shaft 4 advancement is now 190 metres below
ground level. Although progress of these shafts continued during
the quarter, challenges with sinking rates continue, and a program
of work has been initiated to optimize shaft sinking progress going
forward. The impact of shaft sinking rates and related optimization
efforts on post-Panel 0 ramp up is currently being evaluated and
will be incorporated into the underground mine cost and schedule
review and update.
Force Majeure
Oyu Tolgoi concentrate shipment volumes to customers continued
to steadily improve with on-site concentrate inventory levels
reducing by 30% over the quarter. Above target inventory levels
remained at the end of Q1 2022, and management continues to focus
on returning them to target levels. The challenges relating to the
continued COVID-19 related Mongolia / Chinese border restrictions,
which resulted in force majeure being declared from March 30, 2021,
continue despite the improvements experienced during the quarter.
Oyu Tolgoi continues to work closely with Mongolian and Chinese
authorities to manage any supply chain disruptions. The force
majeure will remain in place until there are sufficiently sustained
volumes of convoys crossing the border to ensure Oyu Tolgoi’s
ability to meet its on-going commitments to customers and to return
on-site concentrate inventory to target levels.
Oyu Tolgoi Production Data All data represents full
production and sales on a 100% basis 1Q 2Q 3Q 4Q
1Q
Full Year
2021
2021
2021
2021
2022
2021
Open pit material mined (‘000 tonnes)
22,588
15,829
22,588
23,979
24,386
84,983
Ore treated (‘000 tonnes)
9,813
9,401
9,336
10,573
9,581
39,124
Average mill head grades: Copper (%)
0.56
0.47
0.53
0.46
0.40
0.50
Gold (g/t)
0.68
0.50
0.63
0.38
0.32
0.54
Silver (g/t)
1.29
1.19
1.29
1.27
1.25
1.26
Concentrates produced (‘000 tonnes)
201.9
173.2
191.9
182.7
144.3
749.6
Average concentrate grade (% Cu)
22.5
21.2
21.9
21.3
21.0
21.7
Production of metals in concentrates: Copper (‘000 tonnes)
45.4
36.7
41.9
38.9
30.3
163.0
Gold (‘000 ounces)
146
113
131
79
59
468
Silver (‘000 ounces)
255
235
249
238
211
977
Concentrate sold (‘000 tonnes)
186.3
92.6
224.4
165.9
148.3
669.2
Sales of metals in concentrates: Copper (‘000 tonnes)
39.0
19.6
46.4
34.4
29.9
139.4
Gold (‘000 ounces)
111
73
149
102
57
435
Silver (‘000 ounces)
207
106
278
192
179
783
Metal recovery* (%) Copper
86.3
79.7
83.9
80.1
78.1
82.8
Gold
72.2
69.3
68.7
59.3
59.0
68.4
Silver
65.3
62.5
64.1
55.1
54.3
61.6
*Metal recovery is a function of head
grade and reflects grades delivered in the quarter.
Technical Information included in this Press Release
Disclosure of information of a scientific or technical nature in
this press release in respect of the Oyu Tolgoi mine was approved
by Jo-Anne Dudley (FAusIMM(CP)), Chief Operating Officer of the
Company. Ms. Dudley is a “qualified person” as that term is defined
in National Instrument 43-101—Standards of Disclosure for Mineral
Projects.
Forward-looking statements and forward-looking
information
Certain statements made herein, including statements relating to
matters that are not historical facts and statements of the
Company’s beliefs, intentions and expectations about developments,
results and events which will or may occur in the future,
constitute “forward-looking information” within the meaning of
applicable Canadian securities legislation and “forward-looking
statements” within the meaning of the “safe harbour” provisions of
the United States Private Securities Litigation Reform Act of 1995.
