TIDMBSE 
 
AIM and Media Release 
 
25 January 2022 
 
BASE RESOURCES LIMITED 
Quarterly Activities Report - December 2021 
 
African mineral sands producer, Base Resources Limited (ASX & AIM: BSE) (Base 
Resources or the Company) is pleased to provide a quarterly operational, 
development and corporate update. 
 
Key Points 
 
  * Kwale Operations maintained operational consistency through the quarter, in 
    line with FY22 guidance. 
  * Ongoing strong demand supported further price increases for all products in 
    the quarter. 
  * Bumamani DFS commenced and on track for completion in the June quarter. 
  * Tanzanian exploration commenced with 224 shallow auger holes completed. 
  * Discussions with the Government of Madagascar on Toliara Project fiscal 
    terms continued. 
 
KWALE OPERATIONS 
 
Operational performance 
 
Mining operations continued to plan on the South Dune orebody with mined 
tonnage decreasing slightly due to planned maintenance shutdowns and lower 
mining rates.  The heavy mineral (HM) grade of ore mined in the quarter was 
higher at 3.82% (last quarter: 3.26%) as mining progressed towards the centre 
of the South Dune orebody. 
 
Wet concentrator plant (WCP) production of heavy mineral concentrate (HMC) was 
higher at 153kt (last quarter: 134kt) as a consequence of the higher ore 
grade.  HMC stocks increased to 23kt (last quarter: 17kt).  Sand tails 
continued to be deposited into the mined-out Central Dune area and capped with 
a 2m thick co-disposed slimes/sand layer to aid water retention and subsequent 
rehabilitation and alternate land use.  Rehabilitation of the Central Dune 
slopes and plateau continued to plan and agricultural trials on the co-disposed 
water retention layer proved successful.  Rehabilitation of the mined-out 
sections of the South Dune proceeded as scheduled. 
 
SUMMARY                         Q4 20      Q1 21      Q2 21      Q3 21         Q4 21 
 
Mining (million tonnes) 
 
Ore mined                         4.6        4.7        4.7        4.4           4.3 
 
HM %                             3.43       3.58       3.65       3.26          3.82 
 
VHM %                            2.62       2.80       2.78       2.50          2.94 
 
Production (thousand tonnes) 
 
Ilmenite                         78.5       84.2       88.7       72.9          84.0 
 
Rutile                           18.2       19.5       20.1       17.8          18.4 
 
Zircon                            6.7        7.4        7.1        6.1           6.4 
 
 
 
SUMMARY                         Q4 20      Q1 21      Q2 21      Q3 21         Q4 21 
 
US$ per tonne 
 
Sales revenue                    $464       $478       $497       $668          $459 
 
Operating costs                  $161       $142       $148       $174          $161 
 
Cost of goods sold               $207       $169       $202       $264          $156 
 
Revenue: Cost ratio               2.2        2.8        2.5        2.5           2.9 
 
Sales (thousand tonnes) 
 
Ilmenite                         53.8       97.2       94.0       34.1         130.0 
 
Rutile                           12.0       26.1       24.6       13.8          11.6 
 
Zircon                            6.4        6.6        7.7        5.6           6.2 
 
Mineral separation plant (MSP) feed tonnage of 146kt was higher than the prior 
quarter (last quarter: 137kt), due to increased HMC feed availability. 
Production of ilmenite was significantly higher in the quarter due to increased 
MSP recoveries of 102% (last quarter: 100%) and an elevated proportion of 
ilmenite in the mineral assemblage.  Underlying MSP product recoveries for 
rutile and zircon were steady and their production was in line with 
expectations. 
 
Bulk loading operations at Kwale Operations Likoni export facility continued to 
run smoothly, dispatching a combined 138kt of bulk ilmenite and rutile during 
the quarter (last quarter: 54kt).  Containerised shipments of rutile and zircon 
through the Mombasa Port proceeded to plan. 
 
