DOW JONES NEWSWIRES 
 

The following table lists unplanned and planned production outages at U.S. refineries as reported by Dow Jones Newswires. The information is compiled from both official and unofficial refining sources and doesn't purport to be a comprehensive list.

Chevron (CVX) Tuesday advanced planned FCCU maintenance at its Pascagoula, Mississippi, refinery; the work was originally scheduled for January, a person familiar with operations at the plant said. The unit was experiencing mechanical problems; the repairs are expected to take 20 to 30 days.

Exxon Mobil Corp. (XOM) said Tuesday that work to repair a leaking valve at the Beaumont refinery's coker gas plant will not impact production. The work got underway on Nov. 29 and the leak was isolated and contained.

Valero Energy (VLO) Tuesday said the FCCU at its Memphis, Tennessee, refinery was shut unplanned for maintenance. The restart timing is not yet known, but Valero does not expect it to be a lengthy outage.

LyondellBasell (LYB, LYB.B) Monday reported emissions associated with an operations upset at its Houston, Texas, refinery, citing the FCCU as a source of the release.

Exxon Mobil (XOM) Monday said planned turnaround maintenance at its Beaumont, Texas, refinery is ongoing. The primary units involved in the turnaround that began on about September 28 are a hydrocracker and a catalytic reformer Dow Jones Newswires reported at that time.

ConocoPhillips (COP) Monday reported an emissions event at its Sweeny, Texas, refinery owing to an upset at Unit 27 which was previously identified as an FCCU. Adjustments were made to bring the unit back into compliance, the co. said in a filing to environmental regulators.

Valero Energy Corp. (VLO) Monday reported the scheduled startup of units affected Sunday by unplanned maintenance to repair a boiler water feed system in the West Plant section at its oil refinery in Corpus Christi, Texas, the company said.

Exxon Mobil said Monday a process unit was taken out of service on Friday as a precaution after a mechanical issue was discovered during startup following Wednesday's power failure. The unit was not identified and there is no restart estimate. Most of the other units affected by Wednesday's power outage have returned to service; one unit was in restart mode on Monday, the Co. said.

Total Petrochemicals USA (TOT) Friday experienced a release of sulfur dioxide owing to a Scot Unit air compressor shut down at its Port Arthur, Texas, oil refinery. Refinery personnel were working to get the unit back on line, a filing to Texas environmental regulators said.

Motiva Enterprises (RDSA, RDSB) Saturday reported an emissions event at its Norco, La., refinery owing to equipment failure; no further details were provided in the filing to environmental regulators.

Valero Energy Friday said that a brief period of flaring at its Port Arthur, Texas, refinery was not associated with production units and had no impact on production.

Holly Corp. (HOC) Saturday reported a release of sulfur dioxide at its Tulsa, Oklahoma, oil refinery, but did not know what caused it, a filing to the U.S. National Response Center said.

Coffeyville Resources (CVI) Saturday reported an air release at its Coffeyville, Kansas, oil refinery, citing equipment failure as the cause of the incident. A report to the U.S. National Response Center listed sulfur recovery unit 3 as the affected equipment. Refinery technicians were working on the problem, but the operating status of sulfur recovery unit 3 was unclear.

 
   For more detailed information, search Dow Jones Newswires using the code N/REF. 
 
 
Operator   Refinery    Capacity   Description                   Restart 
                       (in 000s 
                       bbl/day) 
UNPLANNED 
 
CANADA 
 
CARIBBEAN 
 
EAST COAST 
 
Hess    Port Reading,  70.0   Company said on Nov. 19 that      Nov 19 
                              repairs finished on an FCCU 
                              brought down after Nov. 12 
                              power outage. Restart will 
                              begin soon. 
 
GULF COAST 
 
Alon    Big Springs,   67.0   Company said upset electrostatic 
        TX                    precipitator caused opacity on 
                              Nov. 19. 
 
Chevron  Pascagoula,   333.0  Planned FCCU maintenance ad-      Dec 
         MS                   vanced from January to Nov.       20/30 
                              30 due to mechanical issues. 
                              Repairs will take 20-30 days. 
 
                              Leak in a process line caused 
                              emissions on Nov. 13, regulatory 
                              filing said. 
 
Conoco   Sweeny, Tx    247.0  Emissions were caused by an       Nov 29 
Phillips                      upset at Unit 27, previously 
                              identified as an FCCU. Adjust- 
                              ments were made to bring the 
                              unit back to compliance, the 
                              co. said on Nov. 29. 
 
Exxon    Beaumont, TX  344.5  Work to repair leaking valve 
Mobil                         at coker gas plant got under- 
                              way on Nov. 29. No impact on 
                              production, the Co. said. 
 
                              Refinery continues to operate     Nov 24 
Mobil                         following a brief, small fire 
                              on Nov. 24, the Co. said. 
 
