Half Yearly Report -6-
October 29 2010 - 5:40AM
UK Regulatory
the landfill gas. The Manager is continuing to work with its technical
consultants to improve the operational performance, however conditions remain
challenging and the increased costs of operating the generating equipment as a
result of the gas quality means that the portfolio continues to perform below
budget. The Manager is investigating and trialling a number of measures in an
effort to improve performance, however progress since the date of the last
annual report has been limited.
The ability of Redimo LFG Limited to trade out of its current position remains
contingent on stabilising the operational performance and on an improvement in
the level of future wholesale energy prices. Currently, Redimo LFG Limited is in
breach of certain covenants under its banking facilities, however it retains the
support of its lenders. The Company determined in December 2009 that it was
prudent to fully write down the value of its investment in Redimo LFG Limited.
This remains the position even though Redimo LFG Limited is still actively
trading.
PBM Power Limited
PBM Power Limited is a company operating a waste wood biomass electricity
generating plant in Lincolnshire.
Following the acquisition of the assets of Ventus 3 VCT plc, the Company owns
25% of the share capital in PBM Power Limited for which a total consideration of
GBP574,000 has been paid.
The plant became operational in April 2009, which was approximately five months
later than scheduled as a result of delays in provision of the grid connection
by the network operator. There have been a number of operational issues with the
plant since it was first commissioned which have progressively been resolved by
the principal contractor under warranty. These have taken significantly longer
than first expected and there have been further plant shutdowns over the summer
period in order to resolve the operational issues once and for all. The plant
has only recently been put back in to full operation therefore as at the date of
this report there has only been a limited period of consistent generation.
The intention of PBM Power Limited is to run the plant at design output over the
remainder of 2010 to ensure that the technical issues that have arisen in the
past have been fully resolved by the latest works.
Together with the delayed start, the additional shutdowns have led to
significantly lower than expected generation volumes compared to the original
year one and two operating budget.
PBM Power Limited is continuing in negotiations with its lending bank regarding
the rescheduling of the repayments of its long term loan facilities.
In view of the need for the generating plant to demonstrate a consistent period
of stable operation, the investment has not been revalued using a discounted
cash flow methodology. The fair value of this investment is not considered to
be materially different to the historic cost of investment. In consideration of
the discounted future expected cash flows from this investment, the value at
which the investment is held is not considered to be impaired.
Spurlens Rig Wind Limited
Spurlens Rig Wind Limited is a company developing a six turbine wind farm in the
Borders region of Scotland. Following the acquisition of the assets of Ventus 3
VCT plc, the Company owns 60% of the share capital in Spurlens Rig Wind Limited
for which a total consideration of GBP198,000 has been paid.
The planning application is expected to be submitted before the end of October
2010 and a decision is anticipated within twelve months. The Company has secured
the rights to provide the equity and mezzanine debt finance required to build
the wind farm should planning permission be granted.
Olgrinmore Limited
Olgrinmore Limited is a company developing a two turbine wind farm in Caithness,
Scotland. Following the acquisition of the assets of Ventus 3 VCT plc, the
Company owns 17.6% of the share capital in Olgrinmore Limited for which a total
consideration of GBP68,400 has been paid.
A planning application was submitted in January 2009 but was refused by the
local planning department under delegated authority in June 2010. The company
has now submitted an appeal which is expected to be determined before the end of
the calendar year.
The Company has secured the rights to provide the equity and mezzanine debt
finance required to build the wind farm should planning permission be granted on
appeal.
Redeven Energy Limited
The Company holds an investment in Redeven Energy Limited, made by way of a
shareholder loan, to fund the development of three wind farm sites in East
Anglia. The Company made a nominal equity investment which was matched by Ventus
3 VCT plc. Following the acquisition of the assets of Ventus 3 VCT plc, the
Company owns 60% of the share capital in Redeven Energy Limited and is providing
total shareholder loans of GBP534,000, of which GBP60,000 was advanced in May
2010.
Planning consent has been awarded on the first two sites comprising a total of
seven turbines. Procurement work has started and negotiations are taking place
with turbine suppliers, lenders and other key contract counterparties. The
planning application for the third site, which would add a further two wind
turbines to the portfolio, is expected to be submitted later this year once the
required planning reports and public consultations have been completed.