Total cash operating costs of US$18.1 million increased compared to the prior 
quarter (last quarter at US$16.9 million) due to higher mining and maintenance 
costs.  However, the increased production volumes resulted in lower unit 
operating costs of US$161 per tonne produced (rutile, ilmenite, zircon and 
low-grade zircon) (last quarter: US$174 per tonne). 
 
Cost of goods sold decreased to US$156 per tonne sold (operating costs, 
adjusted for stockpile movements, and royalties) due to the sales mix (last 
quarter: US$264 per tonne), as did average unit revenue of US$459 per tonne 
(prior quarter: US$668 per tonne).  Due to these factors, the revenue to cost 
of goods sold ratio for the quarter increased to 2.9 (last quarter: 2.5). 
 
At the end of the quarter, 100% of Kwale Operations employees had received at 
least one dose of COVID-19 vaccine, with 76% fully vaccinated.  Boosters are 
scheduled to commence early in 2022. 
 
FY22 production guidance 
 
Kwale Operations production guidance for the 2022 financial year (FY22) remains 
at: 
 
  * Rutile - 73,000 to 83,000 tonnes. 
  * Ilmenite - 310,000 to 340,000 tonnes. 
  * Zircon - 24,000 to 28,000 tonnes.1 
 
[Note (1): Refer to Base Resources' announcement on 19 October 2021 "Quarterly 
Activities Report - September 2021" for the assumptions upon which the FY22 
production guidance is based.] 
 
MARKETING 
 
Despite uncertainties in China relating to power cuts, environmental controls 
and COVID management policies, the TiO2 pigment industry and the main 
zircon-user sectors (including ceramics) in China remained strong through the 
December quarter.  End user sectors for the Company's products in all other 
markets continued to strengthen through the quarter.  Further price increases 
for TiO2 pigment have been announced globally for early 2022. 
 
Demand for imported ilmenite as a feedstock for Chinese TiO2 pigment producers, 
particularly from the Company's customers, remained strong in the quarter, 
enabling further ilmenite price gains.  Increased ilmenite supply from some 
African sources, Vietnamese exports and Chinese domestic production through 
2021 continued to lag behind demand resulting in an expectation that ilmenite 
prices will maintain December levels through the March quarter.  Bulk freight 
costs to China eased through the quarter but remain volatile and are expected 
to affect ilmenite price gains for the foreseeable future. 
 
Demand for high grade TiO2 feedstocks (which includes rutile) again increased 
significantly through the quarter as western TiO2 pigment producers sought to 
maximise output volumes and the welding consumable and titanium metal sectors 
strengthened further.  The tight market for high grade feedstocks has been 
exacerbated by uncertainties over supply from major high grade feedstock 
producers.  Rutile prices increased through the quarter and substantial price 
increases have been secured for the March quarter.  A major rutile shipment 
scheduled for December 2021 was postponed to January 2022 due to delays with 
the customer's chartered vessel, impacting reported sales for the December 
quarter. 
 
Zircon demand continues to be strong in all end use sectors and regions, which, 
when combined with limited supply and minimal inventories, has resulted in a 
tightening zircon market and upward price pressure.  Zircon prices for the 
Company's December quarter contracts increased by approximately US$600/t from 
prices in September quarter contracts.  Due to ongoing uncertainties in China 
and the seasonally weaker winter period, average zircon pricing agreed for the 
Company's March quarter contracts have seen only a marginal increase over 
December quarter contract prices. 
 
SUSTAINABILITY 
 
Safety 
 
There were no lost time injuries during the quarter, or in the past year, at 
Kwale Operations or the Toliara Project, resulting in a lost time injury 
frequency rate (LTIFR) for Base Resources of zero.  Compared to the Western 
Australian All Mines 2019/2020 LTIFR of 2.1, this is an exceptional performance 
reflective of the ongoing focus and importance placed on safety by management. 
Base Resources group employees and contractors have now worked 26.9 million 
hours lost time injury (LTI) free, with the last LTI recorded in early 2014. 
 
