UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549



FORM 6-K



REPORT OF FOREIGN PRIVATE ISSUER
PURSUANT TO RULE 13a-16 OR 15d-16
UNDER THE SECURITIES EXCHANGE ACT OF 1934

Dated 17 June 2024

Commission File Number 001-31318



Gold Fields Limited
(Translation of registrant’s name into English)



150 Helen Rd.
Sandown, Sandton 2196
South Africa
(Address of principal executive office)



Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F:

  Form 20-F 
  Form 40-F




SIGNATURES

Pursuant to the requirements of the Securities Exchange Act of 1934, the Registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

Gold Fields Limited
Date: 17 June 2024By:/s/ Mike Fraser
Name:Mike Fraser
Title:Chief Executive Officer





INDEX TO EXHIBITS



Gold Fields Limited (Reg. No. 1968/004880/06) (Incorporated in the Republic of South Africa) (“Gold Fields” or the “Company”) JSE, NYSE, DIFX Share Code: GFI ISIN Code:ZAE000018123 UPDATE ON SALARES NORTE PROJECT AND REVISION TO 2024 GROUP GUIDANCE Revision to Salares Norte Project and Group Guidance As reported in the Company’s Q1 2024 operational update, ramp-up at the Salares Norte Project (“Salares Norte” or “the Project”) has been negatively impacted by the early onset of winter events in Chile which have persisted in recent weeks. These weather events resulted in the freezing of material in the piping of the process plant (“Plant”) causing temporary shutdown of the Plant. These impacts have been greater than planned owing to the early onset and extended duration of winter conditions during the commissioning and ramp-up phase. The Plant has been restarted, however, commissioning and ramp-up during the winter period are expected to continue to be challenging, creating uncertainty on production levels during the winter months. Calendar year 2024 production for the Project is therefore being revised down from the previously indicated gold equivalent ounces range of 220koz – 240koz, to 90koz – 180koz. The bottom end of this range (90koz) is largely independent of weather events until late August 2024 and assumes the following for ramp-up from now until the end of 2024:  No production until the end of the winter period, with testing of sub-systems only, until end of August 2024.  Ramp-up resumes on 1 September 2024.  No significant weather events resulting in multiday stoppages from September 2024 onwards (weather-related downtime is considered in the ramp-up factor).  Circuit C commissioning continues from September 2024 onwards, with this circuit fully operational by mid-October 2024.  Conservative metallurgical recoveries. The top end of the range (180koz) assumes the following for ramp-up from now until the end of 2024:  Ramp-up resumes on 15 June 2024.  No significant weather events that result in multiday stoppages for the rest of 2024 (weather-related downtime is considered in the ramp-up factor)  Circuit C commissioning continues from July 2024 onwards with this circuit fully operational by August 2024.  Conservative metallurgical recoveries. The design criteria of the Plant will be capable of handling such winter weather events at steady state and total Project capital costs remain in line with the guidance at US$1,180m - US$1,200m. Due to the Salares Norte production revision, Gold Fields is revising 2024 group production guidance from 2.33Moz - 2.43Moz to 2.20Moz – 2.30Moz. All-in costs for the group in 2024 are revised from the US$1,600/oz – US$1,650/oz range previously guided to US$1,675/oz – US$1,740/oz while guidance for all-in sustaining costs is revised to US$1,470/oz – US$1,530/oz (compared to the US$1,410/oz – US$1,460/oz range previously guided).


 
Update on Chinchilla Capture and Relocation Programme On 17 May 2024, Gold Fields advised shareholders that Salares Norte had received an urgent and transitionary measure (“MUT”) from Chile’s Superintendence of Environment (the “SMA”) ordering temporary suspension of the dismantling of Rocky Area No 3 (“R3”) as part of its approved Chinchilla capture and relocation plan. On 5 June 2024, Salares Norte received an updated notice from the SMA extending the suspension of dismantling R3 for a further 120 days. Mining operations and project activities are continuing, and focus remains on ramp-up of the project, respecting the buffer zones established to avoid any potential disturbance to the Chinchilla and complying with all other regulatory requirements established by the authority. As part of the initial MUT issued on 14 May 2024, the SMA requested additional information detailing the monitoring activities undertaken at R3. Salares Norte submitted this information which included endoscopic probe search and night camera recordings. Gold Fields continues to engage with the SMA to progress the Chinchilla capture and relocation programme. In accordance with the approved capture and relocation plan, Gold Fields is not planning to undertake any capture and relocation activities during the winter months at Salares Norte. The Company is committed to the safe capture and relocation of the protected Chinchilla species and Salares Norte continues to work with the SMA and independent environmental experts on all aspects of this programme. Salares Norte remains a high quality asset that will contribute materially to Gold Fields’ cashflows in future years. 13 June 2024 Sponsor: J.P. Morgan Equities South Africa (Pty) Ltd Forward-looking statements This announcement contains forward-looking statements within the meaning of the “safe harbour” provisions of the Private Securities Litigation Reform Act of 1995. All statements other than statements of historical fact included in this announcement may be forward-looking statements. Forward-looking statements may be identified by the use of words such as “aim”, “anticipate”, “will”, “would”, “expect”, “may”, “could”, “believe”, “target”, “estimate”, “project” and words of similar meaning. These forward-looking statements, including among others, those relating to Gold Fields’ future business strategy, development activities and other initiatives, particularly at the Salares Norte project, business prospects, financial positions, production and operational guidance are necessary estimates reflecting the best judgement of the senior management of Gold Fields and involve a number of risks and uncertainties that could cause actual results to differ materially from those suggested by the forward-looking statements. By their nature, forward- looking statements involve risk and uncertainty because they relate to future events and circumstances and should be considered in light of various important factors, including those set forth in Gold Fields’ Integrated Annual Report 2023 filed with the Johannesburg Stock Exchange and annual report on Form 20-F filed with the United States Securities and Exchange Commission (SEC) on 28 March 2024 (SEC File no. 001-31318). Readers are cautioned not to place undue reliance on such statements. These forward-looking statements speak only as of the date they are made. Gold Fields undertakes no obligation to update publicly or release any revisions to these forward-looking statements to reflect events or circumstances after the date of this announcement or to reflect the occurrence of unanticipated events. These forward-looking statements have not been reviewed or reported on by the Company’s external auditors.