Forward-looking statements and information relate to future events
or future performance, reflect current expectations or beliefs
regarding future events and are typically identified by words such
as “anticipate”, “believe”, “could”, “estimate”, “expect”,
“intend”, “likely”, “may”, “plan”, “seek”, “should”, “will” and
similar expressions suggesting future outcomes or statements
regarding an outlook. These include, but are not limited to,
statements and information regarding: the nature of the Company’s
ongoing relationship and interaction with the Government of
Mongolia with respect to the continued operation and development of
Oyu Tolgoi as and when the key agreements entered into with the
Government of Mongolia announced on January 24, 2022 (the GoM
Agreements) are implemented along with the implementation of
Resolution 103; the continuation of undercutting in accordance with
the mine plan and design; the actual timing of first sustainable
production as well as the lifting of restrictions by the Government
of Mongolia on the ability of Oyu Tolgoi LLC (OT LLC) to incur any
additional indebtedness; the implementation and successful
execution of the updated funding plan that is the subject of the
Amended and Restated Heads of Agreement (the Amended HoA) dated as
of January 24, 2022 between the Company and Rio Tinto, as such
agreement may be further amended or restated, and the amount of any
additional future funding gap to complete the Oyu Tolgoi project
and the availability and amount of potential sources of additional
funding required therefor, all as contemplated by the Amended HoA,
as well as potential delays in the ability of the Company and OT
LLC to proceed with the funding elements contemplated by the
Amended HoA; liquidity, funding sources and funding requirements in
general, in particular until sustainable first production is
achieved, including the Company’s ability to reach agreement with
project finance lenders on the re-profiling of existing debt
payments in line with current cash flow projections, as well as the
Company (or a wholly-owned subsidiary) and OT LLC entering into a
pre-paid copper concentrate sale arrangement; the availability and
amount of potential sources of additional funding, including the
short-term secured advance to be provided by Rio Tinto to the
Company under the Amended HoA; the amount by which a successful
re-profiling of the Company’s existing debt would reduce the
Company’s currently projected funding requirements; the Company’s
ability to conduct one or more equity offerings as contemplated by
the Amended HoA in light of future and then prevailing market
conditions; the expectations set out in the 2020 Oyu Tolgoi
Technical Report (2020 OTTR); the timing and amount of future
production and potential production delays; statements in respect
of the impacts of any delays on achieving first sustainable
production and on the Company’s cash flows; expected copper and
gold grades; the merits of the class action complaints filed
against the Company in October 2020 and January 2021, respectively;
the merits of the defence and counterclaim filed by the Government
of Mongolia in the international tax arbitration brought by OT LLC
and the likelihood of the parties being able to amicably resolve
the ongoing tax issues; the timing of studies, announcements and
analyses; the status of underground development, including any
slowdown of work; the causes of the increase in costs and schedule
extension of the underground development; the mine design for Panel
0 of Hugo North Lift 1 and the related cost and production schedule
implications; the re-design studies for Panels 1 and 2 of Hugo
North Lift 1 and the possible outcomes, content and timing thereof;
expectations regarding the possible recovery of ore in the two
structural pillars, to the north and south of Panel 0; the possible
progression of a state-owned power plant (SOPP) and related
amendments to the Power Source Framework Agreement (PSFA), as
amended, as well as power purchase agreements and extensions
thereto; finalization of an agreement with Inner Mongolia Power
International Cooperation Co., Ltd (IMPIC) on extension of the
current power import arrangements; the timing of construction and
commissioning of the potential SOPP; sources of interim power; the
continuing impact of COVID-19, including any restrictions imposed
by health or governmental authorities relating thereto on the
Company’s business, operations and financial condition, as well as
delays and the development cost impacts of delays caused by the
COVID-19 pandemic; the Company’s ability to operate sustainably,
its community relations and its social licence to operate in
Mongolia; capital and operating cost estimates; mill and
concentrator throughput; anticipated business activities, planned
expenditures, corporate strategies, and other statements that are
not historical facts.