With two medical treatment injuries recorded in the last 12 months, Base 
Resources' total recordable injury frequency rate is 0.50 per million hours 
worked. 
 
Community and environment - Kwale Operations 
 
The Company has continued to assist the Kwale community through the COVID-19 
pandemic, including by collaborating with county and national health 
authorities to encourage the uptake of vaccines. 
 
Agricultural livelihood programs in Kwale continued through the PAVI farmers' 
cooperative, with the arrival of rain in the quarter allowing additional 
planting to take place.  Poultry and beekeeping programs continue to expand and 
provide farmers and community groups with substantial incomes.  Selection of 
tertiary scholarship recipients was completed during the quarter with 220 
awards made. 
 
Implementation of identified projects by the Msambweni, Lunga and Likoni 
Community Development Agreement Committees commenced in the quarter with 
considerable progress made on several infrastructure projects. 
 
Rehabilitation activities on the mined-out sections of the South Dune continued 
in the quarter with community groups supplying indigenous legumes, grass seed 
and manure.  On the Central Dune, 14 hectares began being prepared for 
additional agricultural trials.  Refer to the PDF version of this announcement 
available from Base Resources' website:  https://baseresources.com.au/investors 
/announcements/ for an image showing the progressive land rehabilitation 
activities on the South Dune. 
 
A successful visit by representatives of key government departments and 
agencies, together with representatives of Kwale County, saw the endorsement of 
the Company's post-mining land use concepts that will now move into the 
pre-feasibility study phase. 
 
Community and environment - Toliara Project 
 
All community training programs, and social infrastructure construction, 
remained on hold with the Government of Madagascar's suspension of the Toliara 
Project's on-the-ground activities.  However, the Company continued to partner 
with local governments and community health groups in the Toliara region to 
provide additional support to vulnerable communities affected by COVID-19, 
including programs to address food insecurity and hygiene. 
 
Modern slavery statement 
 
During the quarter, Base Resources published its FY21 modern slavery statement 
reporting on the Company's actions to identify, assess and address the risks of 
modern slavery in the Company's operations and supply chains during the 
period2. 
 
[Note (2): For further information, refer to Base Resources' announcement on 3 
December 2021 "Modern Slavery Statement".] 
 
BUSINESS DEVELOPMENT 
 
Toliara Project development - Madagascar 
 
In November 2019, the Government of Madagascar required the Company to suspend 
on-the-ground activity on the Toliara Project while discussions on fiscal terms 
applying to the project were progressed.  Activity remains suspended as Base 
Resources continues to engage with the Government in relation to the country's 
Large Mining Investment Law (LGIM) regime, fiscal terms applicable to the 
Toliara Project and lifting of the on-the-ground suspension. 
 
In September 2021, the Company completed an enhanced Definitive Feasibility 
Study (DFS2) for the Toliara Project to incorporate an update to the estimated 
Ranobe Ore Reserves and an increase in project scale.3  The outcomes of DFS2, 
compared to the earlier 2019 DFS, included substantially improved forecast 
financial returns for the Toliara Project, including a post-tax/pre-debt (real) 
NPV10 of US$1.0 billion and an average revenue to cost of sales ratio of 3.5, 
over an initial 38-year mine life.4  The DFS2 schedule assumes construction 
will commence at the start of 2023, at a capital cost of US$520 million, which 
would see production starting in early 2025.  However, timing of the Final 
Investment Decision (FID) to proceed with construction of the Toliara Project 
remains subject to lifting of the suspension of on-the-ground activities and 
agreeing acceptable fiscal terms with the Government of Madagascar.  Once these 
two key milestones are achieved, there will be approximately 11 months' work to 
complete prior to reaching FID, including finalisation of funding, completion 
of land acquisition, conclusion of major construction contracts and entering 
into offtake agreements with customers.  Resumption of reasonable international 
travel will also be required to complete a significant portion of this pre-FID 
work.  The Company maintains readiness to accelerate progress when conditions 
support. 
 