Lyondell Houston, TX   270.6  Emission event on Nov 29 due      n/a 
Basell                        to operations upset. FCCU and 
                              wet gas scrubber stack listed 
                              as sources of release. 
 
                              A small fire on Nov. 23 caused    n/a 
                              no serious damage, no injuries. 
 
                              All units at normal rates the     Nov 22 
                              co. said on Nov. 22 after 
                              plantwide outage on Nov. 20. 
 
Motiva   Convent, LA   235.0  Unspecified unit failure caused   n/a 
                              emissions on Nov. 15, according 
                              to filing. 
 
Motiva   Norco, La     235.0  Equipment failure caused emis-    n/a 
                              sions on Nov. 27, a filing to 
                              regulators said. No further de- 
                              tails were provided. 
 
Total    Port Arthur   232.0  Scot Unit compressor shutdown     n/a 
         TX                   on Nov. 26 caused an emissions 
                              event. Refinery personnel were 
                              working to get the unit back 
                              on line. 
 
Valero   Corpus   TX   315.0  Units affected by unplanned       Nov 29 
         Christi              maintenance on Nov. 28 were re- 
                              started as planned on Nov. 29. 
                              The work had no impact on pro- 
                              duction, the co. said. 
 
 
MIDWEST 
 
BP/Husky Toledo, OH   160.0   Crude oil throughput was reduced  n/a 
                              by unspecified amount owing 
                              to Enbridge's crude oil Line 6B 
                              leak/closure since July 26. 
 
Coffey-  Coffeyville  115.0   Sulfur Recovery Unit upset re-    n/a 
ville    KA                   sults in emissions on Nov. 27. 
                              Status of unit unclear. 
 
 
Exxon    Joliet, IL    239.0  Refinery operations may be af- 
                              fected by Enbridge's decision 
                              to reduce crude oil delivery rates 
                              on Line 6A while integrity in- 
                              spections continue. Co. not im- 
                              mediately available for comment 
                              on Oct. 13. 
 
Marathon Robinson, IL  206.0  Trade sources say crude unit      Oct 22- 
                              shut around Oct 16-17 for         25 
                              maintenance. Restart seen by 
                              Oct. 22 or 25. Co. wouldn't 
                              comment. 
 
Valero   Memphis, TN   180.0  FCCU shut Nov. 29 for un-         N/A 
                              planned maintenance. Restart 
                              timing not yet known. 
 
 
ROCKIES 
 
WEST COAST 
 
Exxon     Torrance   149.5   A process unit was shut on Nov.    n/a 
Mobil     CA                 26 owing to a mechanical problem 
                             discovered during its restart 
                             after Monday's power outage. All   Nov 29 
                             other units affected by the outage 
                             are at normal rates but one that is 
                             in restart mode, the co. said on 
                             Nov. 29. 
 
 
 
 
Shell     Anacortes   145.0   A flare line erosion resulted in 
          WA                  emissions on Nov. 16. 
 
Tesoro    Anacortes,    120.0 Refinery at targeted rates after  Nov 16 
                              extensive reparis following the 
                              deadly April 2 explosion, the 
                              company said on Nov. 16. 
 
PLANNED 
 
CANADA 
 
Irving   New                  All units restarted following     Nov 23 
Oil      Brunswick            turnaround maintenance that 
                              began in late Sept. the co. 
                              said on Nov. 23. 
 
Shell    Montreal     130.0   The refinery will be converted 
         Quebec               into a terminal. 
 
CARIBBEAN 
 
Valero   Aruba        235.0   Turnaround maintenance that       late 
 
 
                              began in June is seen con-        Dec/ 
                              cluding late Dec or early Jan.    early 
                              The decision on whether           Jan 
                              units will be restarted after     2011 
                              the turnaround ends will be 
                              made at that time. 
 
EAST COAST 
 
Sunoco   Westville    145.0   Idling all Eagle Point refin-     n/a 
         NJ                   ing operations indefinitely due 
                              to poor economics, co. said 
                              Oct. 6, 2009. 
 
Valero   Delaware      210.0  PBF Energy has closed             Apr 
                              deal to buy plant. Petroplus      2011 
                              said May 5 the plant would be 
                              restarted in 2Q of 2011. 
 
Valero   Paulsboro, NJ 185.0  Agreed to sell refinery for 
                              $360 million to PBF Energy, 
                              Co. said Sept. 27. Deal is 
                              expected to close in Q4. 
 
Western  Yorktown       64.5  The refinery will close in        Sept 
         VA                   September 2010 for economic 
                              reasons. Terminal operations 
                              will continue. 
 
GULF COAST 
 
Chevron  Pascagoula  330.0    Pre-commercial heavy oil          2010 
         Miss.                conversion project delayed 
                              from 2008 to 2010 due to 
                              economic factors. 
 