 
1 Gold Fields Limited Reg. 1968/004880/06 150 Helen Road, Sandown, Sandton, 2196 Tel +27 11 562 9700 Fax +27 11 562 9838 www.goldfields.com Postnet Suite 252 Private Bag X30500 Houghton, 2041 South Africa Investor Enquiries Jongisa Magagula Tel +27 11 562 9775 Mobile +27 67 419 9503 Email Jongisa.Magagula@goldfields.com Media Enquiries Sven Lunsche Tel +27 11 562 9763 Mobile +27 82 260 9279 Email Sven.Lunsche@goldfields.com Directors: YGH Suleman (Chair), MJ Fraser ** (Chief Executive Officer), A Andani #, PJ Bacchus†, MC Bitar@, TP Goodlace, JE McGill^, SP Reid^, PG Sibiya, CAT Smit South African unless stated, ^Australian, †British, @Chilean, #Ghanaian, ** Executive Director Company Secretary: Anré Weststrate Thomas Mengel Tel +27 11 562 9849 Mobile +27 72 493 5170 Email Thomas.Mengel@goldfields.com UPDATE ON SALARES NORTE PROJECT AND REVISION TO 2024 GROUP GUIDANCE Johannesburg, 13 June 2024: Gold Fields Limited (Gold Fields) (JSE, NYSE: GFI) has provided an update on the Salares Norte Project in Chile, the Chinchilla capture and relocation programme at the Project as well as Group production and cost guidance for 2024. Revision to Salares Norte Project As reported in the Company’s Q1 2024 operational update, ramp-up at the Salares Norte Project has been negatively impacted by the early onset of winter events which have persisted in recent weeks. These weather events resulted in the freezing of material in the piping of the process plant causing temporary shutdown of the plant. These impacts have been greater than planned owing to the early onset and extended duration of winter conditions during the commissioning and ramp-up phase. The plant has been restarted, however, commissioning and ramp-up during the winter period are expected to continue to be challenging, creating uncertainty on production levels during the winter months. Calendar year 2024 production guidance for the Project is therefore being revised down from the previously indicated gold-equivalent ounces range of 220koz – 240koz, to 90koz – 180koz. The bottom end of this range (90koz) is largely independent of weather events until late August 2024 and assumes the following for ramp-up from now until the end of 2024:  No production until the end of the winter period with testing of sub-systems only until end of August 2024.  Ramp-up resumes on 1 September 2024.  No significant weather events resulting in multiday stoppages from September 2024 onwards (weather-related downtime is considered in the ramp-up factor).


 
2  Circuit C commissioning continues from September 2024 onwards, with this circuit fully operational by mid-October 2024.  Conservative metallurgical recoveries. The top end of the range (180koz) assumes the following for ramp-up from now until the end of 2024:  Ramp-up resumes on 15 June 2024.  No significant weather events that result in multi-day stoppages for the rest of 2024 (weather-related downtime is considered in the ramp-up factor)  Circuit C commissioning continues from July 2024 onwards with this circuit fully operational by August 2024.  Conservative metallurgical recoveries. The design criteria of the plant will be capable of handling such winter weather events at steady state and total Project capital costs remain in line with guidance of US$1,180m - US$1,200m. Revision to 2024 Group guidance Due to the Salares Norte production revision, Gold Fields is revising 2024 Group production guidance from 2.33Moz - 2.43Moz to 2.20Moz – 2.30Moz. All-in costs (AIC) for the group in 2024 are revised from the US$1,600/oz – US$1,650/oz range previously guided to US$1,675/oz – US$1,740/oz, while guidance for all-in sustaining costs (AISC) is revised to US$1,470/oz – US$1,530/oz (compared to US$1,410/oz – US$1,460/oz previously guided). Update on Chinchilla capture and relocation plan On 17 May 2024, Gold Fields advised shareholders that Salares Norte had received an urgent and transitionary measure (MUT) from Chile’s Superintendence of Environment (SMA) ordering temporary suspension of the dismantling of Rocky Area No 3 (R3) as part of its approved Chinchilla rescue and relocation plan. On 5 June 2024, Salares Norte received an updated notice from the SMA extending the suspension of dismantling R3 for a further 120 days.


