TIDMDCP
RNS Number : 8363F
Diamondcorp Plc
30 April 2014
30 April 2014
DiamondCorp plc
AIM share code: DCP & JSE share code: DMC
ISIN: GB00B183ZC46
(Incorporated in England and Wales)
(Registration number 05400982)
(SA company registration number 2007/031444/10)
("DiamondCorp", "the Group" or "the Company")
Lace mine Project update
DiamondCorp, the Southern African diamond development and
exploration company, is pleased to provide the following update on
the underground development and tailings re-treatment activities at
the Lace diamond mine in the Free State province of South
Africa.
Highlights
-- Underground development remains close to schedule and within budget.
-- The programme for installation of the underground conveyor
belt system is on schedule and fabrication of the first two legs
has been completed.
-- Surface piling for the raise boring of the life of mine vent shaft has been completed.
-- The plant processed 149,957 tonnes of tailings against a
budget of 140,000 tonnes in the three months ending 31 March
2014.
-- Diamond recoveries for the period totalled 6,953 carats at a
recovered grade of 4.64 carats per hundred tonnes (cpht) against a
budget of 5.00 cpht.
-- The recovered grade in March was 5.81 cpht and April to date is 5.77 cpht.
-- Diamond sales for the year to date have totalled 7,505 carats
at an average price of US$63 per carat.
-- The 400 tonne per hour (tph) tailings sand screen is to be
replaced with a conventional de-grit circuit in May.
-- Underground core drilling designed to better define the rim
of the Main Pipe for finalised cave layout and definition of the
'Bulge' area has intersected significantly more high-grade
kimberlite on the eastern side of the pipe above the 345m level
than was projected in the original Lace geological model.
-- This Upper K4 Block has the potential to add at least 1.0
million tonnes of additional kimberlite to the Lace mine plan which
could be mined, without the requirement for additional project
finance, while the 47 Level Block Cave development progresses.
-- The Company remains on track for the commercial production
ramp up from underground kimberlite mining to commence in H2
2015.
Underground development
The Company's 74%-owned subsidiary, Lace Diamond Mines (Pty)
Limited (LDM) continues to ramp up underground development close to
schedule and within budget.
At the end of March, underground tunnel development was 21%
complete versus a scheduled 24% (1,508m against 1,777m), and is
being achieved at 95% of the project budgeted cost per metre
(R33,616/m against R35,327/m). Development rates were impacted
during the period due to mechanical breakdowns on face drilling
rigs and heavy seasonal rains which caused slippery roadway
conditions on the boxcut ramp. The rains have now ceased, and the
rigs are again providing good availability.
Surface piling for the life of mine vent shaft was completed in
the period, well ahead of mobilising the raise bore due in the
second half of the year.
Pleasingly, the underground mining fleet is providing 88%
availability. The last underground loader required for full
production is currently being assembled and is scheduled for
completion within the current quarter. Operating costs are within
budget for the Company's rebuilt trucks and loaders.
The design and detailed drawings for the underground conveyor
belt system is on schedule (95% complete) and under budget.
Fabrication of the first two legs of the conveyor belt to be
installed is 100% complete and has been delivered to site.
Fabrication of the third leg has begun. There is a total of eight
legs to the conveyor system, which will be progressively
commissioned between Q4 2014 and H1 2015.
The Company has experienced no labour issues and continues to
hire the personnel it requires. The labour force at 31 March 2014
totalled 287. The underground development is now operating with
three mining crews on a three shift basis. A fourth crew will be
recruited when additional development ends and the production level
become available. Safety remains a major priority for the Company,
with the lost time injury frequency rate for the year to date
standing at zero.
The Company remains on track for the commercial production ramp
up from underground kimberlite mining to commence in H2 2015.
Tailings retreatment
Following adjustments to the bottom screen size cut reported
previously, tailings retreatment continued on two shifts in January
and February, and three shifts in March.
During the period ended 31 March, the plant processed 149,957
tonnes of tailings against a budget of 140,000 tonnes. Diamond
recoveries totalled 6,953 carats at a recovered grade of 4.64 cpht
against a budget of 5.00 cpht. Production in January and February
was from the oldest and lowest grade section of the dumps. The
recovered grade for March was 5.81 cpht and April to date is 5.77
cpht.
The 400 tph sand screen commissioned in February did not achieve
the required performance and has been demobilised from site. In
accordance with the supplier contract, the Company only paid for
mobilisation and demobilisation costs. The Company is now
installing a conventional de-grit circuit which has the potential
to increase tailings throughput to 120,000 tonnes per month. This
is expected to be commissioned in May.
