DOW JONES NEWSWIRES
The following table lists unplanned and planned production
outages at U.S. refineries as reported by Dow Jones Newswires. The
information is compiled from both official and unofficial refining
sources and doesn't purport to be a comprehensive list.
Marathon Petroleum said Nov. 1 it restarted the crude
distillation unit at its refinery in Catlettsburg, Ky., following a
week of planned maintenance.
Valero Energy Corp. on Nov. 1 announced its first quarter 2012
turnaround schedule for its refineries in Houston, Texas; Norco,
La.; Wilmington, Cali.; and Memphis, Tenn. The dates and units
effected can be found in the chart below.
BP PLC took down one of the three crude units at its refinery in
Whiting, Ind., for maintenance during the weekend of Oct. 30, said
a source familiar with the refinery. A restart date was
unknown.
Total SA will extend a maintenance turnarond currently underway
at its Port Arthur refinery to around Nov. 9, a source said Oct.
26. The work on the refinery's crude unit and FCCU was originally
scheduled to finish by Nov 5.
ConocoPhillips on Oct. 24 had an unspecified unit go out at its
refinery in Belle Chasse, La., according to a filing made on Oct.
25.
Valero Energy Corp. on Oct. 21 said previously announced
turnaround maintenance at a crude distillation unit and a coker
unit began at its oil refinery in Corpus Christi, Texas. The
turnaround is expected to conclude in three weeks.
Valero Energy Corp. on Oct. 20 said emissions reported to Texas
State environmental regulators the day before were associated with
the end of some of the turnaround maintenance underway since late
September at its oil refinery in Three Rivers, Texas. Turnaround
continues at parts of the plant; restart seen in early Nov.
Suncor Energy Inc.'s (SU) oil refinery in Edmonton, Alberta,
will be operating at reduced rates over the next two weeks due to a
disruption in hydrogen supplies, a company spokeswoman said on Oct.
11. The disruption in hydrogen supplies occurred at a third-party
supplier which told Suncor it would be unable to supply hydrogen
over the next two weeks.
For more detailed information, search Dow Jones Newswires using
the code N/REF.
Operator Refinery Capacity Description Restart
(in 000s
bbl/day)
UNPLANNED
CANADA
Suncor Edmonton 135.0 Refinery will operate at re-
Energy duced rates for two weeks due
to a disruption in supplies
from a 3rd-party supplier, co.
said on Oct. 11.
CARIBBEAN
EAST COAST
Sunoco Marcus Hook 178.0 FCCU shut Oct. 11 restarted Oct 17
PA Oct. 16-17. Crude unit,
reformer unit shut Oct. 3 for
two weeks maintenance to re-
start on Oct. 19, traders said. Oct 19
GULF COAST
Conoco Belle Unspecified unit malfunction
Phillips Chasse, La. 247.0 on Oct. 24.
Conoco Sweeny 247.0 Units upset by transformer fire Oct 18
Phillips TX on Oct 18 were in restart mode
soon after the fire was out.
Pasadena Pasadena 100.0 Repairs at CDU shut by fire Early
Refining TX on Sept 30 under way; pro- Nov
duction expected to resume by
early Nov, the Co said on Oct
14.
MIDWEST
ROCKIES
Sinclair Sinclair 74.0 Refinery at reduced rates fol-
WY lowing fires at CDU on Sept. 3
and Sept. 4. Repairs and damage
assessments underway. No update
the company said on Oct. 6.
WEST COAST
PLANNED
CANADA
CARIBBEAN
Hovensa St. Croix 350.0 Planned maintenance at a
crude unit, reformer and
coker unit in Oct. will
last 2-4 weeks, the co.
said on Oct. 3. On-going
the co. said on Oct. 17.
EAST COAST
Conoco Trainer, PA 185.0 Crude processing halted;
operations winding down,
the company said on Sept. 30.
The refinery will be
shuttered in six months if
not sold.
PBF Delaware City 190.0 All refinery units operation- Oct 7
DE al, the company said on Oct. 7.
