IREN (NASDAQ: IREN) (together with its subsidiaries, “IREN” or “the
Company”), today published its monthly investor update for October
2024.
Key Highlights
AI
Cloud Services |
Bitcoin Mining |
- Additional 1,080 NVIDIA H200 GPUs being commissioned
- Preparing data centers for liquid-cooled Blackwell GPUs
|
- 439 Bitcoin mined
- 21 EH/s installed (16 J/TH efficiency); 31 EH/s in 4Q 2024
|
Data Centers |
Corporate |
- 1.4GW site target energization now April 2026
- Ongoing discussions with multiple hyperscalers regarding
monetization structures
|
- 1Q FY25 earnings to be released in coming weeks
|
Key Metrics |
Oct-24 |
Sep-24 |
Aug-24 |
AI Cloud Services |
|
|
|
AI Cloud Services revenue |
$1.0m |
$0.7m |
$1.3m |
Electricity costs |
($0.03m) |
($0.01m) |
($0.02m) |
Hardware profit margin1 |
97% |
98% |
98% |
Bitcoin Mining2 |
|
|
|
Average operating
hashrate |
19.9 EH/s |
16.5 EH/s |
10.9 EH/s |
Bitcoin mined |
439 BTC |
347 BTC |
245 BTC |
Revenue (per Bitcoin) |
$64,165 |
$61,604 |
$61,150 |
Electricity cost (per
Bitcoin) |
($20,834) |
($23,603) |
($29,958) |
Mining revenue |
$28.2m |
$21.4m |
$15.0m |
Electricity costs3 |
($9.1m) |
($8.2m) |
($7.3m) |
Hardware profit margin1 |
68% |
62% |
51% |
AI Cloud Services
Prince George NVIDIA H200 GPU cluster (November 2024)
AI Cloud Services
- 816 NVIDIA H100 GPUs:
Installed and operational
- 1,080 NVIDIA H200
GPUs: Currently being commissioned
- 1,896 H100 & H200 GPUs utilize
less than 0.5% of IREN’s data center capacity4, supporting $32m of
illustrative annualized hardware profit5
- Design and procurement underway to
accommodate liquid-cooled hardware, including NVIDIA Blackwell
GB200 GPUs
Bitcoin Mining
On track for 31 EH/s in 4Q
- Remaining S21 XP miner deliveries
ongoing (13.5 J/TH), with final shipments scheduled for
November
- 31 EH/s supports $344m illustrative
annualized hardware profit5
October operations highlights
- Monthly revenue:
Increased by 32% to $28.2m, driven by ramp-up in operating
hashrate to 21 EH/s and higher Bitcoin prices
- Operating hashrate:
Averaged 20 EH/s, including voluntary power price curtailment
at Childress and ongoing T21 miner issues, currently being
resolved with Bitmain
- Electricity cost
reductions: 12% reduction in electricity cost per Bitcoin
mined, driven by an increased contribution from Childress, which
offers lower unit electricity costs
- Electricity cost at
Childress: 3.06 c/kWh in October
Data Centers
Childress Phase 4 (November 2024)
510MW of data centers in 2024
- Childress Phase 3 (150MW): 4Q 2024
- Substation transformer installed
- DC building construction and electrical works ongoing
- Supports expansion to 31 EH/s in 2024
- Childress Phase 4 – 6: 2025+ expansion
- Civil works and procurement of long lead items ongoing
- Data center building foundation construction underway for Phase
4
1.4GW site timeline accelerated
- Target energization date for 1.4GW substation brought forward
to April 2026
- Procurement underway for key electrical items, including
transformers and circuit breakers to support 1.4GW bulk and primary
substations
- 800 acres of additional land secured (>1,300 total)
Monetization opportunities
- Ongoing discussions
with multiple hyperscalers regarding monetization structures,
including powered land leases, colocation, and
build-to-suit options
- Morgan Stanley
process remains in progress
Data Center |
Capacity (MW) |
Capacity
(EH/s)6 |
Timing |
Status |
Canal Flats (BC, Canada) |
30 |
1.6 |
Complete |
Operating |
Mackenzie (BC, Canada) |
80 |
5.2 |
Complete |
Operating |
Prince George (BC,
Canada) |
50 |
3.0 |
Complete |
Operating |
Childress (Texas, USA) |
200 |
11.1 |
Complete |
Operating |
Total
Operating |
360 |
21 |
|
|
Childress Phase 3 (Texas,
USA) |
150 |
10 |
4Q 2024 |
Under construction |
Childress Phase 4 - 5 (Texas,
USA) |
300 |
20 |
2025 |
Under construction |
Childress Phase 6 (Texas,
USA) |
100 |
|
2025 |
Under construction |
Total Operating &
Construction |
910 |
50 |
|
|
Development Site (Texas,
USA) |
1,400 |
|
2Q 2026 |
Connection underway |
Additional Pipeline |
>1,000 |
|
|
Development |
Total |
>3,000 |
|
|
|
|
|
|
|
|
Corporate
CheatCode Conference, Sydney (October 2024)
Upcoming events
- Cantor Crypto, Digital Assets & AI
Infrastructure Conference, Miami (Nov 13 – 14, 2024)
- SC24, Atlanta (Nov 17 – 22,
2024)
- Roth Technology Conference, New
York (Nov 19 – 20, 2024)
- B Riley Crypto & Energy
Infrastructure Conference, New York (Dec 4, 2024)
Assumptions and Notes
- Hardware profit margin for Bitcoin mining and AI Cloud Services
is calculated as revenue less net electricity costs, divided by
revenue (for each respective revenue stream) and excludes all other
costs.
