TIDMDCP
RNS Number : 7880N
Diamondcorp Plc
31 July 2014
31 July 2014
DiamondCorp plc
AIM share code: DCP & JSE share code: DMC
ISIN: GB00B183ZC46
(Incorporated in England and Wales)
(Registration number 05400982)
(SA company registration number 2007/031444/10)
("DiamondCorp", "the Group" or "the Company")
Lace mine Project update
DiamondCorp, the Southern African diamond development and
exploration company, is pleased to provide the following update on
the underground development and tailings re-treatment activities at
the Lace diamond mine in the Free State province of South
Africa.
Highlights
-- The scoping and mine design studies on the Upper K4 ("UK4")
Block have been completed and confirm the potential for commercial
ramp up from underground kimberlite mining. This can start in H1
2015, six months ahead of schedule, with steady state production of
30,000 tonnes per month achievable by H2 2015.
-- Drilling of the UK4 block is ongoing and to date a mining
block totalling approximately 1.5 million tonnes of kimberlite has
been outlined which can be mined by bottom up longhole open
stoping.
-- Ongoing microdiamond analysis continues to confirm the UK4
Block contains high-grade kimberlite with the potential to yield up
to 60 carats per hundred tonnes ("cpht") of ore.
-- A revised budget and schedule has been adopted to fund
development of the UK4 Block from within existing project finance
facilities.
-- Overall mine development costs to date are averaging
R37,051/m against a budget of R35,327/m.
-- Installation of the underground conveyor belt system has
commenced and is on schedule to be used for mining of the UK4
Block.
-- Plans to complete an updated resource statement have been
rescheduled so that results from a bulk test of kimberlite
extracted from the UK4 Block can be incorporated. This is now
expected to be issued in Q1 2015.
-- Mining of tailings slowed during the quarter as the surface
earth moving fleet was diverted to building an additional surface
dam in preparation for early production of kimberlite from
underground.
-- Diamond recoveries for the three months ended 30 June 2014
totalled 6,102 carats at a recovered grade of 6.32 cpht.
-- This month a 15.2 carat clean white octahedral diamond was
recovered from the tailings, the largest gem diamond the Company
has recovered to date.
-- The de-grit circuit has been commissioned and is operating efficiently.
-- Diamond sales for the six months to 30 June 2104 totalled
14,583 carats at an average price of US$62 per carat.
Underground Development
As we reported last quarter, core drilling of the Bulge area
provisionally indicates that the zone is largely lower grade
(volcanoclastic) kimberlite, meaning that the total recoverable
diamond content is likely to be significantly less than the UK4
Block. Mining of the UK4 Block has the potential to provide
significant additional cashflow which would allow the Bulge to be
bulk tested and (if warranted) financed from internally generated
cashflow, whereas mining of the Bulge alone would require
additional project finance. Further, the UK4 Block has the
potential to provide high grade ore while the 47 Level Block cave
is developed and matures and smoothes out the potential lumpiness
in tonnage which can occur in the early stages of block caving. For
these reasons, the UK4 Block is considered a high priority
development target, and the zone where underground production
drilling will now concentrate.
During the three months ending 30 June 2014, the Company's
74%-owned subsidiary Lace Diamond Mines (Pty) Limited (LDM) adopted
a revised underground development schedule and budget which aims to
bring forward the ramp up of commercial production from underground
kimberlite mining by six months into H1 2015. The accelerated
mining development will be financed from within existing project
finance facilities.
To achieve mine production from the UK4 block, 1,149m of waste
development and 880m of kimberlite development is planned over the
next 12 months at a budgeted cost of R75 million (R37,000 per
metre). Development not common to both mining of the UK4 Block and
the 47 level block cave has been rescheduled to occur after mining
of the UK4 Block commences.
Overall mine development costs to date are averaging R37,051/m
against a budget of R35,327/m. The 5% over spend is largely a
result of rising operating costs on the Company's underground
mining fleet. The cost increases are a result of increased tyre
wear in the final uphill sections of the decline development and
higher diesel, repairs and maintenance costs as waste hauling
distances increase. The current winter months are also the peak
period of the year for electricity tariffs in South Africa.
Management considers there is scope to reverse this cost
increase and has instituted operational efficiency projects in
mining, maintenance and procurement to improve productivity and
reduce costs. However, until any improvements are achieved, a new
development budget of R37,000/m has been adopted for the UK4
development going forward which can be accommodated from existing
contingencies.
