The following table lists unplanned and planned production outages at U.S. refineries as reported by Dow Jones Newswires. The information is compiled from both official and unofficial refining sources and doesn't purport to be a comprehensive list.

BP PLC (BP, BP.LN) on May 7 notified Texas state environmental regulators of its plan to restart several residual hydrotreating unit, or RHU, trains as part of its efforts to bring its Texas City, Texas, refinery back to normal processing rates. Gasoline production resumed on May 3 for the first time since a power outage caused the shut down of the entire plant, a person familiar with operations there said.

Sunoco (SUN) said on May 5 that its Philadelphia and Marcus Hook refineries in Pennsylvania were operating at planned rates following multiple outages.

Frontier Oil Corp. (FTO) on May 5 said its Cheyenne refinery should return to targeted run rates next week after undergoing an equipment upgrades. The company has no maintenance planned for any of its refineries for the remainder of the year.

Holly Oil Corp. (HOC) on May 5 said a crude-distillation unit at the Tulsa refinery should be back to normal next week after shutting down on April 22 for unplanned maintenance.

Citgo Corp. on May 5 briefly shut a coker unit at its Corpus Christi, Texas, refinery for maintenance.

Valero Energy Corp. (VLO) on May 4 said its refinery in Aruba was nearing planned rates after restarting a crude unit shut last week for unplanned maintenance.

PBF Energy on May 4 said its Paulsboro, New Jersey, refinery is up and running after recently concluding planned turnaround maintenance. PBF's Delaware City refinery is on track to start up in 2nd quarter 2011.

Valero Energy Corp. (VLO) on May 3 said its Texas City, Texas, refinery had resumed normal processing rates following last weeks power-related plant wide shutdown.

ConocoPhillips (COP) on May 3 said its Wilmington, California, refinery had resumed normal operations after a power dip on May 2 shut down several processing units.

Tesoro Corp. (TSO) on May 2 said planned maintenance that began on April 28 at its Anacortes, Washington, refinery had no impact on operations. The work was expected to conclude on May 2 a filing to environmental regulators said.

 
 
   For more detailed information, search Dow Jones Newswires using the 
code N/REF. 
 
 
Operator   Refinery    Capacity   Description                   Restart 
                       (in 000s 
                       bbl/day) 
UNPLANNED 
 
CANADA 
 
CARIBBEAN 
 
Valero     Aruba       235.0  Refinery nearing planned rates    May 4 
                              on May 4 after restarting a 
                              crude unit shut last week to 
                              to repair a leak. 
 
EAST COAST 
 
Sunoco   Philadelphia  335.0  Refinery at planned rates after    May 
                              multiple outages, the co. said 
                              on May 5. 
 
 
GULF COAST 
 
BP       Texas City    437.0  Restart efforts continue; RHU      May 7 
         TX                   trains restarted on May 7. 
 
                              Several process units restarted    May 1-7 
                              a source said on May 2. It will 
                              take several days for the plant 
                              to reach normal rates. Power outage 
                              on Apr 25/26 resulted in plant wide 
                              shutdown. 
 
Citgo    Corpus        165.0  Coker unit shut for about six      May 5 
         Christi, TX          hours to repair a leak in a feed 
                              line on May 5. 
 
Valero   Texas City    214.0  Refinery at normal rates on May    May 3 
         TX                   3 after plant wide shutdown 
                              on April 26 due to a power failure. 
 
 
MIDWEST 
 
Holly    Tulsa, OK     125.0  Crude unit shut on April 22 for    May 8- 
Corp                          unplanned maintenance restarted;   15 
                              refinery should return to normal 
                              run rates in the week starting 
                              May 8, the co. said on May 5. 
 
 
ROCKIES 
 
WEST COAST 
 
Conoco   Wilmington    139.0  Several processing units re-       May 3 
         CA                   started and at normal rates on 
                              May 3 after shut down on May 2 
                              due to power dip. 
 
 
PLANNED 
 
CANADA 
 
Suncor   Edmonton      135.0  4 weeks of planned work starts 
                              Apr 22 at one of two crude units 
                              and associated equip. 
 
