TIDMHOC
RNS Number : 7900H
Hochschild Mining PLC
17 July 2012
17 July 2012
Production Report for the 6 months ended 30 June 2012
Highlights
-- Q2 2012 attributable production of 5.2 million silver equivalent ounces
-- H1 2012 attributable production of 10.2 million silver equivalent ounces
-- On track to deliver 2012 attributable production target of 20.0 million silver equivalent ounces
-- Temporary accumulation of San Jose concentrate inventory at end Q2 2012 due to industry-wide regulatory changes
in Argentina; exports resumed and inventory to be sold in H2 2012
-- Continued progress at Inmaculada and Crespo Advanced Projects
-- Ongoing positive results from mines and brownfield exploration programme with significant intercepts reported and
continued discovery of new economic veins
-- Resource additions at current operations on track to meet annual target
-- Solid financial position with total cash of approximately $543m and minority investments of $413.6m as at 30 June
2012
Ignacio Bustamante, Chief Executive Officer, commented:
"I am pleased to report that we have delivered another robust
performance from our operations in the first half and are therefore
on track to achieve our 20.0 million attributable silver equivalent
ounce production target for 2012. Our record $90 million
exploration programme is also on course, with some encouraging
results already recorded from our current operations and our
ambitious 2012 greenfield drilling programme is also making good
progress."
Overview
In Q2 2012, Hochschild produced 5.2 million attributable silver
equivalent ounces, which comprised 3.5 million ounces of silver and
27.6 thousand ounces of gold. Overall, in the first half of 2012,
the Company has delivered attributable production of 10.2 million
silver equivalent ounces, including 6.9 million ounces of silver
and 55.9 thousand ounces of gold, placing it on track to achieve
its full year production target of 20.0 million attributable silver
equivalent ounces in 2012.
Production
Main operations
At Arcata, silver equivalent production of 1.8 million ounces in
Q2 2012 and 3.6 million ounces in H1 2012 was broadly in line with
the comparable periods of 2011, with an increase in treated tonnage
offset by lower silver grades. In addition, the volume of treated
low grade material from the Macarena Waste Dam deposit was similar
to the first half of 2011 but is expected to rise in the second
half with incremental plant capacity of 500 tonnes per day being
added to accommodate this increase. The Arcata dore project, to
process 100% of Arcata's concentrate, remains on schedule for
completion in the second half.
San Jose delivered another strong performance in the first half
of 2012, resulting from increased tonnages. Total silver equivalent
production increased by almost 18% in the second quarter versus the
same period of 2011, to 2.8 million ounces, with the half year
production rising by 4% versus H1 2011, to 5.4 million silver
equivalent ounces.
At Pallancata, despite an increase in production in the second
quarter versus Q1 2012, to 2.2 million total silver equivalent
ounces, overall half year production fell by 16% versus H1 2011, to
4.3 million ounces. This decrease was due to a decline in grades
resulting from two factors. Firstly, temporary delays in the mine
execution plan led to the treatment of an increased volume of lower
grade material from the mine (as disclosed in the Q1 2012
Production Report). In addition, the Company continues with its
previously-mentioned strategy of mining close to the average
reserve grade at each of its core operations in order to ensure a
consistent level of long-term production.
Other operations
The Company's ageing Ares mine in Peru continued to operate in
Q2 2012 and produced 470 thousand silver equivalent ounces,
bringing the H1 2012 production at Ares to 985 thousand silver
equivalent ounces. The Company continues to monitor production
closely at Ares to ensure the extraction of profitable ounces
during the last stage of its life cycle. Subject to additional
resources, and the price environment, production at Ares is
expected to continue throughout H2 2012. Exploration work is
continuing at Ares and some promising intercepts were reported
during the quarter.
At Moris, the Company's open pit operation in Mexico, despite
mine production having ceased in September 2011, continued leaching
of the pads produced a further 139 thousand silver equivalent
ounces in Q2 2012, bringing the first half total to 357 thousand
silver equivalent ounces. Moris remains in the final stages of the
pads' cyanidation process with exploration continuing at the
property.
Average realisable prices and sales
Average realisable precious metal prices (which are reported
before the deduction of commercial discounts) in Q2 2012 were
US$1,586.92/ounce for gold and US$26.08/ounce for silver. Average
realisable precious metal prices in H1 2012 were US$1,669.00/ounce
for gold and US$31.18/ounce for silver.