- Bitcoin and Bitcoin mined in this investor update are presented
in accordance with our revenue recognition policy which is
determined on a Bitcoin received basis (post deduction of mining
pool fees).
- Electricity costs are presented on a net basis and calculated
as IFRS electricity charges net of realized gain/(loss) on
financial assets (excluding one-off cost of $7.2m to close out
August and September 2024 power hedges, as part of the transition
to spot pricing), ERS revenue (included in other income) and ERS
fees (included in other operating expenses). Figures are based on
current internal estimates and exclude REC purchases.
- Assumes 1.25kW power draw per GPU, 510MW of operating data
center capacity (by end of 2024) and 1,896 NVIDIA H100 and H200
GPUs.
- Illustrative Annualized Hardware Profit = illustrative revenue
less assumed electricity costs (excludes all other site, overhead
and Renewable Energy Certificate (“REC”) costs). Calculations
assume hardware operates at 100% uptime. AI Cloud Services
calculations assume 1.25kW power draw per GPU, $0.045/kWh
electricity costs and lower end of a $2.00 - $2.50 per GPU hour
revenue assumption range. Bitcoin mining calculations assume
$70,000 (Bitcoin price), 728 EH/s (global hashrate), 3.125 BTC
(block reward), 0.1 BTC (transaction fees), 0.15% (pool fees),
484MW (power consumption), $0.038/kWh electricity costs (4.5c/kWh
BC, 3.5c/kWh Childress). See Forward-Looking Statements disclaimer
below, including Non-IFRS Financial Measures.
- Capacity to be installed comprises combination of Bitmain S21
Pro and S21 XP miners.
Contacts
MediaJon
Snowball Sodali & Co+61 477 946 068 |
InvestorsLincoln
Tan IREN+61 407 423 395 lincoln.tan@iren.com |
Danielle GhiglieraAircover
Communications+1 510 333 2707 |
|
|
|
To keep updated on IREN’s news releases and SEC
filings, please subscribe to email alerts at
https://iren.com/investor/ir-resources/email-alerts.
Forward-Looking Statements
This investor update includes “forward-looking
statements” within the meaning of the Private Securities Litigation
Reform Act of 1995. Forward-looking statements generally relate to
future events or IREN’s future financial or operating performance.
For example, forward-looking statements include but are not limited
to the Company’s business strategy, expected operational and
financial results, and expected increase in power capacity and
hashrate. In some cases, you can identify forward-looking
statements by terminology such as “anticipate,” “believe,” “may,”
“can,” “should,” “could,” “might,” “plan,” “possible,” “project,”
“strive,” “budget,” “forecast,” “expect,” “intend,” “target”,
“will,” “estimate,” “predict,” “potential,” “continue,” “scheduled”
or the negatives of these terms or variations of them or similar
terminology, but the absence of these words does not mean that
statement is not forward-looking. Such forward-looking statements
are subject to risks, uncertainties, and other factors which could
cause actual results to differ materially from those expressed or
implied by such forward-looking statements. In addition, any
statements or information that refer to expectations, beliefs,
plans, projections, objectives, performance or other
characterizations of future events or circumstances, including any
underlying assumptions, are forward-looking.