Total expenditure on the Toliara Project for the quarter was US$1.2 million 
(last quarter: US$2.1 million). 
 
[Note (3): For further information, refer to Base Resources' announcement on 27 
September 2021 "DFS2 enhances scale and economics of the Toliara Project" (DFS2 
Announcement).] 
 
[Note (4): Refer to the DFS2 Announcement for the material assumptions and 
underlying methodologies for deriving these financial outcomes.  The DFS2 
Announcement also discloses key pre and post FID risks in respect of the 
Toliara Project.  Base Resources confirms that all the material assumptions 
underpinning the production information and forecast financial information in 
the DFS2 Announcement continue to apply and have not materially changed.] 
 
Kwale mine life extension 
 
The Company is progressing a definitive feasibility study (DFS) on higher grade 
subsets of the Bumamani and Kwale North Dune deposits to extend Kwale 
Operations mine life to July 2024.  Following a pit optimisation study 
completed in the quarter, a further Kwale North Dune pit area, referred to as 
the P200 pit area (in addition to the original P199 pit area), has been 
included in the DFS, which could further extend Kwale Operations mine life to 
early Q4 2024.  To secure the required mining tenure, an application for a 
variation to extend the Kwale Special Mining Lease 23 (SML 23) to cover these 
areas has been lodged.  The DFS is expected to be completed in the second 
quarter of 2022. 
 
Extensional exploration - Kenya & Tanzania 
 
No further work was conducted on the Vanga Prospecting License (PL/2015/0042) 
in the quarter and completion of the remaining drill program (4,200 metres) in 
the North-East Sector (Kwale East) of PL 2018/0119 remains on hold pending 
community access being secured. 
 
Prospecting licence applications lodged for an area in the Kuranze region of 
Kwale county, about 70 km west of Kwale Operations (applications 2019 0260, 
2510 and 2512), together with an area south of Lamu (applications 2019 0263, 
0265, 0266), remain in process towards granting.  An additional prospecting 
licence application has been lodged for the area surrounded by the Kuranze 
applications in Kenya, however application numbers and boundaries have not yet 
been issued.  A Government of Kenya moratorium on the issuance of prospecting 
licences in November 2019 has affected the progress of all licence 
applications.  The Company continues to work with the Government, and other 
mining sector stakeholders, to see the moratorium lifted to enable the 
recommencement of the issuance of mineral rights. 
 
The Company progressed on-ground exploration in Tanzania with a shallow auger 
drilling program completing 224 holes to assess geochemical anomalies and 
identify air core drilling targets.  Sample assaying is in progress at the 
Kwale Operations mine laboratory with infill auger drilling and test pits 
planned in the March quarter to better understand the more prospective areas. 
 Subject to the outcomes of assays, as well as drill rig availability, deeper 
drilling will then be progressed. 
 
Expenditure on exploration activities in Kenya during the quarter was US$0.2 
million (last quarter: US$0.3 million) and in Tanzania was US$0.2 million (last 
quarter: US$0.1 million). 
 
CORPORATE 
 
FY22 interim financial results 
 
The Company is targeting release of its FY22 interim consolidated financial 
statements on 28 February 2022.  Confirmation of timing and shareholder and 
investor call details will be advised closer to the planned release. 
 
Kwale royalty rate 
 
As previously announced,5 in parallel with the extension of SML 23 to 
incorporate the estimated Kwale South Dune Ore Reserves previously falling 
outside the SML 23 boundary, Base Titanium Limited, Base Resources' wholly 
owned Kenyan subsidiary, agreed to royalty rate increases that applied 
retrospectively.  During the quarter, Base Titanium Limited made royalty 
payments to the Government of Kenya totalling US$18.8 million comprising the 
necessary catch-up payments to the June 2021 quarter and payment of the 
September quarter royalty at the agreed increased rate.  Base Titanium Limited 
also paid corporate tax instalments of US$7.7 million to the Government of 
Kenya for the first half of FY22. 
 
