DOW JONES NEWSWIRES
The following table lists unplanned and planned production
outages at U.S. refineries as reported by Dow Jones Newswires. The
information is compiled from both official and unofficial refining
sources and doesn't purport to be a comprehensive list.
Planned maintenance activity at a crude unit, reformer unit and
coker unit in October at Hovensa's oil refinery on the U.S. Virgin
Island of St. Croix is not expected to affect the company's ability
to meet customer commitments, the company said on Oct. 3.
Crude unit maintenance at Chevron's (CVX) Bay-area refinery in
Richmond, Ca., is scheduled to begin on October 8, traders said on
Oct. 3. This information has not been confirmed.
In the Pacific Northwest, an unspecified process unit, rumored
to be a key gasoline-making fluid catalytic cracking unit, at
Tesoro Corp.'s (TSO) Anacortes, Washington, refinery was shut on
Oct. 1 for maintenance. The work wasn't expected to affect Tesoro's
ability to meet regional supply commitments, traders said on Oct.
3.
ExxonMobil Corp. (XOM) on Oct. 3 said operations at its oil
refinery in Billings, Montana, were nearing normal operations and
should be at planned rates very soon, company spokeswoman Rachael
Moore said. Rates had been reduced on July 1 when the Silvertip
crude oil pipeline leaked about 1,000 barrels of crude oil into the
Yellowstone River.
A power failure on Sept. 28 at Alon USA Energy Inc's (ALJ)
67,000 barrel-a-day refinery in Big Spring, Texas, was responsible
for taking down a substantial number of units at the refinery,
according to a filing to the Texas Commission On Environmental
Quality. A flaring event lasted for 24 hours and it wasn't known
whether the units were back on line.
Total SA (TOT) is performing maintenance work for six weeks at
its 232,000 barrel-a-day refinery in Port Arthur, La., that
includes work on the crude distillation unit and fluid catalyst
cracker, a source familiar with the refinery said Sept. 21.
For more detailed information, search Dow Jones Newswires using
the code N/REF.
Operator Refinery Capacity Description Restart
(in 000s
bbl/day)
UNPLANNED
CANADA
CARIBBEAN
EAST COAST
GULF COAST
Alon Big Spring 67.0 Power failure on Sept 28 shuts
TX several process units, a TCEQ
filing said. Status of opera-
tions unclear.
Total Port Arthur 232.0 Crude unit shut, traders said Sep. 19
TX on Sep. 12; coker 'blow out'
reported to NRC. Restart seen
by about Sep. 19.
MIDWEST
ROCKIES
Sinclair Sinclair 74.0 Refinery at reduced rates fol-
WY lowing fires at CDU on Sep. 3
and Sep. 4. Repairs and damage
assessments underway, the co.
said on Sep.6.
Exxon Billings, 60.0 Operations nearing normal rates
MT after being reduced due to rup-
tured Silvertip pipeline on July
1, the company said on Oct. 3.
WEST COAST
Tesoro Anacortes, 120.0 FCCU shut Oct. 1 for maintenance
WA traders said on Oct. 3; no further
details provided.
PLANNED
CANADA
CARIBBEAN
Hovensa St. Croix 350.0 Planned maintenance at a
crude unit, reformer and
coker unit in Oct. will
last 2-4 weeks, co. said
on Oct. 3.
EAST COAST
Sunoco Philadelphia 335.0 Refineries up for sale on
Marcus Hook 190.0 Sep. 6; process units will
be shuttered in July 2012
if no buyer is found.
GULF COAST
Motiva Port Arthur 285.0 Expansion project to increase 1Q
TX throughput capacity by 325,000 2012
b/d, to 610,000-b/d, slowed.
Completion now seen 1Q
2012, from 2010.
Total Port Arthur 232.0 Several units, including crude
USA TX unit and FCCU shut six weeks
turnaround maintenance, a source
familiar with the plant said on
Sept. 21.
Valero Corpus 315.0 Crude & coker unit turnaround Oct.
Christi, TX to start in Oct. for three 2011
weeks.
Valero McKee TX 170.0 Crude Unit and FCCU to undergo 3Q 2011
turnaround maintenance for six
weeks starting in Oct. 2011, the
co. said on July 26.
Vacuum unit turnaround planned for
first half of 2012, co. said.
Expansion project announced
March 2011 to increase crude oil
throughput by 25,000 b/d to
195,000 b/d.
Valero Norco, LA 185.0 Hydrocracker project will pro- 2013
ceed and be completed in late
2013, the co. said on 7/27/10.
Upgrade project to build 2012
a new diesel hydrotreater
unit moved from 2010 to
4Q 2012.
Valero Port Arthur 325.0 Hydrocracker project will pro- 2012
TX ceed and be completed in late
2012.
MIDWEST
BP Whiting, IN 405.0 Turnaround at Pipestill 12 de-
layed by 3 months; it was sup-
posed to begin in November, a
source said on Mar 25.
Cenovus Roxana, IL 306.0 Coker and refinery expansion Q4 2011
(Conoco/WRB) project on track for comple-
tion 4th Q 2011, the co. said
on July 26, 2011.
CVR Coffeyville 115.7 Periodic turnaround will take 2012
KS place in two phases beginning in
Fall 2011 and completed in Spring
2012.
Husky Lima, OH 160.0 15-days of maintenance planned at
Energy at aromatics unit in the fall
of 2012.
Husky Toledo, OH 140.0 Minor maintenance planned in 4Q
Energy 2011, the co. said on July 28;
no details provided.
Tesoro Mandan, ND 58.0 Total crude-oil processing capa- 2nd Q
city to increase by 17% to 68,000 2012
b/d by 2nd quarter 2012.
WEST COAST
Chevron Richmond, 240.0 Crude unit maintenance scheduled
CA to begin on Oct. 8, traders said
on Oct. 3. No further details pro-
vided.