These forward-looking statements are based on
management’s current expectations and beliefs. These statements are
neither promises nor guarantees, but involve known and unknown
risks, uncertainties and other important factors that may cause
IREN’s actual results, performance or achievements to be materially
different from any future results performance or achievements
expressed or implied by the forward looking statements, including,
but not limited to: Bitcoin price and foreign currency exchange
rate fluctuations; IREN’s ability to obtain additional capital on
commercially reasonable terms and in a timely manner to meet its
capital needs and facilitate its expansion plans; the terms of any
future financing or any refinancing, restructuring or modification
to the terms of any future financing, which could require IREN to
comply with onerous covenants or restrictions, and its ability to
service its debt obligations, any of which could restrict its
business operations and adversely impact its financial condition,
cash flows and results of operations; IREN’s ability to
successfully execute on its growth strategies and operating plans,
including its ability to continue to develop its existing data
center sites and to diversify and expand into the market for high
performance computing (“HPC”) solutions it may offer (including the
market for AI Cloud Services); IREN’s limited experience with
respect to new markets it has entered or may seek to enter,
including the market for HPC solutions (including AI Cloud
Services); expectations with respect to the ongoing profitability,
viability, operability, security, popularity and public perceptions
of the Bitcoin network; expectations with respect to the
profitability, viability, operability, security, popularity and
public perceptions of any current and future HPC solutions
(including AI Cloud Services) that IREN offers; IREN’s ability to
secure and retain customers on commercially reasonable terms or at
all, particularly as it relates to its strategy to expand into
markets for HPC solutions (including AI Cloud Services); IREN’s
ability to manage counterparty risk (including credit risk)
associated with any current or future customers, including
customers of its HPC solutions (including AI Cloud Services) and
other counterparties; the risk that any current or future
customers, including customers of its HPC solutions (including AI
Cloud Services), or other counterparties may terminate, default on
or underperform their contractual obligations; Bitcoin global
hashrate fluctuations; IREN’s ability to secure renewable energy,
renewable energy certificates, power capacity, facilities and sites
on commercially reasonable terms or at all; delays associated with,
or failure to obtain or complete, permitting approvals, grid
connections and other development activities customary for
greenfield or brownfield infrastructure projects; IREN’s reliance
on power and utilities providers, third party mining pools,
exchanges, banks, insurance providers and its ability to maintain
relationships with such parties; expectations regarding
availability and pricing of electricity; IREN’s participation and
ability to successfully participate in demand response products and
services and other load management programs run, operated or
offered by electricity network operators, regulators or electricity
market operators; the availability, reliability and/or cost of
electricity supply, hardware and electrical and data center
infrastructure, including with respect to any electricity outages
and any laws and regulations that may restrict the electricity
supply available to IREN; any variance between the actual operating
performance of IREN’s miner hardware achieved compared to the
nameplate performance including hashrate; IREN’s ability to curtail
its electricity consumption and/or monetize electricity depending
on market conditions, including changes in Bitcoin mining economics
and prevailing electricity prices; actions undertaken by
electricity network and market operators, regulators, governments
or communities in the regions in which IREN operates; the
availability, suitability, reliability and cost of internet
connections at IREN’s facilities; IREN’s ability to secure
additional hardware, including hardware for Bitcoin mining and any
current or future HPC solutions (including AI Cloud Services) it
offers, on commercially reasonable terms or at all, and any delays
or reductions in the supply of such hardware or increases in the
cost of procuring such hardware; expectations with respect to the
useful life and obsolescence of hardware (including hardware for
Bitcoin mining as well as hardware for other applications,
including any current or future HPC solutions (including AI Cloud
Services) IREN offers); delays, increases in costs or reductions in
the supply of equipment used in IREN’s operations; IREN’s ability
to operate in an evolving regulatory environment; IREN’s ability to
successfully operate and maintain its property and infrastructure;
reliability and performance of IREN’s infrastructure compared to
expectations; malicious attacks on IREN’s property, infrastructure
or IT systems; IREN’s ability to maintain in good standing the
operating and other permits and licenses required for its
operations and business; IREN’s ability to obtain, maintain,
protect and enforce its intellectual property rights and
confidential information; any intellectual property infringement
and product liability claims; whether the secular trends IREN