 
3 Mining operations and project activities are continuing, and the focus remains on ramp-up of the project, respecting the buffer zones established to avoid any potential disturbance to this species and complying with all other regulatory requirements established by the authority. As part of the initial MUT issued on 14 May 2024, the SMA requested additional information detailing the monitoring activities undertaken at R3. Salares Norte submitted this information which included endoscopic probe search and night camera recordings. Gold Fields continues to engage with the SMA to progress the Chinchilla capture and relocation plan. In accordance with the approved capture and relocation plan, Gold Fields is not planning to undertake any capture and relocation activities during the winter months at Salares Norte. The Company remains committed to the safe capture and relocation of the protected Chinchilla species and Salares Norte continues to work with the SMA and independent environmental experts on all aspects of this programme. Salares Norte remains a high-quality asset that will contribute materially to Gold Fields’ cashflows in future years. About Gold Fields Gold Fields is a globally diversified gold producer with nine operating mines in Australia, South Africa, Ghana, Chile and Peru and one project in Canada. We have total attributable annual gold-equivalent production of 2.30Moz, proved and probable gold Mineral Reserves of 46.1Moz, measured and indicated gold Mineral Resources of 31.1Moz (excluding Mineral Reserves) and inferred Gold Mineral Resources of 11.2Moz (excluding Mineral Reserves). Our shares are listed on the Johannesburg Stock Exchange (JSE) and our American depositary shares trade on the New York Exchange (NYSE). Sponsor: J.P. Morgan Equities South Africa (Pty) Ltd


 
4 Forward-looking statements This announcement contains forward-looking statements within the meaning of the “safe harbour” provisions of the Private Securities Litigation Reform Act of 1995. All statements other than statements of historical fact included in this announcement may be forward-looking statements. Forward-looking statements may be identified by the use of words such as “aim”, “anticipate”, “will”, “would”, “expect”, “may”, “could”, “believe”, “target”, “estimate”, “project” and words of similar meaning. These forward-looking statements, including among others, those relating to Gold Fields’ future business strategy, development activities and other initiatives, particularly at the Salares Norte project, business prospects, financial positions, production and operational guidance are necessary estimates reflecting the best judgement of the senior management of Gold Fields and involve a number of risks and uncertainties that could cause actual results to differ materially from those suggested by the forward-looking statements. By their nature, forward- looking statements involve risk and uncertainty because they relate to future events and circumstances and should be considered in light of various important factors, including those set forth in Gold Fields’ Integrated Annual Report 2023 filed with the Johannesburg Stock Exchange and annual report on Form 20-F filed with the United States Securities and Exchange Commission (SEC) on 28 March 2024 (SEC File no. 001-31318). Readers are cautioned not to place undue reliance on such statements. These forward-looking statements speak only as of the date they are made. Gold Fields undertakes no obligation to update publicly or release any revisions to these forward-looking statements to reflect events or circumstances after the date of this announcement or to reflect the occurrence of unanticipated events. These forward-looking statements have not been reviewed or reported on by the Company’s external auditors.


 
5 Gold Fields Limited Reg. 1968/004880/06 150 Helen Road, Sandown, Sandton, 2196 Tel +27 11 562 9700 Fax +27 11 562 9838 www.goldfields.com Postnet Suite 252 Private Bag X30500 Houghton, 2041 South Africa Investor Enquiries Jongisa Magagula Tel +27 11 562 9775 Mobile +27 67 419 9503 Email Jongisa.Magagula@goldfields.com Media Enquiries Sven Lunsche Tel +27 11 562 9763 Mobile +27 82 260 9279 Email Sven.Lunsche@goldfields.com Directors: YGH Suleman (Chair), MJ Fraser ** (Chief Executive Officer), A Andani #, PJ Bacchus†, MC Bitar@, TP Goodlace, JE McGill^, SP Reid^, PG Sibiya, CAT Smit South African unless stated, ^Australian, †British, @Chilean, #Ghanaian, ** Executive Director Company Secretary: Anré Weststrate Thomas Mengel Tel +27 11 562 9849 Mobile +27 72 493 5170 Email Thomas.Mengel@goldfields.com


 

Gold Fields (NYSE:GFI)
Historical Stock Chart
From May 2024 to Jun 2024 Click Here for more Gold Fields Charts.
Gold Fields (NYSE:GFI)
Historical Stock Chart
From Jun 2023 to Jun 2024 Click Here for more Gold Fields Charts.