DOW JONES NEWSWIRES
The following table lists unplanned and planned production
outages at U.S. refineries as reported by Dow Jones Newswires. The
information is compiled from both official and unofficial refining
sources and doesn't purport to be a comprehensive list.
Exxon Mobil Corp. (XOM) reported a pump failure at its 560,000
barrel-a-day refinery in Baytown, Texas, according to a government
filing made public Sept. 14. There was no impact to supply, the
company said.
A pipe leak at Citgo Petroleum Corp.'s oil refinery in Lemont,
Illinois, caused a compressor shutdown on Sep. 13 and resulted in
an emissions release. Efforts to repair the leak and restart the
compressor are on-going, a report by the U.S. National Response
Center said. The compressor is used in sulfur recovery, the filing
said.
Valero Energy Corp. (VLO) reported a compressor malfunction and
flaring at its refinery in Benicia, Calif., according to a
government filing made public Sep. 13. The problem had no material
impact on production, Valero spokesman Bill Day said.
ConocoPhillips (COP) on Sep. 12 reported flaring because of a
unit startup at its Rodeo, Calif., a government filing said. No
further details were provided.
Marathon Petroleum Corp. (MPC) said Sept. 12 it successfully
restarted the FCCU at the company's 210,000 barrel-a-day refinery
in Catlettsburg, Ken., during the weekend. The unit had been down
after a fire on Aug. 17.
Total shut down a crude distillation unit over the weekend at
its 232,00 barrel-a-day refinery in Port Arthur, Texas, traders
said Sept. 12. The company planned the unit to be back up within
the week, traders said.
Exxon Mobil Corp. (XOM) on Sep. 12 said planned work at its
joint venture refinery in Chalmette, La., caused emissions at the
sulfur plant on Sep. 11. The work is expected to continue for less
than two weeks and is not expected to impact production.
PBF Energy's 193,000 barrel-a-day refinery in Delaware City,
Del., experienced an emissions release of sulfur dioxide on Sep. 9
due to maintenance at the plant's hydrocracking unit, not the key
gasoline-making fluid catalytic cracking unit as had been reported
to state regulators. The company declined to estimate when the unit
would restart.
Valero Energy Corp. (VLO) said on Sep. 9 maintenance at a
hydrocracking unit at its oil refinery in Benicia, Calif., had no
material impact to production. The work resulted in a release of
sulfur dioxide to the plant's safety flare system, according to a
filing to the California Emergency Management Agency earlier on
Sep. 9.
Tesoro Corp. (TSO) on Sep. 9 said its Los Angeles-area refinery
in Wilmington, Calif. was ramping towards targeted rates following
an off-site power interruption the day before.
For more detailed information, search Dow Jones Newswires using
the code N/REF.
Operator Refinery Capacity Description Restart
(in 000s
bbl/day)
UNPLANNED
CANADA
CARIBBEAN
EAST COAST
PBF Delaware 193.0 FCCU snag on Sep. 9 results in
Energy City, DE emissions; status of unit un-
clear.
GULF COAST
Conoco Belle Chasse 247.0 Equipment malfunction occurred on
Phillips La. Sep. 4 while refinery was opera-
ting at very low rates due to
Tropical Storm Lee. No details
were provided.
Flint Corpus 300.0 Second power disruption in as
Hills Christi, TX many days shut West Refinery on
Sep. 4. On Sep. 3 the Mid-Plant
Complex and an SRU resumed nor-
mal operations after a brief
power snag.
Total Port Arthur 232.0 Crude unit shut, traders said Sep. 19
TX on Sep. 12; coker 'blow out'
reported to NRC. Restart seen
by about Sep. 19.
Refinery resumed normal rates
on Sep. 7 after early-day up-
set at sulfur recovery area.
MIDWEST
Citgo Lemont, IL 167.0 Pipe leak on Sep. 13 caused a
compressor shutdown and emis-
sions, an NRC report said.