As at 31 December 2021, the Company had net cash of US$37.1 million consisting 
of: 
 
  * Cash and cash equivalents of US$37.1 million. 
  * No debt. 
 
As at 31 December 2021, the Company had the following securities on issue: 
 
  * 1,178,011,850 fully paid ordinary shares. 
  * 76,570,331 performance rights pursuant to the terms of the Base Resources 
    Long Term Incentive Plan, comprising: 
      + 8,149,202 vested performance rights, which remain subject to exercise6. 
      + 68,421,129 unvested performance rights subject to performance testing 
        in accordance with their terms of issue. 
 
[Note (5): For further information, including the agreed increased royalty 
rates and the periods during which they apply, refer to Base Resources' 
announcement on 30 September 2021 "Kwale mining lease extension secured and 
royalty discussion finalised".] 
 
[Note (6): Vested performance rights have a nil cash exercise price.  Unless 
exercised beforehand, these rights expire five years after vesting.] 
 
Forward looking statements 
 
Certain statements in or in connection with this announcement contain or 
comprise forward looking statements.  Such statements may include, but are not 
limited to, statements with regard to future production and grades, capital 
cost, capacity, sales projections and financial performance and may be (but are 
not necessarily) identified by the use of phrases such as "will", "expect", 
"anticipate", "believe" and "envisage".  By their nature, forward looking 
statements involve risk and uncertainty because they relate to events and 
depend on circumstances that will occur in the future and may be outside Base 
Resources' control.  Accordingly, results could differ materially from those 
set out in the forward-looking statements as a result of, among other factors, 
changes in economic and market conditions, success of business and operating 
initiatives, changes in the regulatory environment and other government 
actions, fluctuations in product prices and exchange rates and business and 
operational risk management.  Subject to any continuing obligations under 
applicable law or relevant stock exchange listing rules, Base Resources 
undertakes no obligation to update publicly or release any revisions to these 
forward-looking statements to reflect events or circumstances after today's 
date or to reflect the occurrence of unanticipated events.S. 
 
For further information contact: 
 
James Fuller, Manager Communications and Investor  UK Media Relations 
Relations 
 
Base Resources                                     Tavistock Communications 
 
Tel: +61 (8) 9413 7426                             Jos Simson and Gareth Tredway 
 
Mobile: +61 (0) 488 093 763                        Tel: +44 (0) 207 920 3150 
 
Email: jfuller@baseresources.com.au 
 
About Base Resources 
 
Base Resources is an Australian based, African focused, mineral sands producer 
and developer with a track record of project delivery and operational 
performance.  The company operates the established Kwale Operations in Kenya 
and is developing the Toliara Project in Madagascar.  Base Resources is an ASX 
and AIM listed company.  Further details about Base Resources are available at 
www.baseresources.com.au 
 
PRINCIPAL & REGISTERED OFFICE 
Level 3, 46 Colin Street 
West Perth, Western Australia, 6005 
Email:  info@baseresources.com.au 
Phone: +61 (0)8 9413 7400 
Fax: +61 (0)8 9322 8912 
 
NOMINATED ADVISOR 
RFC Ambrian Limited 
Stephen Allen 
Phone: +61 (0)8 9480 2500 
 
JOINT BROKER 
Berenberg 
Matthew Armitt / Detlir Elezi 
Phone: +44 20 3207 7800 
 
JOINT BROKER 
Canaccord Genuity 
Raj Khatri / James Asensio / Patrick Dolaghan 
Phone: +44 20 7523 8000 
 
 
 
 
END 
 
 

(END) Dow Jones Newswires

January 25, 2022 02:00 ET (07:00 GMT)

Base Resources (LSE:BSE)
Historical Stock Chart
From Jun 2024 to Jul 2024 Click Here for more Base Resources Charts.
Base Resources (LSE:BSE)
Historical Stock Chart
From Jul 2023 to Jul 2024 Click Here for more Base Resources Charts.