There was an accumulation in concentrate inventory at the San
Jose mine during Q2 2012 due to the impact of industry-wide
regulatory changes in Argentina that significantly reduced the time
allowancesduring which export contracts were required to be
settled. As at 30 June 2012, approximately 1.0 million silver
equivalent ounces of concentrate remained in finished goods
inventory. However, exports have now resumed and sales of this
inventory will be reflected in the second half sales figures.
Brownfield exploration(1)
San Jose
The exploration programme at San Jose continued to deliver
positive results in Q2 2012 with 28.9 thousand metres of
exploration drilling carried out to incorporate further resources
and new economic areas. A total of 43.6 thousand metres of
exploration drilling was carried out at San Jose in H1 2012. In Q2
2012, drilling took place on several veins with significant
intercepts including(1) :
Vein Results
-------- ------------------------------------------
Nuevo 1 SJD-1099 0.75m at 5.18 g/t Au & 216.32
g/t Ag
-------- ------------------------------------------
Kospi SJD-1100 2.45m at 6.37 g/t Au & 382.30
g/t Ag
-------- ------------------------------------------
Frea SJD-1119 1.70m at 3.11 g/t Au & 238.61
g/t Ag
-------- ------------------------------------------
Chenque SJD-1121 1.70m at 11.05 g/t Au & 1,186.36
g/t Ag
-------- ------------------------------------------
R350 SJD-1125 0.50m at 3.06 g/t Au & 329.63
g/t Ag
-------- ------------------------------------------
In H2 2012, the exploration programme in and around the San Jose
mine will continue and the geological map of the southern area of
the district will be completed. An estimated 46.4 thousand metres
of exploration drilling is planned for H2 2012.
Arcata
At Arcata, there were also positive results from the exploration
programme. A high grade resource was discovered in the Tunel 4 area
with the potential to not only increase the life of mine but to
also improve the average grade quality of the resource. During Q2
2012, 18.2 thousand metres of drilling was carried out at Arcata,
with exploration work focused on the definition of new high grade
structures and the incorporation of high quality resources from
known vein systems, as well as to provide further geological
interpretation of the district. Significant intercepts included(1)
:
Vein Results
-------- ------------------------------------
Tunel 4 DDH306-S-12 1.15m at 6.87 g/t Au &
2,387.39 g/t Ag
-------- ------------------------------------
Tunel 4 DDH312-S-12 1.08m at 3.38 g/t Au &
1,261.64 g/t Ag
-------- ------------------------------------
Tunel 4 DDH304-S-12 1.33m at 3.48 g/t Au &
2,815.12 g/t Ag
-------- ------------------------------------
Marion DDH216-GE-12 0.82m at 1.35 g/t Au &
428.86 g/t Ag
-------- ------------------------------------
Sandra DDH301-S-12 1.18m at 2.06 g/t Au &
1,059.53 g/t Ag
-------- ------------------------------------
In the second half, the near-mine exploration programme will
continue, with drilling focused on the definition of new high grade
structures and on improving the average grade of the resource. An
estimated 35.2 thousand metres of drilling is planned.
Pallancata
Exploration work at Pallancata in Q2 2012 focused on identifying
wider structures and the incorporation of new resources. During the
quarter, drilling continued at the Luisa, Pallancata Este, Ramal
Este and Teresa veins, with 13.9 thousand metres of diamond
drilling completed. Promising intercepts included(2) :
Vein Results
----------- ---------------------------------------
Luisa DLLU-A60 2.53m at 1.70 g/t Au & 313.28
g/t Ag
----------- ---------------------------------------
Luisa DLLU-A65 1.60m at 1.41 g/t Au & 447.02
g/t Ag
----------- ---------------------------------------
Luisa DLLU-A88 3.03m at 1.76 g/t Au & 522.69
g/t Ag
----------- ---------------------------------------
Ramal Este DLPE-A91 1.04m at 1.38 g/t Au & 358.50
g/t Ag
----------- ---------------------------------------
Teresa DLTE-A03 0.62m at 3.78 g/t Au & 497.97
g/t Ag
----------- ---------------------------------------
In H2 2012, exploration will focus on identifying new high grade
areas, with an estimated 22.9 thousand metres of drilling
planned.