Approximately 55,000 tonnes of kimberlite will be mined as part
of the UK4 development which will be processed in batches in a
controlled bulk test supervised by MPH Consulting. The recovered
diamonds will be valued and sold as part of the Company's
established sales cycle. The resulting grade and carat value will
allow for an upgraded SAMREC compliant resource statement to be
issued in Q1 2015. Management considers it more meaningful to delay
the updated resource statement to incorporate the bulk test results
than to issue an interim estimate based on microdiamond analysis
alone. Revenue generated from the diamond sales during development
and bulk testing will be credited to development costs.
Underground drilling of the UK4 block continued during the
quarter, and approximately 600 kg of core samples were submitted
for microdiamond analysis. Results received to date continue to
confirm that recovered grades of up to 60 cpht can be expected from
the K4 kimberlite.
Scoping and mine design studies have been completed based on
approximately 1.5 million tonnes to be mined from the block above
the 365m level which is in addition to the existing geological
resource. The studies recommend bottom up longhole open stoping as
the mining method and estimate that steady state production of
30,000 tonnes per month can be achieved by H2 2015, with the
potential for this to double after development and conveyor belts
for the 47 level block cave are installed past the 365m level.
Mining and processing costs at the initial production rate are
forecast at R169/t.
The design and detailed drawings for the underground conveyor
belt system have been completed under budget. Installation of the
conveyor belt is underway and is scheduled to be commissioned in H1
2015 in time for accelerated mining of the UK4 block. The Company
has experienced no labour issues and continues to hire the
personnel it requires. The labour force at 30 June 2014 totalled
287. Safety remains a major priority for the Company, with the lost
time injury frequency rate for the year to date standing at
zero.
Tailings retreatment
In the three months to 30 June 2014, a decision was taken to
reduce tailings re-treatment processing rates and divert the
surface earth moving fleet to building another 150,000 cubic metre
surface process water dam. This activity needs to be completed in
the dry winter months ahead of rains commencing later in the
year.
As a consequence, the plant processed 96,490 tonnes of tailings
in the period against a budget of 205,000 tonnes. Pleasingly,
diamond recoveries totalled 6,102 carats as recovered grades were
6.32 cpht against a budget of 5 cpht. This month the Company
recovered a 15.2 carat clear white octahedral diamond from the
dumps (photo to be published on website shortly). This is the
largest gem diamond recovered to date from the tailings and
demonstrates the plant's efficiency in recovering larger diamonds
as well as the smaller size fractions.
The reduced production rate in the last quarter allowed for the
de-grit circuit to be installed, which is efficiently removing the
fine sand fraction and allowing for approximately 90% of the
tailings diamonds to be recovered from 60% of the tonnes previously
reporting to the dense media separation plant, thereby reducing
operating costs per tonne and improving the stone size average and
carat value of the diamonds recovered.
Diamond sales (+1.5 mm) for six months ended 30 June 2014
totalled 14,583 carats for proceeds of $909,611, equating to an
average sales price of $62 per carat. At the reduced production
rate, the tailings retreatment operation is breaking even and the
plant is now operating in the optimal configuration for processing
kimberlite from development as this ramps up over the next six
months.
Demand for good quality rough diamonds remains relatively strong
and prices are 5-10% over the prices achieved in December 2013. The
Company is forecasting the market to be steady to modestly higher
for the balance of 2014, with potential for price strengthening in
2015 as world economies continue to recover.
Competent Person
Mr. Paul Sobie, P.Geo., President of MPH Consulting Limited,
being an Independent Qualified Person and a member in good standing
of the Association of Professional Geoscientists of Ontario,
Membership # 0374, has reviewed and approved the technical content
of this news release.
Contact details:
DiamondCorp plc
Paul Loudon, Chief Executive
Tel: +27 56 216 1300
Euan Worthington, Chairman
Tel: +44 7753 862 097
UK Broker & Nomad
Panmure Gordon (UK) Limited
Dominic Morley/Adam James
Tel: +44 20 7886 2500
JSE Designated Advisor
Sasfin Capital (a division of Sasfin Bank Limited)
Megan Young
Tel: +27 11 445 8068
This information is provided by RNS
The company news service from the London Stock Exchange
END
DRLEASXEDAALEFF
Diamondcorp (LSE:DCP)
Historical Stock Chart
From Jun 2024 to Jul 2024
Diamondcorp (LSE:DCP)
Historical Stock Chart
From Jul 2023 to Jul 2024