TIDMUKOG

RNS Number : 0573V

UK Oil & Gas Investments PLC

18 July 2018

UK Oil & Gas Investments PLC

("UKOG" or the "Company")

Portland Extended Flow Test ("EWT"): Well Clean-Up Phase Complete, Dry Oil Flows to Surface,

Horse Hill-1 Oil Discovery, PEDL137, Weald Basin, UK

Highlights:

   --     Initial Portland well "clean-up" phase completed successfully 

-- Light sweet crude oil (36 API) and associated solution gas flowed sustainably via pump and natural flow to surface over a 4-day period to date. Oil contains no metered water content (i.e. "dry oil")

-- Metered daily oil rates to date equal to or exceed 2016 values. Highest observed hourly rate equivalent to an implied daily rate of 352 barrels of oil per day ("bopd"). Corresponding metered solution gas volumes are up to an implied rate of 30,000 cu ft per day.

   --     Flow has not yet been optimised for maximum sustainable flow rates 
   --     First tanker containing 214 barrels of dry oil exported to BP's Hamble oil terminal 
   --     Initial analysis indicates well productivity unaffected by 2 year shut-in period since 2016 

-- Following a planned 24-hour shut in (i.e. pressure build-up test) the first of three planned Portland test sequences will commence

UK Oil & Gas Investments PLC (London AIM: UKOG) is pleased to announce that it has been informed by Horse Hill Developments Ltd ("HHDL"), the operator of the Horse Hill-1 ("HH-1") Kimmeridge and Portland oil discovery, in which UKOG holds a 32.435% beneficial interest along with licence PEDL137, that the initial well "clean-up" phase of the Portland extended well test ("EWT") programme has been completed according to plan. Over the past four days, the well has delivered a sustained dry oil and solution gas flow to surface via pump and natural flow.

Observed metered Portland flow rates to date are broadly equivalent to, or exceed, those recorded during the short duration 2016 test. The highest recorded hourly metered rate to date, equates to an implied daily rate of 352 bopd and was achieved using a 20/64" choke, a notably more restricted setting than the 64/64" choke used in 2016. Corresponding solution gas flows have been measured up to an implied rate of 30,000 cubic feet per day. Note that, to date, flow has not yet been optimised for maximum sustainable production rates, this will follow in the subsequent test sequences.

Several periods of sustained natural flow (i.e. flow to surface without pumping) have also been observed over the past few days, with the most productive period producing an implied daily dry oil rate of 228 bopd over a two-hour period.

Initial reservoir parameter analysis indicates that the Portland is performing very well compared to the productivity measured in 2016 prior to temporarily shutting in and suspending the well.

To date a total of 463 barrels of light sweet 36 API crude have been recovered to surface during the clean-up period, together with all 141 barrels of completion and kill fluids (i.e. saline water) used to suspend the well after the 2016 well test.

Forward EWT Plans

The well will now be shut in for a planned 24-hour pressure build-up test. Operations will then include further flow parameter optimisation, followed by the first of three planned flow sequences designed to assess whether the Portland oil pool contains a commercially viable volume of oil. The first test sequence will likely include an optimised maximum rate test, prior to choking back the well to provide the steady state flow conditions necessary to determine the Portland oil pool's connected oil volume. Note that in order to collect the required data during these steady state flow periods, rates will likely be below any future optimised production rates.

Testing of each of the Kimmeridge Limestone 4 ("KL4") and KL3 oil pools will follow completion of the Portland test sequence.

Stephen Sanderson, UKOG's Executive Chairman and Chief Executive, commented:

"Test results to date have exceeded our initial expectations given the length of time the well was shut-in since 2016. Although we are in the very early stages of our 150-day test campaign at Horse Hill, the signs to date are extremely positive for the Portland oil pool. The unexpected bonus of natural oil flow to the surface, without the use of a pump, gives us cause for further optimism regarding the Portland's overall commercial potential. It is important at this stage, however, to keep our expectations at a realistic level.

The Company looks forward to further positive results from the remaining Portland test sequences and then the testing of the two deeper and higher productivity Kimmeridge Limestone oil pools. Further updates will be made throughout the test campaign."

Extended Well Test ("EWT") Overview

As the 2016 short flow test campaign established commercially viable initial flow rates for each of the Portland, KL4 and KL3 zones, the 2018 EWT's prime goal is to confirm that the wellbore is connected to a commercially viable oil volume within one or more of the three zones.

The long-term reservoir performance data is also expected to provide the necessary data to enable, for the first time, Petroleum Resources Management System compliant Kimmeridge and Portland reserve figures to be estimated at Horse Hill.