Sales of diamonds from tailings recovery for 2014 commenced in
February, with ten sales scheduled for the year. Sales for the year
to date (including carryover of year end stock) totalled 7,505
carats for proceeds of $471,160. The average sales price of $63 per
carat is in line with our forecast for the year.
At current exchange rates, the budget grade and sales price, and
operating costs after the installation of the de-grit circuit, the
tailings re-treatment is forecast to generate positive cashflow of
R9 per tonne.
Demand for rough has improved and prices have increased 5-10%
over the prices achieved in December. The Company is forecasting
the market to be steady to modestly higher for the balance of 2014,
with potential for price strengthening in 2015 as world economies
continue to recover.
Underground drilling
Underground core drilling designed to better define the rim of
the Main Pipe for finalised cave layout and definition of the
'Bulge' area, as previously announced, has intersected
significantly more high-grade kimberlite on the eastern side of the
pipe above the 345m level than was projected in the original Lace
geological model. This block is predominantly higher grade
kimberlite (K4 hypabyssal, otherwise called coherent or CK
kimberlite) and has thus far been defined over an area of
approximately 75m x 75m on the 250m level, and is being actively
delineated above and below to add to the resource base.
No kimberlite of any type above the 345m level is included in
the current mine plan, as definition drilling from surface was not
possible due to the presence of old workings. This Upper K4
resource drilling is now being completed from underground with the
Company's own rig and drilling crews, under the direction of the
Company's independent consultants.
The Upper K4 Block now being defined has the potential to add at
least 1.0 million tonnes of additional kimberlite to the Lace mine
plan which could be mined while the 47 Level Block Cave development
progresses.
In the current Lace geological model, the K4 kimberlite becomes
volumetrically dominant below the 500m level. Previous microdiamond
analysis of the K4 kimberlite has predicted 57 cpht as recoverable
in diamond sizes larger than 1.18mm. Microdiamond analysis of core
from the current drilling is underway and tunnels to independently
bulk test the block are being driven off the existing decline
development. Kimberlite from the bulk test will start to be
processed in the third quarter of 2014 and be completed by year
end.
Mining of the UK4 Block by conventional stoping could commence
in the first quarter of 2015 and reach 30,000 tonnes per month by
the third quarter of 2015. Development of the block would be
financed from existing project finance facilities. MPH Consulting
Limited has been appointed as the competent person with respect to
the bulk test as well as the preparation of an updated resource
statement in the second quarter of 2014, based initially on the new
core drilling and microdiamond work, then subsequently on the bulk
test.
Core drilling of the Bulge area provisionally indicates that the
zone is largely lower grade (volcanoclastic) kimberlite, meaning
that the total recoverable diamond content is likely to be
significantly less than the UK4 Block. Mining of the UK4 Block has
the potential to provide significant additional cashflow which
would allow the Bulge to be bulk tested and (if warranted) financed
from internally generated cashflow, whereas mining of the Bulge
alone would require additional project finance. Further, the UK4
Block has the potential to provide high grade ore while the 47
Level Block cave is developed and matures and smoothes out the
potential lumpiness in tonnage which can occur in the early stages
of caving. For these reasons it is considered a high priority
development target, and the zone where underground production
drilling will now concentrate.
Competent Person
Mr. Paul Sobie, P.Geo., President of MPH Consulting Limited,
being an Independent Qualified Person and a member in good standing
of the Association of Professional Geoscientists of Ontario,
Membership # 0374, has reviewed and approved the technical content
of this news release.
Contact details:
DiamondCorp plc
Paul Loudon, Chief Executive
Tel: +27 56 216 1300
Euan Worthington, Chairman
Tel: +44 7753 862 097
UK Broker & Nomad
Panmure Gordon (UK) Limited
Dominic Morley/Adam James
Tel: +44 20 7886 2500
JSE Designated Advisor
Sasfin Capital (a division of Sasfin Bank Limited)
Megan Young
Tel: +27 11 445 8068
This information is provided by RNS
The company news service from the London Stock Exchange
END
DRLEAXLNAFXLEFF
Diamondcorp (LSE:DCP)
Historical Stock Chart
From Jun 2024 to Jul 2024
Diamondcorp (LSE:DCP)
Historical Stock Chart
From Jul 2023 to Jul 2024