Ares
Exploration work at Ares in Q2 2012 focused on identifying new
economic structures. During the quarter, 3.1 thousand metres of
drilling was carried out on the Olga, Isabel and Rosario veins.
Promising intercepts included(2) :
Vein Results
------- --------------------------------------
Olga AM-1482 2.65m at 0.13 g/t Au & 448.31
g/t Ag
------- --------------------------------------
Isabel AM-1482 6.05m at 0.44 g/t Au & 154.78
g/t Ag
------- --------------------------------------
Isabel AM-1481 0.60m at 0.54 g/t Au & 303.24
g/t Ag
------- --------------------------------------
Additional exploration initiatives have been approved for Ares
in order to continue expanding the life of mine. In H2 2012,
exploration will focus on the definition of new economic structures
outside of the mine premises, with an estimated 28.8 thousand
metres of drilling planned.
Moris
In Q2 2012, exploration work at Moris focused on identifying new
economic structures. During the quarter, 5.9 thousand metres of
drilling was carried out on the La Nopalera, Creston and Eureka
areas. Promising intercepts included(2) :
Vein Results
----------------------- --------------------------------------
Veta del Bajo San Luis BM-04 12.0m at 0.63 g/t Au & 0.18 g/t
Ag
----------------------- --------------------------------------
Veta del Bajo San Luis BM-04 3.55m at 0.63 g/t Au & 0.63 g/t
Ag
----------------------- --------------------------------------
Exploration at Moris in H2 2012 will focus on increasing the
life of mine at the operation, with an estimated 8.3 thousand
metres of drilling planned.
(1) please note that all mineralised intersections referred to
in this release are quoted as down-hole lengths, not true
widths.
(2) please not that all mineralised intersections referred to in
this release are wuoted as down-hole lengths, not true widths.
Advanced Projects
On 11 January 2012, Hochschild announced the successful
completion of the Inmaculada and Crespo feasibility studies which
are forecast to contribute 10 million silver equivalent ounces of
attributable production on average per annum at an initial combined
capital cost of $335 million (attributable). Full details of the
feasibility studies can be found in the announcement.
Inmaculada
In Q2 2012, further steady progress was made at Inmaculada. The
suppliers for the main site equipment were selected, with equipment
purchasing starting in the period. Construction of three
exploration tunnels commenced and the contract for the construction
of the main access road to the site was granted, with completion
due by the end of 2012. Project engineering continued during the
quarter with a geomechanical drilling programme completed in June,
whilst engineering contracts for maintenance workshops and stores
were also granted at the end of June. The contract for the
construction of the electricity transmission line was awarded and
work began during the period.
The Company continued initiatives with the local communities
surrounding Inmaculada during the quarter, and work in response to
the observations made in the Environmental Impact Study ('EIS')
also continued, with the EIS approval expected in Q3 2012.
In Q2 2012, resource exploration continued at Inmaculada, with
seven drill rigs in operation throughout the quarter. During the
quarter, 32 drill holes were completed, with six more in progress
at the end of June, totaling 42 drill holes completed in H1 2012. A
total of 12.2 thousand metres of exploration drilling was carried
out in Q2 2012 in order to continue with the incorporation of
inferred resources and to identify new structures. Drilling was
carried out in the Cimoide Angela SW, and Lucy veins, with
encouraging results including(3) :
Vein Results
------------------ ----------------------------------------
Angela SW ASW12-029 1.35m at 2.19 g/t Au & 129
g/t Ag
------------------ ----------------------------------------
Lucy ASW12-032 0.90m at 7.75 g/t Au & 232
g/t Ag
------------------ ----------------------------------------
Angela SW ASW12-033 1.70m at 1.00 g/t Au & 569
g/t Ag
------------------ ----------------------------------------
Lucy ASW12-025 1.58m at 3.16 g/t Au & 107.47
g/t Ag
------------------ ----------------------------------------
Cimoide Angela SW ASW12-033 1.00m at 4.62 g/t Au & 123.58
g/t Ag
------------------ ----------------------------------------
In H2 2012, exploration will focus on the definition and
incorporation of potential systems outside of the current resource
area, with an estimated 30.8 thousand metres of drilling
planned.
Crespo
At the Company's 100% owned Crespo project, engineering
contracts for the plant, leach pads, waste dump and infrastructure
areas were awarded to a local contractor. Proposals for the
construction of the main access road to Crespo were received in
June and the contract will be awarded later this month.