CARIBBEAN 
 
Hovensa  St. Croix     350.0  Restarting distillate desulfurizer  May 
                              unit No. 4 in May, Co. said April 
                              15. Unit was damaged by Feb. 11 
                              fire and a replacement one was 
                              brought online. 
EAST COAST 
 
PBF      Delaware      210.0  Plant expected to start up in      2nd Q 
                              in 2Q of 2011.                     2011 
 
PBF      Paulsboro     185.0  Refinery up and running after      May 4 
         NJ                   recently concluding planned 
                              turnaround maintenance, the co. 
                              said on May 4. 
 
Sunoco   Philadelphia  335.0  Refinery operating at planned      May 
         PA                   rates after multiple outages, 
                              the co. said on May 5. 
 
GULF COAST 
 
Lyondell Houston, TX   270.0  FCCU rate cut on Apr 22 follow- 
Basell                        upset. Unit status remains un- 
                              unclear on May 3; the co. won't 
                              comment. 
 
Motiva   Port Arthur   285.0  Expansion project to increase       1Q 
                              throughput capacity by 325,000      2012 
                              b/d, to 610,000-b/d, slowed. 
                              Completion now seen 1Q 
                              2012, from 2010. 
 
Pasadena Pasadena, TX   56.0  FCCU, 56,000-b/d, will be taken 
                              out of service Feb. 28 for 44 days 
                              days planned work. Co. preparing 
                              statement regarding the FCCU on 
                              May 2. 
 
Valero   McKee    TX   170.0  Vacuum unit turnaround planned for 
                              first half of 2012, co. said. 
 
                              Expansion project announced on 
                              March 2011 to increase crude oil 
                              throughput by 25,000 b/d to 
                              195,000 b/d. 
 
Valero   Norco, LA     250.0  Turnaround maintenance at FCCU      mid-May 
                              and alkylation unit seen ending 
                              by mid-May, the co. said on 
                              April 26. Work began on 3/7. 
 
                              Hydrocracker project will pro- 2013 
                              ceed and be completed in late 
                              2013, the co. said on 7/27/10. 
 
                              Upgrade project to build            2012 
                              a new diesel hydrotreater 
                              unit moved from 2010 to 
                              4Q 2012. 
 
Valero   Port Arthur   325.0  Hydrocracker project will pro-    2012 
         TX                   ceed and be completed in late 
                              2012. 
 
MIDWEST 
 
BP       Whiting, IN   405.0  Turnaround will start at the      End-May 
                              end of March at Reformer No. 4 
                              and alkylation unit for 60 days, 
                              source said on Mar 25. 
 
                              Turnaround at Pipestill 12 de- 
                              layed by 3 months; it was sup- 
                              posed to begin in November, a 
                              source said on Mar 25. 
 
Frontier Cheyenne, WY   47.0  Refinery to return to targeted     May 8- 
                              run rates week starting May 8      15 
                              after undergoing equipment up- 
                              grades, the co. said on May 5. 
 
CVR      Coffeyville   115.7  Periodic turnaround will take place 
         KS                   in two phases beginning in Fall 2011 
                              and completed in Spring 2012. 
 
Tesoro   Mandan, ND     58.0  Total crude-oil processing capa-    2nd Q 
                              city to increase by 17% to 68,000   2012 
                              b/d by 2nd quarter 2012. 
 
WEST COAST 
 
Conoco   Carson, CA   139.0   Planned maintenance under way at 
Phillips                      unspecified units the co. said 
                              on April 25. Traders said work 
                              is being performed at a crude 
                              an coker unit. 
 
Tesoro   Anacortes     120.0  Planned maintenance under way       May 2 
                              since April 29 expected to con- 
                              clude on May 2; no impact to 
                              production. 
 
 
Imperial Oil (AMEX:IMO)
Historical Stock Chart
From Jun 2024 to Jul 2024 Click Here for more Imperial Oil Charts.
Imperial Oil (AMEX:IMO)
Historical Stock Chart
From Jul 2023 to Jul 2024 Click Here for more Imperial Oil Charts.