The Company has secured the rights to provide the equity and mezzanine debt
finance required to build the wind farms for the sites when planning permissions
are obtained.
Osspower Limited
Osspower Limited is a company developing a group of four small scale
hydro-electric generating assets in Scotland. . The Company made an equity
investment of GBP150,000 which was matched by Ventus 3 VCT plc. Following the
acquisition of the assets of Ventus 3 VCT plc, the Company owns 50% of the share
capital in Osspower Limited and provides shareholder loans of GBP55,000. The
Company has also negotiated the rights to arrange the finance to build the
hydro-electric schemes.
The planning applications for the four hydro-electric schemes were submitted to
the Scottish Government Consents Unit in July 2009 and full planning permission
was granted in April 2010. The Investment Manager is currently working with the
other shareholders of Osspower Limited to put in place the finance facilities
and contracts required to take the consented sites forward into construction and
long term operation.
The Small Hydro Company Limited
The Small Hydro Company Limited is a company developing a number of small scale
hydro-electric generating assets in England. The Company made an equity
investment of GBP57,500 which was matched by Ventus 3 VCT plc. Following the
acquisition of the assets of Ventus 3 VCT plc, the Company owns 22.5% of the
share capital in The Small Hydro Company Limited and provides shareholder loans
amounting to GBP384,000.
The Small Hydro Company Limited submitted planning applications for its first
five sites in July 2009 and is continuing to work with the relevant authorities
to manage the applications through the planning process and to obtain the
necessary environmental licences. One of the planning applications was
initially refused and a resubmission has been made. Three sites have been
consented and the other application is yet to be determined.
Renewable Power Systems (Dargan Road) Limited
Renewable Power Systems (Dargan Road) Limited is a company operating a landfill
gas generating scheme on Belfast City Council's North Foreshore waste management
site.
The Company made an equity investment of GBP390,000 which was matched by Ventus
3 VCT plc. Following the acquisition of the assets of Ventus 3 VCT plc, the
Company owns 50% of the share capital in Renewable Power Systems (Dargan Road)
Limited and provides a shareholder loan facility of GBP1.12 million. Renewable
Power Systems (Dargan Road) Limited has been operational for a suitable period
andin accordance with the Company's investment valuation policy, the investment
has been revalued to GBP1.97 million.
The project manager and developer is Renewable Power Systems Limited, an
experienced UK landfill gas generation specialist. Renewable Power Systems
Limited owns 50% of Renewable Power Systems (Dargan Road) Limited and provides
long term operational support services.
Construction on the site began in 2008 and the plant became operational on
schedule and to budget in August 2009. Operating performance in the first
contract year at the project has been in accordance with budget and no
significant operational issues have occurred.
The Company received mezzanine loan interest of GBP36,000 in April 2010 against
income accrued in the current and prior periods. In May 2010, the Company
received a dividend of GBP150,000. The Company received mezzanine loan interest
of GBP73,000in September 2010 against income accrued in the half year together
with a further dividend of GBP100,000.
Sandsfield Heat & Power Limited
Sandsfield Heat & Power Limited is a company developing a biomass generating
scheme in North Yorkshire. The scheme uses waste wood as a fuel to generate
electricity, via a conventional steam turbine, for export to the grid.
The project manager and developer is Bioflame Limited, a company specialising in
energy from waste systems. Bioflame Limited own 30% of Sandsfield Heat & Power
Limited.
Following the acquisition of the assets of Ventus 3 VCT plc, the Company owns
44.9% of the share capital in Sandsfield Heat & Power Limited acquired for total
consideration of GBP1.8 million and provides a mezzanine loan facility of GBP1.0
million.
Construction on the site commenced in early 2009 and the plant entered operation
in July 2010 in line with the construction schedule. The plant is currently
undergoing performance optimisation testing in accordance with the post
commissioning testing regime and satisfactory full output has been achieved.
Ventus 2 Vct (LSE:VEN2)
Historical Stock Chart
From Jun 2024 to Jul 2024
Ventus 2 Vct (LSE:VEN2)
Historical Stock Chart
From Jul 2023 to Jul 2024