Each test sequence will include a short, optimised rate test, together with a sequence of "choked back" (i.e. reduced) steady-state flow periods necessary to obtain the data required to determine the connected oil volume within each zone. A series of associated long pressure build up tests are also planned. Oil produced from the EWT will be sold on the "spot" oil market and any revenues will be utilised to offset overall testing costs.

Qualified Person's Statement

Stephen Sanderson, UKOG's Executive Chairman and Chief Executive, who has over 35 years of relevant experience in the oil industry, has approved the information contained in this announcement. Mr Sanderson is a Fellow of the Geological Society of London and is an active member of the American Association of Petroleum Geologists.

For further information, please contact:

UK Oil & Gas Investments PLC

Stephen Sanderson / Kiran Morzaria Tel: 01483 243450

WH Ireland (Nominated Adviser and Broker)

James Joyce / James Sinclair-Ford Tel: 020 7220 1666

Cenkos Securities PLC (Joint Broker)

Joe Nally / Neil McDonald Tel: 0207 397 8919

Public Relations

Brian Alexander / David Bick Tel: 01483 243450

UKOG Licence Interests

The Company has interests in the following UK licences:

 
Asset               Licence     UKOG's        Licence          Operator         Area             Status 
                                Interest       Holder                           (km(2) 
                                                                                  ) 
Avington                                     UKOG (GB)        IGas Energy                   Field currently 
 (1)                PEDL070       5%          Limited             Plc           18.3             shut in 
-----------------             ----------  --------------  ------------------  --------  ----------------------- 
                                            Kimmeridge        Kimmeridge                  BB-1 & 1z completed, 
Broadford                                    Oil & Gas         Oil & Gas                      preparing two 
 Bridge                                       Limited           Limited                     further planning 
 (3)                PEDL234      100%           (4)               (4)           300.0         applications 
-----------------             ----------  --------------  ------------------  --------  ----------------------- 
                                                              Europa Oil                 Holmwood-1 exploration 
Holmwood                                                    & Gas (Holdings)                  well planned 
 (3)                PEDL143       40%          UKOG               plc           91.8             in 2018 
-----------------             ----------  --------------  ------------------  --------  ----------------------- 
Horndean                                     UKOG (GB)        IGas Energy                   Field in stable 
 (1)                 PL211        10%         Limited             Plc           27.3           production 
-----------------             ----------  --------------  ------------------  --------  ----------------------- 
                                                                                            Production tests 
                                            Horse Hill        Horse Hill                  and further appraisal 
Horse Hill                                  Developments      Developments                  well(s) scheduled 
 (5)                PEDL137     32.435%         Ltd               Ltd           99.3            for 2018 
-----------------             ----------  --------------  ------------------  --------  ----------------------- 
                                            Horse Hill        Horse Hill 
Horse Hill                                  Developments      Developments 
 (5)                PEDL246     32.435%         Ltd               Ltd           43.6            As above 
-----------------             ----------  --------------  ------------------  --------  ----------------------- 
                                                                                          Preparing Arreton-3 
Isle of                                                                                       oil discovery 
 Wight (Onshore)                                                                             appraisal well 
 (2, 3)             PEDL331       65%          UKOG              UKOG           200.0      planning submission 
-----------------             ----------  --------------  ------------------  --------  ----------------------- 
                                                                                            Revised drilling 
Markwells                                    UKOG (GB)         UKOG (GB)                  and testing planning 
 Wood (2)           PEDL126      100%         Limited           Limited         11.2      application underway 
-----------------             ----------  --------------  ------------------  --------  ----------------------- 
 

Notes:

1. Oil field currently in production.

2. Oil discovery pending development and/or appraisal drilling.

3. Exploration asset with drillable prospects and leads. PEDL234 contains the Broadford Bridge-1 and 1z

discovery well, the extension of the Godley Bridge Portland gas discovery plus further exploration

prospects.

4. UKOG has a 100% interest in Kimmeridge Oil & Gas Limited, which has a 100% interest in PEDL234.

5. Oil discovery with successful flow test in 3 zones, further long-term testing scheduled in 2018

6. UKOG has a direct 49.9% interest in HHDL, which has a 65% interest in PEDL137 and PEDL246.

The information contained within this announcement is deemed by the Company to constitute inside information under the Market Abuse Regulation (EU) No. 596/2014.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

END

MSCLVLFFVDFZBBX

(END) Dow Jones Newswires

July 18, 2018 09:00 ET (13:00 GMT)

Uk Oil & Gas (LSE:UKOG)
Historical Stock Chart
From Apr 2024 to May 2024 Click Here for more Uk Oil & Gas Charts.
Uk Oil & Gas (LSE:UKOG)
Historical Stock Chart
From May 2023 to May 2024 Click Here for more Uk Oil & Gas Charts.