Petra Diamonds Update re Williamson TSF wall breach
November 30 2022 - 2:00AM
UK Regulatory
TIDMPDL
30 November 2022 LSE: PDL
FOR IMMEDIATE RELEASE
Petra Diamonds Limited
("Petra") or the ("Company")
Update regarding Tailings Storage Facility (TSF) wall breach at Williamson in
Tanzania
In follow up to its announcement of 10 November 2022, Petra provides a further
update regarding the TSF wall breach at the Williamson mine on 7 November 2022.
Impact on the environment and local community
The assessment team has concluded there is a low risk of further breaches of
the TSF or a breach of the New Alamasi water dam. Williamson Diamonds Limited
(WDL) has constructed an initial 6m high wall to close the breached wall area.
As a precautionary measure, WDL has also constructed containment walls upstream
and downstream of the New Alamasi water dam, while buttressing of the New
Alamasi water dam wall is underway. Various diversion trenches are also being
constructed to prevent any build-up of water and to enable rainwater to flow
into the surrounding rivers and streams.
A total of 12.8 million cubic metres of water and tailings material were
released from the TSF as a result of the breach. A total area of 3.57km2 is
covered with this material on Williamson's mine lease area with 1.52km2 outside
the mine lease area. Environmental work to date confirms the tailings material
which flowed out of the TSF is inert. Water and tailings material samples were
taken by the Tanzanian Government Chemist Laboratory Authority, which confirmed
that no dangerous chemicals were found and that all chemicals were within
normal parameters. This was confirmed by separate, private, laboratory tests.
Analysis is underway with the assistance of independent experts to ascertain
appropriate measures for the clean-up or remediation of affected areas.
Petra reconfirms that no fatalities or serious injuries occurred as a result of
the incident. A temporary rehousing scheme is being planned for the families
affected by the breach. Interim accommodation and humanitarian relief,
including psycho-social assistance, continues to be provided to those affected.
Valuation, land and socio-economic surveys are being implemented with all the
necessary approvals from the Government.
A socio-economic study, supported by an external social impact specialist, is
well advanced to determine socio-economic impacts. WDL, along with local,
Regional and National authorities, continues its extensive engagements with
local communities to ensure that key stakeholders are kept informed of WDL's
response, including planned remediation activities. WDL and Petra remain
appreciative of the continued cooperation and assistance provided by
Government, community leadership and affected parties.
Technical and Production
Following the visit of a technical team that included independent external
specialists, the preliminary assessment concluded that the failure mechanism
was subsidence of a portion of the East wall of the TSF by around 1.5m that
enabled the water to crest the wall, initiating the breach. The root cause of
the subsidence has not been determined and will require a forensic geotechnical
investigation to be completed. This work will be undertaken by an independent
company specialising in tailings dam design and management. Cost and timing of
the investigation will be available after a detailed scoping process is
completed, but initial indications are that this exercise will take between 6
and 12 months.
In light of the failure of the existing facility, the design of the new TSF is
currently under review. This is only expected to be finalised in February 2023,
which will determine the additional construction work required to make the
facility operational. It is now expected that this new TSF will take longer
than initially anticipated to become operable. In parallel, a further
potential option of repairing and using the existing TSF is also being explored
as a long-term solution, but this is subject to the outcome of the geotechnical
investigation. Updates on the progress of these potential long-term solutions
will be provided in due course.
As a result of the additional work required to progress these long-term
solutions, interim deposition options are being developed that may enable the
Williamson mine to resume production around the middle of 2023. These interim
options may include utilising a portion of the existing or new TSF. The
Williamson mine will not resume any deposition under these interim options
until it has been confirmed that it is safe to do so and any necessary
regulatory approvals have been obtained. Further work is being conducted
between WDL, Petra's technical team and external specialists to determine the
best possible options to recommence production safely and as soon as possible.
As previously stated, accelerated waste stripping and planned maintenance
activities will continue in order to minimise the impact of lost production.
This interim plan will be adjusted as we progress the interim options referred
to above.
WDL is considering additional financing options to provide support during this
period and is engaging with the Government of Tanzania regarding the sale of
the previously blocked and confiscated diamond parcel, the proceeds of which
the Government of Tanzania has agreed to allocate to WDL under the Framework
Agreement entered into in December 2021.
Further updates will be provided in due course.
Petra currently has a 75% shareholding in WDL, with the Government of Tanzania
owning the remaining 25%.
This announcement includes inside information as defined in Article 7 of the UK
Market Abuse Regulation No. 596/2014 and is being released on behalf of Petra
by the Company Secretary.
Ends
For further information, please contact:
Petra Diamonds, London Telephone: +44 20 7494 8203
Patrick Pittaway
investorrelations@petradiamonds.com
Julia Stone
About Petra Diamonds Limited
Petra Diamonds is a leading independent diamond mining group and a supplier of
gem quality rough diamonds to the international market. The Group's portfolio
incorporates interests in three underground mines in South Africa (Finsch,
Cullinan Mine and Koffiefontein) and one open pit mine in Tanzania
(Williamson).
Petra's strategy is to focus on value rather than volume production by
optimising recoveries from its high-quality asset base in order to maximise
their efficiency and profitability. The Group has a significant resource base
which supports the potential for long-life operations.
Petra strives to conduct all operations according to the highest ethical
standards and only operates in countries which are members of the Kimberley
Process. The Group aims to generate tangible value for each of its
stakeholders, thereby contributing to the socio-economic development of its
host countries and supporting long-term sustainable operations to the benefit
of its employees, partners and communities.
Petra is quoted with a premium listing on the Main Market of the London Stock
Exchange under the ticker 'PDL'. The Group's loan notes due in 2026 are listed
on the Irish Stock Exchange and admitted to trading on the Global Exchange
Market. For more information, visit www.petradiamonds.com.
END
(END) Dow Jones Newswires
November 30, 2022 02:00 ET (07:00 GMT)
Petra Diamonds (LSE:PDL)
Historical Stock Chart
From Jun 2024 to Jul 2024
Petra Diamonds (LSE:PDL)
Historical Stock Chart
From Jul 2023 to Jul 2024