                              Expansion project including 
                              the replacement of two 30-year- 
                              old reformers and construction 
                              of a 55,000 b/d continuous 
                              catalytic reformer platformer 
                              unit to be completed by late 
                              summer, Industrial Info 
                              Resources said July 6. A 
                              premium base-oil facility 
                              was also being planned, co. 
                              said in late Feb. 
 
Exxon    Baytown, TX   560.6  New ULSD Units commissioned, 
                              Co. said Oct 21. ULSD supply 
                              will increase by over 3 million 
                              gallons from Baytown & Baton 
                              Rouge. 
 
 
Exxon    Beaumont, TX  344.5  Scheduled turnaround maintenance  n/a 
Mobil                         continues since Sept. 28. Units 
                              involved include hydrocracker and 
                              catalytic reformer. No restart 
                              estimate available, the co. said 
                              on Nov. 29. 
 
Exxon    Chalmette     120.0  Crude throughput will be re-      N/A 
         LA                   duced to 90,000-b/d as redun- 
                              dant units and about 70 jobs 
                              are taken out of service and 
                              cut for economic reason. These 
                              have begun to take place, the 
                              co. said Aug 26. 
 
                              $250 mln project for new Spring 2010 
                              diesel desulfurization, 
                              sulfur recovery unit to begin 
                              in Fall 2008. Construction 
                              to last 18 months. 
 
Motiva   Port Arthur   285.0  Expansion project to increase     1Q 
                              throughput capacity by 325,000    2012 
                              b/d, to 610,000-b/d, slowed. 
                              Completion now seen 1Q 
                              2012, from 2010. 
 
Valero   Corpus       340.0   West Plant 50,000-b/d FCCU at 
         Christi, TX          reduced rates since mid-Dec for 
                              economic reasons. 
 
Valero   Norco, LA    250.0   Hydrocracker project will pro-    2013 
                              ceed and be completed in late 
                              2013, the co. said on July 27. 
 
                              FCCU, 100,000 b/d, will be        2Q 
                              revamped and work will take       2011 
                              place atat alky unit, lasting 
                              55 days starting in March, Co. 
                              said Oct. 26. 
 
                              Upgrade project to build          2012 
                              a new diesel hydrotreater 
                              unit moved from 2010 to 
                              4Q 2012. 
 
Valero   Port Arthur  325.0   Hydrocracker project will pro-    2012 
         TX                   ceed and be completed in late 
                              2012, the co. said on July 27. 
 
                              Six coke drums will be re-        2011 
                              placed in 2011. 
 
                              77,000-b/d FCCU at reduced        n/a 
                              rates since mid-Dec for 
                              economic reasons. 
 
Valero   Sunray, TX   170.0   55,000-b/d FCCU at reduced        n/a 
                              rates since mid-Dec for 
                              economic reasons. 
 
                              Expanded crude gather system      4Q 
                              will increase available crude     2010 
                              supplies to refinery by 4Q. 
 
                              24-day turnaround to begin at     2Q 
                              30,000-b/d hydrocracker in        2011. 
                              March 2011. 
 
MIDWEST 
 
BP       Toledo, OH   155.0   $400 million upgrade              2012 
                              to start 2010. 
 
Husky    Lima, OH     160.0   Scheduled fall turnaround main- 
                              tenance finished on Nov. 19, 
                              rates to return to normal within 
                              a week, company said. 
 
Marathon Detroit, MI  106.0   Turnaround maintenance finished 
                              on Nov. 19 after getting 
                              underway Oct 10. Scope 
                              of work unclear. 
 
Valero   Ardmore, OK   90.0   Plant-wide turnaround planned;    2Q 
                              work will impact 1Q 2011          2011 
                              results. It will begin in March 
                              and last 40 days, Co. said 
                              Oct. 26 
ROCKY MOUNTAIN 
 
Suncor   Commerce      93.0   Planned work at reformer unit     Fall 
         City, CO             deferred to Fall 2010 from Feb    2010 
                              28 start date. 
 
WEST COAST 
 
BP       Carson, CA   265.0   Planned flaring occurred on       N/A 
                              Nov. 20, a filing to state re- 
                              gulators said. 
 
Valero   Benicia      170.0   Scrubber installation continues;  2010 
         CA                   work seen concluding by year-end, 
                              the co. said on July 27. 
 
                              Plantwide turnaround to begin in  1Q 
                              January and will last 36 days.    2011 
 
Tesoro   Golden Eagle 166.0   Major turnaround maintenance      2011 
         Martinez, CA         deferred to 2011 from late 
                              2009, the co. said Feb. 3. 
 
 
 
 
Imperial Oil (AMEX:IMO)
Historical Stock Chart
From Jun 2024 to Jul 2024 Click Here for more Imperial Oil Charts.
Imperial Oil (AMEX:IMO)
Historical Stock Chart
From Jul 2023 to Jul 2024 Click Here for more Imperial Oil Charts.