expects to drive growth in its business materialize to the degree
it expects them to, or at all; any pending or future acquisitions,
dispositions, joint ventures or other strategic transactions; the
occurrence of any environmental, health and safety incidents at
IREN’s sites, and any material costs relating to environmental,
health and safety requirements or liabilities; damage to IREN’s
property and infrastructure and the risk that any insurance IREN
maintains may not fully cover all potential exposures; ongoing
proceedings relating to the default by two of IREN’s wholly-owned
special purpose vehicles under limited recourse equipment financing
facilities; ongoing securities litigation relating in part to the
default; and any future litigation, claims and/or regulatory
investigations, and the costs, expenses, use of resources,
diversion of management time and efforts, liability and damages
that may result therefrom; IREN's failure to comply with any laws
including the anti-corruption laws of the United States and various
international jurisdictions; any failure of IREN's compliance and
risk management methods; any laws, regulations and ethical
standards that may relate to IREN’s business, including those that
relate to Bitcoin and the Bitcoin mining industry and those that
relate to any other services it offers, including laws and
regulations related to data privacy, cybersecurity, the storage,
use or processing of information and consumer laws; IREN’s ability
to attract, motivate and retain senior management and qualified
employees; increased risks to IREN’s global operations including,
but not limited to, political instability, acts of terrorism, theft
and vandalism, cyberattacks and other cybersecurity incidents and
unexpected regulatory and economic sanctions changes, among other
things; climate change, severe weather conditions and natural and
man-made disasters that may materially adversely affect IREN’s
business, financial condition and results of operations; public
health crises, including an outbreak of an infectious disease (such
as COVID-19) and any governmental or industry measures taken in
response; IREN’s ability to remain competitive in dynamic and
rapidly evolving industries; damage to IREN’s brand and reputation;
expectations relating to Environmental, Social or Governance issues
or reporting; the costs of being a public company; and other
important factors discussed under the caption “Risk Factors” in
IREN’s annual report on Form 20-F filed with the SEC on August 28,
2024 as such factors may be updated from time to time in its other
filings with the SEC, accessible on the SEC’s website at
www.sec.gov and the Investor Relations section of IREN’s website at
https://investors.iren.com.
These and other important factors could cause
actual results to differ materially from those indicated by the
forward-looking statements made in this investor update. Any
forward-looking statement that IREN makes in this investor update
speaks only as of the date of such statement. Except as required by
law, IREN disclaims any obligation to update or revise, or to
publicly announce any update or revision to, any of the
forward-looking statements, whether as a result of new information,
future events or otherwise.
Preliminary Financial Information
The preliminary financial information included
in this investor update is not subject to the same closing
procedures as our unaudited quarterly financial results and has not
been reviewed by our independent registered public accounting firm.
The preliminary financial information included in this investor
update does not represent a comprehensive statement of our
financial results or financial position and should not be viewed as
a substitute for unaudited financial statements prepared in
accordance with International Financial Reporting Standards.
Accordingly, you should not place undue reliance on the preliminary
financial information included in this investor update.
Non-IFRS Financial Measures
This investor update includes non-IFRS financial
measures, including electricity costs (presented on a net basis)
and hardware profit. We provide these measures in addition to, and
not as a substitute for, measures of financial performance prepared
in accordance with IFRS. There are a number of limitations related
to the use of non-IFRS financial measures. For example, other
companies, including companies in our industry, may calculate these
measures differently. The Company believes that these measures are
important and supplement discussions and analysis of its results of
operations and enhances an understanding of its operating
performance.
Electricity costs are calculated as our IFRS
Electricity charges net of Realized gain/(loss) on financial asset,
ERS revenue (included in Other income) and ERS fees (included in
Other operating expenses), and excludes the cost of RECs.
Illustrative Annualized Hardware Profit is
calculated as illustrative revenue less assumed electricity costs
(excludes all other site, overhead and REC costs).
Photos accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/d9cfbc2b-770d-4a01-a838-f4de9ecaf582
https://www.globenewswire.com/NewsRoom/AttachmentNg/45f15c65-2054-4be5-9155-b9bb5d442f21
https://www.globenewswire.com/NewsRoom/AttachmentNg/b5030972-11ed-4116-9a12-80c1cb0292d9
https://www.globenewswire.com/NewsRoom/AttachmentNg/8f3d2462-93a0-472e-abfd-8b8a15959c4c
IREN (NASDAQ:IREN)
Historical Stock Chart
From Nov 2024 to Dec 2024
IREN (NASDAQ:IREN)
Historical Stock Chart
From Dec 2023 to Dec 2024