Exxon Channahon 268.0 Power failure on Sep. 3 causes
Mobil IL emissions and flaring; impact
on production unclear.
Marathon Catlettsburg 210.0 FCCU restarted Sep 10-11 after Sep 11
KY Aug. 17 shutdown due to fire.
ROCKIES
Sinclair Sinclair 74.0 Refinery at reduced rates fol-
WY lowing fires at CDU on Sep. 3
and Sep. 4. Repairs and damage
assessments underway, the co.
said on Sep.6.
Exxon Billings, 60.0 Production at minimum rates due
MT to ruptured Silvertip Pipeline.
Company looking for alternative
crude sources, the co. said on
July 5.
WEST COAST
Conoco Rodeo, CA 120.0 Emissions/flaring reported on
Phillips Sep. 12 owing to unspecified
unit start-up.
Tesoro Wilmington 92.0 Refinery returning to targeted
rates on Sep. 9 following an
off-site power outage the day
before.
PLANNED
CANADA
CARIBBEAN
EAST COAST
Sunoco Philadelphia 335.0 Refineries up for sale on
Marcus Hook 190.0 Sep. 6; process units will
be shuttered in July 2012
if no buyer is found.
GULF COAST
Alon Big Spring 67.0 FCCU turnaround maintenance under-
TX way, a filing to environmental reg-
ulators made public on July 24 said.
Exxon Chalmette 192.5 Planned maintenance started Sep.
Mobil LA 11 at sulfur plant; emissions re-
ported to NRC. Work will end in
less than 2 weeks with no impact on co.
said on Sep. 12.
Motiva Port Arthur 285.0 Expansion project to increase 1Q
TX throughput capacity by 325,000 2012
b/d, to 610,000-b/d, slowed.
Completion now seen 1Q
2012, from 2010.
Valero Corpus 315.0 Crude & coker unit turnaround Oct.
Christi, TX to start in Oct. for three 2011
weeks.
Valero McKee TX 170.0 Crude Unit and FCCU to undergo 3Q 2011
turnaround maintenance for six
weeks starting in Oct. 2011, the
co. said on July 26.
Vacuum unit turnaround planned for
first half of 2012, co. said.
Expansion project announced
March 2011 to increase crude oil
throughput by 25,000 b/d to
195,000 b/d.
Valero Norco, LA 185.0 Hydrocracker project will pro- 2013
ceed and be completed in late
2013, the co. said on 7/27/10.
Upgrade project to build 2012
a new diesel hydrotreater
unit moved from 2010 to
4Q 2012.
Valero Port Arthur 325.0 Hydrocracker project will pro- 2012
TX ceed and be completed in late
2012.
MIDWEST
BP Whiting, IN 405.0 Turnaround at Pipestill 12 de-
layed by 3 months; it was sup-
posed to begin in November, a
source said on Mar 25.
Cenovus Roxana, IL 306.0 Coker and refinery expansion Q4 2011
(Conoco/WRB) project on track for comple-
tion 4th Q 2011, the co. said
on July 26, 2011.
CVR Coffeyville 115.7 Periodic turnaround will take 2012
KS place in two phases beginning in
Fall 2011 and completed in Spring
2012.
Husky Lima, OH 160.0 15-day isocracker maintenance to
Energy replace reactor catalyst will be-
gin in 3rd Q 2011. Refinery will
operate at 90% of capacity during
that time.
15-days of maintenance planned Autumn
at aromatics unit in the fall 2012
of 2012.
Husky Toledo, OH 140.0 Isocracker maintenance and gen-
Energy eral maintenance for 38 days will
commence in Q3 2011, the Co. said
on July 28.
Minor maintenance planned in 4Q
2011, the co. said on July 28;
no details provided.
Tesoro Mandan, ND 58.0 Total crude-oil processing capa- 2nd Q
city to increase by 17% to 68,000 2012
b/d by 2nd quarter 2012.