The following table lists unplanned and planned production outages at U.S. refineries as reported by Dow Jones Newswires. The information is compiled from both official and unofficial refining sources and doesn't purport to be a comprehensive list.

ExxonMobil's (XOM) Beaumont, Texas, refinery experienced a small fire in a processing area Wednesday. It was extinguished quickly and the refinery continued to operate, a company representative said.

ExxonMobil Wednesday reported a flaring event at its Torrance, California, refinery to state environmental regulators; the cause of the release was unknown, the filing said.

LyondellBasell (LYB, LYB.B) said Tuesday a small fire broke out at its Houston refinery, but caused no major damage. It was extinguished within 20 minutes; there were no injuries. Operations at the plant had just returned to normal Monday, after a power outage caused a loss of steam forcing the shutdown of all process units.

Irving Oil Tuesday said all units at its Saint John refinery in New Brunswick, Canada, are back on line following extensive turnaround maintenance that began in late September. The refinery exports about 175,000 barrels of finished product to the U.S. a day accounting for about 19% of U.S. gasoline imports.

 
   For more detailed information, search Dow Jones Newswires using the code N/REF. 
 
 
Operator   Refinery    Capacity   Description                   Restart 
                       (in 000s 
                       bbl/day) 
UNPLANNED 
 
CANADA 
 
CARIBBEAN 
 
EAST COAST 
 
Conoco   Linden, NJ    238.0  Bayway has restarted 
                              units, including the FCCU, 
                              after a complete power outage 
                              early Oct. 25, a person familiar 
                              with the plant said Nov. 19. 
                              Power was restored at about 3 p.m. 
                              Oct. 26. 
 
Hess    Port Reading,  70.0   Company said on Nov. 19 that repair 
                              finished on an FCCU brought down 
                              after Nov. 12 power outage. No set 
                              restart date given. 
 
GULF COAST 
 
Alon    Big Springs,   67.0   Company said upset electrostatic 
        TX                    precipitator caused opacity on 
                              Nov. 19. 
 
Chevron  Pascagoula,   333.0  Leak in a process line caused 
        MS                    emissions on Nov. 13, regulatory 
                              filing said. 
 
Exxon    Beaumont, TX  344.5  Refinery continues to operate     Nov 24 
Mobil                         following a brief, small fire 
                              on Nov. 24, the Co. said. 
 
Lyondell Houston, TX   270.6  A small fire on Nov. 23 caused    n/a 
Basell                        no serious damage, no injuries. 
                              All units at normal rates the     Nov 22 
                              co. said on Nov. 22 after 
                              plantwide outage on Nov. 20. 
 
Motiva   Convent, LA   235.0  Unspecified unit failure caused 
                              emissions on Nov. 15, according to 
                              filing. 
 
MIDWEST 
 
BP/Husky Toledo, OH   160.0   Crude oil throughput was reduced  n/a 
                              by unspecified amount owing 
                              to Enbridge's crude oil Line 6B 
                              leak/closure since July 26. 
 
Exxon    Joliet, IL    239.0  Refinery operations may be af- 
                              fected by Enbridge's decision 
                              to reduce crude oil delivery rates 
                              on Line 6A while integrity in- 
                              spections continue. Co. not im- 
                              mediately available for comment 
                              on Oct. 13. 
 
Marathon Robinson, IL  206.0  Trade sources say crude unit      Oct 22- 
                              shut around Oct 16-17 for         25 
                              maintenance. Restart seen by 
                              Oct. 22 or 25. Co. wouldn't 
                              comment. 
 
ROCKIES 
 
WEST COAST 
 
Shell     Anacortes   145.0   A flare line erosion resulted in 
          WA                  emissions on Nov. 16. 
 
Tesoro    Anacortes,    120.0 Refinery at targeted rates after  Nov 16 
                              extensive reparis following the 
                              deadly April 2 explosion, the 
                              company said on Nov. 16. 
 
PLANNED 
 
CANADA 
 
Irving   New                  All units restarted following     Nov 23 
Oil      Brunswick            turnaround maintenance that 
                              began in late Sept. the co. 
                              said on Nov. 23. 
 
Shell    Montreal     130.0   The refinery will be converted 
         Quebec               into a terminal. 
 
CARIBBEAN 
 
Valero   Aruba        235.0   Turnaround maintenance that       late 
                              began in June is seen con-        Dec/ 
                              cluding late Dec or early Jan.    early 
                              The decision on whether           Jan 
                              units will be restarted after     2011 
                              the turnaround ends will be 
                              made at that time. 
 
EAST COAST 
 
Sunoco   Westville    145.0   Idling all Eagle Point refin-     n/a 
         NJ                   ing operations indefinitely due 
                              to poor economics, co. said 
                              Oct. 6, 2009. 
 
Valero   Delaware      210.0  PBF Energy has closed             Apr 
                              deal to buy plant. Petroplus      2011 
                              said May 5 the plant would be 
                              restarted in 2Q of 2011. 
 
Valero   Paulsboro, NJ 185.0  Agreed to sell refinery for 
                              $360 million to PBF Energy, 
                              Co. said Sept. 27. Deal is 
                              expected to close in Q4. 
 
