maintenance in early 2012, the Co. 
                              said on Aug. 5. 
 
Phillips Belle Chasse  247.0  Refinery up for sale a 
66       LA                   Nov. 29 Bloomberg News 
                              report said. 
 
Valero   McKee    TX   170.0  FCCU in restart after turnaround   May 11 
                              that began on Mar 31 the co. said 
                              on May 11. 
 
                              Vacuum unit turnaround planned in 
                              first half of 2012, company said. 
 
                              Expansion project announced 
                              March 2011 to increase crude oil 
                              throughput by 25,000 b/d to 
                              195,000 b/d. 
 
Valero   Meraux, LA    135.0  Co. on May 16 said the alky and    June 1 
                              FCCU shut Jan 2 for turnaround 
                              are restarting and at normal rates 
                              by June 1. 
 
Valero   Norco, LA     185.0  Hydrocracker project will pro-     2013 
                              ceed and be completed in late 
                              2013, the co. said on 7/27/10. 
 
                              Upgrade project to build           2012 
                              a new diesel hydrotreater 
                              unit moved from 2010 to 
                              4Q 2012. 
 
Valero   Port Arthur   325.0  Hydrocracker project will pro-     2012 
         TX                   ceed and be completed in late 
                              2012. 
 
 
MIDWEST 
 
Citgo    Lemont, IL    167.0  FCCU restarted on May 17; unclear  May 17 
                              when unit shut down. Equipment 
                              failure and emissions reported 
                              on May 10. 
 
                              Portion of refinery shut for       May 29 
                              30 days of planned maintenance, 
                              on Apr 29 the co. said. No 
                              details provided. 
 
CVR      Wynnewood      54.0  30-40 days maintenance planned     Q3 
         OK                   in 3rd Q 2013, the co. said on     2013 
                              Nov. 3, 2011. 
 
Holly    Tulsa, OK     125.0  The entire refinery will be shut   Late 
Frontier                      while West Plant section under-    2012 
                              goes major turnaround maintenance 
                              in late 2012, the Co. said on 
                              Aug. 5, 2011. 
 
Husky    Lima, OH      160.0  15-days of maintenance at diesel   4Q 
Energy                        hydrotreater; 29-day at aromatics  2012 
                              unit set for 4Q 2012, the co. 
                              on Feb 9. 
 
                              New 20,000-b/d kerosene hydro-     1stH 
                              treater will start up in 1st       2013 
                              half 2013, to co. said on Feb 9, 
                              2012. 
 
                              45-days of major turnaround 
                             scheduled in 2014; 70% of units 
                              involved. Remaining 30% will under 
                              go major turnaround in 2015, the 
                              co. said on Feb 9, 2012. 
 
Husky    Toledo, OH    140.0  Minor turnaround planned in mid-   mid-2012 
Energy                        2012; the partial outage will 
                              last about 21 days, the co. said 
                              on Feb. 9. 
 
Tesoro   Mandan, ND     58.0  Total crude-oil processing capa-   2nd Q 
                              city to increase by 17% to 68,000  2012 
                              b/d by 2nd quarter 2012. 
 
ROCKIES 
 
WEST COAST 
 
Alon     Bakersfield    14.5  Hydrocraker Unit to restart        Mid-May 
         CA                   mid-May traders said on May 4. 
 
BP       Carson, CA    265.0  Planned flaring may occur 
                              May 15-21; not associated with 
                              equipment breakdown- filing. 
 
Chevron  Richmond      246.0  Source on May 14 said units in-    May 28 
         CA                   volved in May 12 planned shutdown 
                              include FCCU and hydrotreater. 
                              Work to last for two weeks. 
 
Shell    Martinez      156.4  Scheduled work (unspecified) 
         CA                   is underway, the co. said on 
                              Apr 27. Traders said crude and 
                              coker unit involved; end date 
                              not provided. 
 
Tesoro   Martinez      166.0  Hydrocracker has been shut for     May 11- 
                              two weeks of maintenance, traders      13 
                              said on May 2. 
 
 
Imperial Oil (AMEX:IMO)
Historical Stock Chart
From Jun 2024 to Jul 2024 Click Here for more Imperial Oil Charts.
Imperial Oil (AMEX:IMO)
Historical Stock Chart
From Jul 2023 to Jul 2024 Click Here for more Imperial Oil Charts.