Forward-looking statements and information are made based upon
certain assumptions and other important factors that, if untrue,
could cause the actual results, performance or achievements of the
Company to be materially different from future results, performance
or achievements expressed or implied by such statements or
information. There can be no assurance that such statements or
information will prove to be accurate. Such statements and
information are based on numerous assumptions regarding present and
future business strategies, local and global economic conditions,
and the environment in which the Company will operate in the
future, including: the price of copper, gold and silver; projected
gold, copper and silver grades; anticipated capital and operating
costs; anticipated future production and cash flows; the
anticipated location of certain infrastructure in Hugo North Lift 1
and sequence of mining within and across panel boundaries; the
nature of the Company’s ongoing relationship and interaction with
the Government of Mongolia with respect to the continued operation
and development of Oyu Tolgoi as and when the GoM Agreements are
implemented along with the implementation of Resolution 103; the
continuation of undercutting in accordance with the mine plan and
design; the actual timing of first sustainable production as well
as the lifting of restrictions by the Government of Mongolia on the
ability of OT LLC to incur any additional indebtedness; the
availability and timing of required governmental and other
approvals for the construction of the SOPP; the ability of the
Government of Mongolia to finance and procure the SOPP within the
timeframes anticipated in the PSFA, as amended, subject to ongoing
discussions relating to a standstill period; finalization of an
agreement with IMPIC on an extension of the current power import
arrangements; the eventual pre-payment arrangement between the
Company (or a wholly-owned subsidiary) and OT LLC; the
implementation and successful execution of the updated funding plan
that is the subject of the Amended HoA, as such agreement may be
further amended and restated; the Company’s ability to operate
sustainably, its community relations and its social licence to
operate in Mongolia; and the amount of any additional future
funding gap to complete the Oyu Tolgoi project and the availability
and amount of potential sources of additional funding required
therefor.
Certain important factors that could cause actual results,
performance or achievements to differ materially from those in the
forward-looking statements and information include, among others:
copper, gold and silver price volatility; discrepancies between
actual and estimated production; mineral reserves and resources and
metallurgical recoveries; development plans for processing
resources; public health crises such as COVID-19; matters relating
to proposed exploration or expansion; mining operational and
development risks, including geotechnical risks and ground
conditions; litigation risks, including the outcome of the class
action complaints filed against the Company; the outcome of the
international arbitration proceedings, including the likelihood of
the parties being able to amicably resolve the ongoing tax issues;
regulatory restrictions (including environmental regulatory
restrictions and liability); OT LLC or the Government of Mongolia’s
ability to deliver a domestic power source for the Oyu Tolgoi
project within the required contractual time frame; the Company’s
ability to operate sustainably, its community relations, and its
social licence to operate in Mongolia; activities, actions or
assessments, including tax assessments, by governmental
authorities; events or circumstances (including public health
crises strikes, blockades or similar events outside of the
Company’s control) that may affect the Company’s ability to deliver
its products in a timely manner; currency fluctuations; the
speculative nature of mineral exploration; the global economic
climate; global climate change; dilution; share price volatility;
competition; loss of key employees; cyber security incidents;
additional funding requirements, including in respect of the
development or construction of a long-term domestic power supply
for the Oyu Tolgoi project; capital and operating costs, including
with respect to the development of additional deposits and
processing facilities; defective title to mineral claims or
property; and human rights requirements. Although the Company has
attempted to identify important factors that could cause actual
actions, events or results to differ materially from those
described in forward-looking statements and information, there may
be other factors that cause actions, events or results not to be as
anticipated, estimated or intended. All such forward-looking
statements and information are based on certain assumptions and
analyses made by the Company’s management in light of their
experience and perception of historical trends, current conditions
and expected future developments, as well as other factors
management believes are reasonable and appropriate in the
circumstances. These statements, however, are subject to a variety
of risks and uncertainties and other factors that could cause
actual events or results to differ materially from those projected
in the forward-looking statements or information.