Following the successful public hearing held in April in
relation to the EIS permit, Hochschild continued the process of
responding to the relevant observations with approval expected in
Q4 2012. Community relations support programmes were also put in
place during the quarter.
During the quarter, the surface sampling programme continued at
Crespo, and the lithological and alteration models were completed.
In H2 2012, a drilling programme will commence at Crespo in order
to identify new potential areas of disseminated mineralisation.
Azuca
In Q2 2012, surface geology and detailed mapping were conducted
at Azuca and the drilling programme continued with two drill rigs
in operation. In H2 2012, exploration will focus on identifying new
potential areas with an estimated 22.2 thousand metres of drilling
planned.
(3) please note that all mineralised intersections referred to
in this release are quoted as down-hole lengths, not true
widths.
Greenfield pipeline
In Q2 2012, a total of 9.7 thousand metres was drilled as part
of the greenfield exploration programme, bringing the total for H1
2012 to 17.8 thousand metres. The Company's greenfield exploration
programme saw good progress in H1 2012 and is broadly on track to
meet its full year drilling targets. In H1 2012, drilling was
carried out at 10 projects; of which, six were Company Maker
projects and four were Medium Scale projects.
Company Makers
Victoria
At the 60% owned Victoria project in northern Chile, exploration
work delivered good results in H1 2012. A total of 3.7 thousand
metres of drilling was completed, with exploration work focusing on
the porphyry potential of the property. Drilling to better define
the Picaron porphyry mineralisation and exotic copper oxide targets
was carried out, and geological mapping and target delineation was
continued on further targets with a view to commence the drilling
of defined targets in Q3 2012.
Valeriano
Drilling commenced at Valeriano in October 2011 and, in H1 2012,
2.6 thousand metres of drilling was carried out at the property to
fully test the epithermal high sulphidation and porphyry copper
targets identified last year. In H2 2012 the drilling programme
will include follow up drilling and drill testing of the near
surface high sulphidation target.
Encrucijada
Following positive results from the exploration programme at the
51% owned Encrucijada property in Chile, the project was
re-categorised as a Company Maker project in Q1 2012. In H1 2012,
1.7 thousand metres of drilling was carried out. Additional
geophysical interpretation and targeting of the porphyry style
mineralisation below the San Bernardo tourmaline breccias and dome
complex, and in the surrounding area, was also carried out.
Mercurio
In H1 2012 the drilling campaign continued at the Mercurio
property in Mexico, with the focus on expanding the known
mineralisation and identifying new mineralised structures. A total
of 2.6 thousand metres of drilling was carried out. Drilling
commenced on the Santa Rosa vein system and geochemical sampling
also continued at the property. In H2 2012, the drilling campaign
will focus on the Santa Rosa and Virginia vein areas and along the
large north east structural zone which hosts a barite vein.
Apacheta
At the Apacheta project in Peru, 2.5 thousand metres of drilling
was completed in H1 2012 to complete the initial exploration
programme at Apacheta 1, and a surface sampling programme was
carried out in order to define further targets. In H2 2012,
exploration work will focus on obtaining the social permits for
Apacheta 2 in order to initiate the drilling programme there.
Soranpampa
At the Soranpampa project in Peru, the drilling programme was
initiated in June. Drilling was carried out on a geophysical
anomaly area in order to identify economic near-surface gold
mineralization. Further detailed geophysical work has identified
targets in and adjacent to the primary target with exploration work
continuing into the second half.
Medium Scale projects
In H1 2012, positive results were reported at a number of the
Company's Medium Scale projects and the El Tanque project in Mexico
was added to the Company's exploration pipeline.
Cuello Cuello
At the Cuello Cuello project in Peru, the relevant government
and community permits and approvals were received in December 2011.
At the end of H1 2012 the drilling programme commenced at the
project, with one drill rig in operation. A total of 1.2 thousand
metres of drilling was carried out. Four silica structures with
high sulphide content were identified. In H2 2012, exploration work
will continue.
San Antonio
In H1 2012, a comprehensive mapping and sampling programme to
define drill targets was completed at the San Antonio project in
Chile with almost three thousand metres of drilling carried out.
However, following this exploration work, the Company decided not
to proceed with the San Antonio project.