Some units came on-line after
major overhaul in June; the
hydrocracking unit was the last
unit to be restarted.
Sunoco Philadelphia 335.0 Refineries up for sale on
Marcus Hook 190.0 Sept. 6; process units will
be shuttered in July 2012
if no buyer is found.
Sunoco Marcus Hook 190.0 Crude unit, reformer unit Oct 16
PA and sulfur recovery unit shut
for 2 weeks work, traders
on Oct. 3. Not confirmed.
GULF COAST
Motiva Port Arthur 285.0 Expansion project to increase 1Q
TX throughput capacity by 325,000 2012
b/d, to 610,000-b/d, slowed.
Completion now seen 1Q
2012, from 2010.
Total Port Arthur 232.0 Several units, including crude mid-Nov
USA TX unit and FCCU shut six weeks
turnaround maintenance, a source
familiar with the plant said on
Sept. 21.
Valero Corpus 315.0 Crude & coker unit turnaround Nov 10
Christi, TX underway the Co. said on Oct. 21
and will continue for three weeks.
Valero McKee TX 170.0 Vacuum unit turnaround planned for
first half of 2012, company said.
Expansion project announced
March 2011 to increase crude oil
throughput by 25,000 b/d to
195,000 b/d.
Valero Houston,TX 88.0 Seven weeks of FCCU maintnance end-March
starting in Feb. 2012. 2012
Valero Norco, LA 185.0 Ten weeks of work planned for mid-April
the crude and coker units starting 2012
Feb. 2012.
Valero Norco, LA 185.0 Hydrocracker project will pro- 2013
ceed and be completed in late
2013, the co. said on 7/27/10.
Upgrade project to build 2012
a new diesel hydrotreater
unit moved from 2010 to
4Q 2012.
Valero Port Arthur 325.0 Hydrocracker project will pro- 2012
TX ceed and be completed in late
2012.
Valero Three Rivers 100.0 6 weeks of turnround work under Nov 6
TX way since late-Sep at FCCU and (est)
crude unit. This work was ad-
vanced from an early-Oct start.
MIDWEST
BP Whiting, IN 405.0 Turnaround at crude unit began
during weekend of Oct. 30.
Cenovus Roxana, IL 306.0 Coker and refinery expansion Q4 2011
(Conoco/WRB) project on track for comple-
tion 4th Q 2011, the company said
on July 26.
Conoco Ponca City 187.0 Turnaround maintenance under
way week of Oct. 3, the co.
said on Oct. 6. No details pro-
vided.
CVR Coffeyville 115.7 Periodic turnaround will take 2012
KS place in two phases beginning in
Fall 2011 and completed in Spring
2012.
Husky Lima, OH 160.0 15-days of maintenance planned at
Energy at aromatics unit in the fall
of 2012.
Husky Toledo, OH 140.0 Minor maintenance planned in 4Q
Energy 2011, the company said on July 28;
no details provided.
Tesoro Mandan, ND 58.0 Total crude-oil processing capa- 2nd Q
city to increase by 17% to 68,000 2012
b/d by 2nd quarter 2012.
Valero Memphis, TN 180.0 Five weeks of maintenance on early-April
crude unit starting in March. 2012
WEST COAST
BP Ferndale, WA 225.0 Seasonal turnaround maintenance
started Oct. 3. Hydrocracker, 2
reformers, 2 delayed coking units,
listed among units involved in
the turnaround. Catalyst regener-
ation will also take place.
Chevron Richmond, 240.0 4-6 weeks of planned work under Oct 30-
CA way at unspecified units, the Nov 13
company said on Oct. 4. Traders said
the crude unit will be worked on
in this 4-6 week period.
Shell Anacortes, 145.0 Performing maintenance on crude Nov. 28
WA unit and other units starting
Sep. 23.
Tesoro Anacortes, 120.0 FCCU and several other process
WA units shut Oct 1 for planned
maintenance seen restarting at
end-Oct.
Valero Wilmington, 78.0 Four weeks of maintenance for Feb. 2012
CA crude and coker units starting
in January 2012.