Western  Yorktown       64.5  The refinery will close in        Sept 
         VA                   September 2010 for economic 
                              reasons. Terminal operations 
                              will continue. 
 
                              Maintenance had been planned 
                              for 3Q 2010. 
GULF COAST 
 
Chevron  Pascagoula  330.0    Pre-commercial heavy oil          2010 
         Miss.                conversion project delayed 
                              from 2008 to 2010 due to 
                              economic factors. 
 
                              Expansion project including 
                              the replacement of two 30-year- 
                              old reformers and construction 
                              of a 55,000 b/d continuous 
                              catalytic reformer platformer 
                              unit to be completed by late 
                              summer, Industrial Info 
                              Resources said July 6. A 
                              premium base-oil facility 
                              was also being planned, co. 
                              said in late Feb. 
 
Exxon    Baytown, TX   560.6  New ULSD Units commissioned, 
                              Co. said Oct 21. ULSD supply 
                              will increase by over 3 million 
                              gallons from Baytown & Baton 
                              Rouge. 
 
Exxon    Chalmette     120.0  Crude throughput will be re-      N/A 
         LA                   duced to 90,000-b/d as redun- 
                              dant units and about 70 jobs 
                              are taken out of service and 
                              cut for economic reason. These 
                              have begun to take place, the 
                              co. said Aug 26. 
 
                              $250 mln project for new Spring 2010 
                              diesel desulfurization, 
                              sulfur recovery unit to begin 
                              in Fall 2008. Construction 
                              to last 18 months. 
 
Motiva   Port Arthur   285.0  Expansion project to increase     1Q 
                              throughput capacity by 325,000    2012 
                              b/d, to 610,000-b/d, slowed. 
                              Completion now seen 1Q 
                              2012, from 2010. 
 
Valero   Corpus       340.0   West Plant 50,000-b/d FCCU at 
         Christi, TX          reduced rates since mid-Dec for 
                              economic reasons. 
 
Valero   Norco, LA    250.0   Hydrocracker project will pro-    2013 
                              ceed and be completed in late 
                              2013, the co. said on July 27. 
 
                              FCCU, 100,000 b/d, will be        2Q 
                              revamped and work will take       2011 
                              place atat alky unit, lasting 
                              55 days starting in March, Co. 
                              said Oct. 26. 
 
                              Upgrade project to build          2012 
                              a new diesel hydrotreater 
                              unit moved from 2010 to 
                              4Q 2012. 
 
Valero   Port Arthur  325.0   Hydrocracker project will pro-    2012 
         TX                   ceed and be completed in late 
                              2012, the co. said on July 27. 
 
 
 
                              Six coke drums will be re-        2011 
                              placed in 2011. 
 
                              77,000-b/d FCCU at reduced        n/a 
                              rates since mid-Dec for 
                              economic reasons. 
 
Valero   Sunray, TX   170.0   55,000-b/d FCCU at reduced        n/a 
                              rates since mid-Dec for 
                              economic reasons. 
 
                              Expanded crude gather system      4Q 
                              will increase available crude     2010 
                              supplies to refinery by 4Q. 
 
                              24-day turnaround to begin at     2Q 
                              30,000-b/d hydrocracker in        2011. 
                              March 2011. 
 
MIDWEST 
 
BP       Toledo, OH   155.0   $400 million upgrade              2012 
                              to start 2010. 
 
Husky    Lima, OH     160.0   Scheduled fall turnaround main- 
                              tenance finished on Nov. 19, 
                              rates to return to normal within 
                              a week, company said. 
 
Marathon Detroit, MI  106.0   Turnaround maintenance finished 
                              on Nov. 19 after getting 
                              underway Oct 10. Scope 
                              of work unclear. 
 
Valero   Ardmore, OK   90.0   Plant-wide turnaround planned;    2Q 
                              work will impact 1Q 2011          2011 
                              results. It will begin in March 
                              and last 40 days, Co. said 
                              Oct. 26 
ROCKY MOUNTAIN 
 
Suncor   Commerce      93.0   Planned work at reformer unit     Fall 
         City, CO             deferred to Fall 2010 from Feb    2010 
                              28 start date. 
 
WEST COAST 
 
BP       Carson, CA   265.0   Planned flaring occurred on       N/A 
                              Nov. 20, a filing to state re- 
                              gulators said. 
 
Valero   Benicia      170.0   Scrubber installation continues;  2010 
         CA                   work seen concluding by year-end, 
                              the co. said on July 27. 
 
                              Plantwide turnaround to begin in  1Q 
                              January and will last 36 days.    2011 
 
Tesoro   Golden Eagle 166.0   Major turnaround maintenance      2011 
         Martinez, CA         deferred to 2011 from late 
                              2009, the co. said Feb. 3. 
 
 
 
 
Imperial Oil (AMEX:IMO)
Historical Stock Chart
From Jun 2024 to Jul 2024 Click Here for more Imperial Oil Charts.
Imperial Oil (AMEX:IMO)
Historical Stock Chart
From Jul 2023 to Jul 2024 Click Here for more Imperial Oil Charts.