Jasperoide
In H1 2012, 566 metres of drilling was carried out at the
Jasperoide copper project in Peru, focused on the already
identified mineralised zone and surrounding area to locate new
skarn blankets and to test for a potential associated porphyritic
system. In H2 2012 exploration work will continue.
Financial position
The Company's financial position remains strong with total cash
of approximately $543 million as at 30 June 2012 and minority
investments of $413.6 million.
Outlook
The Company remains on track to achieve its full year production
target of 20.0 million attributable silver equivalent ounces in
2012. Production at the core operations will remain broadly stable
throughout the second half as the Company continues to mine close
to average reserve grades in order to ensure a consistent level of
long-term production. The Company currently expects that, excluding
the effects of royalties and the impact of the Arcata dore project,
unit cost per tonne performance in H1 2012 at the main operations
will be broadly in line with the 15% guidance given in March for
Peru and between 25-30% guidance for Argentina.
__________________________________________________________________
A conference call will be held at 3pm (London time) on Tuesday
17 July 2012 for analysts and investors.
Dial in details as follows:
UK: +44 (0) 20 3003 2666
A recording of the conference call will be available for one
week following its conclusion, accessible from the following
telephone number:
UK: +44 (0) 20 8196 1998
Access code: 8843136
__________________________________________________________________
Enquiries:
Hochschild Mining plc
Charles Gordon +44 (0)20 7907 2934
Head of Investor Relations
RLM Finsbury
Charles Chichester +44 (0)20 7251 3801
Public Relations
__________________________________________________________________
About Hochschild Mining plc
Hochschild Mining plc is a leading precious metals company
listed on the London Stock Exchange (HOCM.L / HOC LN) with a
primary focus on the exploration, mining, processing and sale of
silver and gold. Hochschild has almost fifty years' experience in
the mining of precious metal epithermal vein deposits and currently
operates four underground epithermal vein mines, three located in
southern Peru and one in southern Argentina. Hochschild also has
numerous long-term projects throughout the Americas.
PRODUCTION & SALES INFORMATION
TOTAL GROUP PRODUCTION(1)
Q2 Q1 Q2 H1 H1
2012 2012 2011 2012 2011
------------------------- ------- ------- ------- ------- -------
Silver production (koz) 4,966 4,762 5,174 9,728 10,414
Gold production (koz) 40.96 40.51 43.99 81.47 88.91
Total silver equivalent
(koz) 7,424 7,193 7,814 14,616 15,748
Total gold equivalent
(koz) 123.73 119.88 130.23 243.61 262.47
Silver sold (koz) 4,528 4,068 5,658 8,596 10,758
Gold sold (koz) 38.20 27.71 50.27 65.91 89.39
------------------------- ------- ------- ------- ------- -------
1 Total production includes 100% of all production, including
production attributable to joint venture partners at San Jose and
Pallancata.
ATTRIBUTABLE GROUP PRODUCTION(1)
Q2 Q1 Q2 H1 H1
2012 2012 2011 2012 2011
--------------------------- ------- ------- ------- ------- -------
Silver production (koz) 3,501 3,386 3,653 6,887 7,340
Gold production (koz) 27.65 28.29 31.95 55.94 63.26
Attrib. silver equivalent
(koz) 5,160 5,083 5,570 10,243 11,136
Attrib. gold equivalent
(koz) 86.00 84.72 92.84 170.72 185.60
--------------------------- ------- ------- ------- ------- -------
1 Attributable production includes 100% of all production from
Arcata, Ares and Moris, 60% from Pallancata and 51% from San
Jose.
