Keras Resources plc (AIM: KRS)
("Keras") is pleased to announce that dry commissioning ("C1"), of
its Integrated Granulator Plant ("Granulator Plant") at its newly
acquired Delta processing facility ("Delta") has commenced on
schedule. C1 involves energisation of motors for directional
checking, start-up sequencing, instrument set-up and confirmation
that all installed items meet design requirements under no-load
conditions without dry feed materials or binding and dust control
liquids. With all equipment installed, C1 is a significant
milestone for Keras's 100% owned Falcon Isle Resources Corp
("Falcon Isle").
Given the scale of what was required
to transition from an outsourced production and ownership model
operating from three rental facilities to the Company's wholly
owned, fully integrated production facility at Delta in just four
months, which was underpinned by the conclusion of the Phosul Utah
LLC joint venture ("JV") as announced on 22 January 2024, has been
an outstanding achievement by the project team as well as the
Company's supportive funding partners.
The project team will now work
towards wet commissioning under load conditions with granulator
binder fluids ("C2") during the first half of June 2024 which will
initially comprise test granulation of Falcon Isle's rock phosphate
before introducing the additional constituents of the Phosul® final
product. The Granulator Plant has a nameplate capacity of 5 tonnes
per hour of finished product. At steady-state single shift
operation, the Granulator Plant is planned to produce approximately
520 tons per month ("tpm"), working towards upgrading to double
shift operations during the fourth quarter of 2024 to produce
approximately 920tpm of saleable bulk Phosul® granules. The Phosul®
formula comprises 80% of 50 mesh PhosAgri feed produced from ore
mined at the Diamond Creek mine, Falcon Isle's wholly owned, high
grade organic phosphate mine. Falcon Isle currently holds inventory
of approximately 4,250tons of 50# PhosAgri product, sufficient to
cover Granulator Plant operations for the rest of 2024 which,
importantly, will have a positive impact on cashflow with all
mining and crushing costs already expensed.
Graham Stacey, CEO of Keras,
commented, "Having made the decision
to migrate operations from Spanish Fork, acquiring the Delta
Property and achieving C1 commissioning on schedule in the space of
four months has been an outstanding achievement from both our
project team but also with the support of our funding
partners.
As
we now move into C2 commissioning and build up to steady-state
commercial production of Phosul® granules, the value add of the
Phosul Utah LLC JV will underpin our traditional PhosAgri markets
and significantly increase the footprint of our sales in North
America. Having the Phosul LLC team as partners, who have five
years of both producing and importantly marketing Phosul® from
their Sugar City, Idaho facility is key to achieving our growth
strategy and we look forward to working with their team going
forward.
As
always, I encourage shareholders and potential investors to view
our social media posts to get a sense of the physical progress
achieved in Delta to date. I look forward to updating shareholders
on progress as we now move towards the final commissioning and
ramp-up phase of the integrated Granulator
Plant."
The information contained within
this announcement is deemed by the Company to constitute inside
information as stipulated under Article 7 of the Market Abuse
Regulation (EU) No. 596/2014 (as amended) as it forms part of the
domestic law of the United
Kingdom by virtue of
the European Union (Withdrawal) Act 2018 (as amended). Upon the publication
of this announcement via the Regulatory Information Service, this
inside information is now considered to be in the public
domain.
**ENDS**
For further information please
visit www.kerasplc.com,
follow us on Twitter @kerasplc or contact the
following:
Graham Stacey
|
Keras Resources plc
|
info@kerasplc.com
|
Nominated Adviser & Joint Broker
Ewan Leggat / Caroline
Rowe
Joint Broker
Damon Heath / Erik
Woolgar
|
SP Angel Corporate Finance
LLP
Shard Capital Partners
LLP
|
+44 (0) 20 3470 0470
+44 (0) 207 186 9900
|
Notes:
Keras Resources (AIM: KRS)
wholly owns the Diamond Creek organic
phosphate mine in Utah, US. Diamond Creek is one of
the highest-grade organic phosphate deposits in the US and is a
fully integrated mine to market operation with in-house mining and
processing facilities. The operation produces a variety of organic
phosphate products that can be tailored to customer
organic fertiliser requirements.
The Company is focused on continuing to increase market share in the
fast-growing US organic fertiliser market and build Diamond Creek
into the premier organic phosphate producer in the
US.