With respect to specific forward-looking information concerning
the continued operation and development of the Oyu Tolgoi project,
the Company has based its assumptions and analyses on certain
factors which are inherently uncertain. Uncertainties and
assumptions include, among others: the nature of the Company’s
ongoing relationship and interaction with the Government of
Mongolia with respect to the continued operation and development of
Oyu Tolgoi as and when the GoM Agreements are implemented along
with the implementation of Resolution 103; the continuation of
undercutting in accordance with the mine plan and design; the
approval or non-approval by the OT LLC Board of any future
necessary additional investment, and the likely consequences on the
timing and overall economic value of the Oyu Tolgoi project,
including slowdown on the underground development and significant
delays to first sustainable production; the timing and cost of the
construction and expansion of mining and processing facilities; the
timing and availability of a long-term domestic power source (or
the availability of financing for the Company or the Government of
Mongolia to construct such a source) for Oyu Tolgoi; the
implementation and successful execution of the updated funding plan
that is the subject of the Amended HoA, as such agreement may be
further amended or restated, and the amount of any additional
future funding gap to complete the Oyu Tolgoi project and the
availability and amount of potential sources of additional funding
required therefor the eventual pre-payment arrangement between the
Company (or a wholly-owned subsidiary) and OT LLC; the potential
impact of COVID-19, including any restrictions imposed by health
and governmental authorities relating thereto, as well as the
development cost impacts of delays caused by the COVID-19 pandemic;
the Company’s ability to operate sustainably, its community
relations and its social licence to operate in Mongolia; the impact
of changes in, changes in interpretation to or changes in
enforcement of, laws, regulations and government practices in
Mongolia; the availability and cost of skilled labour and
transportation; the obtaining of (and the terms and timing of
obtaining) necessary environmental and other government approvals,
consents and permits; delays and the costs which would result from
delays, including delays caused by COVID-19 restrictions and
impacts and related factors, in the development of the underground
mine (which could significantly exceed the costs projected in the
2020 OTTR); projected copper, gold and silver prices and their
market demand; and production estimates and the anticipated yearly
production of copper, gold and silver at Oyu Tolgoi.
The cost, timing and complexities of mine construction and
development are increased by the remote location of a property such
as Oyu Tolgoi. It is common in mining operations and in the
development or expansion of existing facilities to experience
unexpected problems and delays during development, construction and
mine start-up. Additionally, although Oyu Tolgoi has achieved
commercial production, there is no assurance that future
development activities will result in profitable mining
operations.
Readers are cautioned not to place undue reliance on
forward-looking information or statements. By their nature,
forward-looking statements involve numerous assumptions, inherent
risks and uncertainties, both general and specific, which
contribute to the possibility that the predicted outcomes will not
occur. Events or circumstances could cause the Company’s actual
results to differ materially from those estimated or projected and
expressed in, or implied by, these forward-looking statements.
Important factors that could cause actual results to differ from
these forward-looking statements are included in the “Risk Factors”
section in the Company’s annual information form for the year ended
December 31, 2021 (“AIF”).
Readers are further cautioned that the list of factors
enumerated in the “Risk Factors” section of the AIF that may affect
future results is not exhaustive. When relying on the Company’s
forward-looking statements and information to make decisions with
respect to the Company, investors and others should carefully
consider the foregoing factors and other uncertainties and
potential events. Furthermore, the forward-looking statements and
information contained herein are made as of the date of this
document and the Company does not undertake any obligation to
update or to revise any of the included forward-looking statements
or information, whether as a result of new information, future
events or otherwise, except as required by applicable law. The
forward-looking statements and information contained herein are
expressly qualified by this cautionary statement.
View source
version on businesswire.com: https://www.businesswire.com/news/home/20220419006043/en/
Investors and Media Roy McDowall
roy.mcdowall@turquoisehill.com Follow us on
Twitter@TurquoiseHillRe
Turquoise Hill Resources (TSX:TRQ)
Historical Stock Chart
From Nov 2024 to Dec 2024
Turquoise Hill Resources (TSX:TRQ)
Historical Stock Chart
From Dec 2023 to Dec 2024