QUARTERLY PRODUCTION BY MINE
ARCATA
Q2 Q1 Q2 H1 H1
2012 2012 2011 2012 2011
---------------------------- -------- -------- -------- -------- --------
Ore production (tonnes) 180,500 164,160 159,110 344,660 316,086
Average head grade silver
(g/t) 300 317 334 308 342
Average head grade gold
(g/t) 0.88 0.94 0.94 0.91 0.94
Silver produced (koz) 1,515 1,498 1,506 3,012 3,056
Gold produced (koz) 4.56 4.48 4.32 9.04 8.66
Silver equivalent produced
(koz) 1,788 1,766 1,765 3,555 3,575
Silver sold (koz) 1,548 1,112 1,703 2,659 3,020
Gold sold (koz) 4.99 2.81 4.66 7.81 8.36
---------------------------- -------- -------- -------- -------- --------
ARES
Q2 Q1 Q2 H1 H1
2012 2012 2011 2012 2011
---------------------------- ------- ------- ------- -------- --------
Ore production (tonnes) 82,368 78,265 82,181 160,632 155,683
Average head grade silver
(g/t) 54 47 64 51 64
Average head grade gold
(g/t) 2.51 2.62 2.99 2.56 3.01
Silver produced (koz) 115 112 151 227 284
Gold produced (koz) 5.92 6.71 7.39 12.63 14.08
Silver equivalent produced
(koz) 470 515 594 985 1,129
Silver sold (koz) 93 85 186 178 287
Gold sold (koz) 6.73 3.21 8.75 9.94 14.32
---------------------------- ------- ------- ------- -------- --------
PALLANCATA(1)
Q2 Q1 Q2 H1 H1
2012 2012 2011 2012 2011
---------------------------- -------- -------- -------- -------- --------
Ore production (tonnes) 270,961 257,339 266,673 528,300 508,734
Average head grade silver
(g/t) 250 263 295 256 299
Average head grade gold
(g/t) 1.08 0.99 1.31 1.04 1.31
Silver produced (koz) 1,825 1,780 2,170 3,606 4,188
Gold produced (koz) 6.40 5.61 8.43 12.01 16.21
Silver equivalent produced
(koz) 2,209 2,117 2,676 4,326 5,160
Silver sold (koz) 1,730 1,826 2,166 3,556 4,492
Gold sold (koz) 5.95 5.48 7.94 11.43 16.57
---------------------------- -------- -------- -------- -------- --------
1 The Company holds a 60% interest in Pallancata.
SAN JOSE(1)
Q2 Q1 Q2 H1 H1
2012 2012 2011 2012 2011
---------------------------- -------- -------- ------- -------- --------
Ore production (tonnes) 128,803 115,531 98,251 244,334 211,947
Average head grade silver
(g/t) 430 416 463 423 461
Average head grade gold
(g/t) 5.98 5.98 5.98 5.98 6.03
Silver produced (koz) 1,500 1,356 1,332 2,855 2,854
Gold produced (koz) 21.95 20.36 17.70 42.30 39.11
Silver equivalent produced
(koz) 2,816 2,577 2,394 5,393 5,201
Silver sold (koz) 1,146 1,032 1,585 2,178 2,927
Gold sold (koz) 17.66 14.34 21.69 32.00 39.32
---------------------------- -------- -------- ------- -------- --------
1 The Company holds a 51% interest in San Jose.
MORIS
Q2 Q1 Q2 H1 H1
2012 2012 2011 2012 2011
---------------------------- ------- ------- -------- ------- --------
Ore production (tonnes) - - 306,846 - 612,257
Average head grade silver
(g/t) - - 5.54 - 4.83
Average head grade gold
(g/t) - - 1.12 - 0.94
Silver produced (koz) 11.3 16.8 15.3 28.09 31.72
Gold produced (koz) 2.13 3.35 6.17 5.48 10.86
Silver equivalent produced
(koz) 139 218 385 357 683
Silver sold (koz) 11 13 19 24 31
Gold sold (koz) 2.86 1.87 7.23 4.73 10.82
---------------------------- ------- ------- -------- ------- --------
Forward looking statements
This announcement may contain forward looking statements. By
their nature, forward looking statements involve risks and
uncertainties because they relate to events and depend on
circumstances that will or may occur in the future. Actual results,
performance or achievements of Hochschild Mining plc may, for
various reasons, be materially different from any future results,
performance or achievements expressed or implied by such forward
looking statements.
The forward looking statements reflect knowledge and information
available at the date of preparation of this announcement. Except
as required by the Listing Rules and applicable law, the Board of
Hochschild Mining plc does not undertake any obligation to update
or change any forward looking statements to reflect events
occurring after the date of this announcement. Nothing in this
announcement should be construed as a profit forecast.
- ends -
This information is provided by RNS
The company news service from the London Stock Exchange
END
MSCVQLFFLDFZBBD
Hochschild Mining (LSE:HOC)
Historical Stock Chart
From Jun 2024 to Jul 2024
Hochschild Mining (LSE:HOC)
Historical Stock Chart
From Jul 2023 to Jul 2024