Cuomo Promises Solutions to Subway's Power Problems
August 09 2017 - 4:29PM
Dow Jones News
By Paul Berger
New York Gov. Andrew Cuomo says the biggest cause of the city's
subway delays is power problems, but fixes are on the way.
Instead of the Consolidated Edison utility and the Metropolitan
Transportation Authority pointing fingers at each other every time
there is a problem, Mr. Cuomo said the pair will work together to
inspect, repair and modernize the power system that feeds the
subway.
"This is a massive undertaking," Mr. Cuomo said. "It will be the
first time the system has been gone through and modernized
literally in 80 years."
The fix isn't voluntary. The New York Public Service Commission,
the state's utility regulator, is directing the power company to
take action following several power-related disruptions earlier
this year. If it fails to comply, the regulator can impose
penalties.
In a statement, the utility's chief executive, John McAvoy,
welcomed the initiative, saying that the utility is "fully
committed to implementing the recommendations."
Mr. Cuomo took reporters on a tour of the electrical system
Wednesday, accompanied by Mr. McAvoy and Charlie Hall, a senior
vice president at the engineering consulting firm WSP.
Dressed in khaki slacks and a white polo shirt emblazoned with
the New York state seal, Mr. Cuomo started at an open manhole on
Central Park West, pointing out where power feeds into the subway.
Then, he led reporters into the 59th Street-Columbus Circle
station, onto the tracks and over the third rail to an energy
distribution room.
Subway delays are an increasing problem, with on-time
performance this year languishing at 62.9%, well below the MTA's
target of 75%.
For Mr. Cuomo, who controls the MTA, it is a growing headache,
particularly following two subway derailments this summer as well
as a well-publicized incident in which riders were stuck for almost
an hour in subway cars without air conditioning.
The MTA runs 8,200 trains every weekday. There are myriad
reasons for delays, including sick passengers, overcrowding,
equipment failures, track fires or problems with an antiquated
signal system, which in some places is more than 50 years old.
Mr. Cuomo began Wednesday's tour by saying there were 32,000
power-related delays last year. He included in that figure not just
times when Con Ed lost power, but also when fluctuations in the
power supply caused subway signals and other MTA equipment to
fail.
"It's not the signal that fails," he said, pointing to a chart
of how power flows through the system. "It's somewhere in
here."
Mr. Cuomo ordered the Public Service Commission to investigate
following a crippling power outage in April. The commission's
chairman, John Rhodes, who was also present Wednesday, said that
investigation is continuing.
The commission's review of the April power outage as well as
other power-related delays led to the state's order for a
comprehensive overhaul.
The plan includes changing cables from aluminum to copper and
replacing switches that cannot cope with deviations in power. The
most immediate trouble areas are to be fixed in six months and the
remainder are to be fixed within a year.
Mr. Cuomo emphasized the scale of the problem as he stood in a
relay room at the 59th Street station. About 20,000 relays, each
one in a glass case, stretched in rows along the room. The switches
were installed in the 1970s but were built using 1950s technology,
the governor was told.
There are 300 such rooms throughout the subway system.
Write to Paul Berger at Paul.Berger@wsj.com
(END) Dow Jones Newswires
August 09, 2017 16:14 ET (20:14 GMT)
Copyright (c) 2017 Dow Jones & Company, Inc.
Consolidated Edison (NYSE:ED)
Historical Stock Chart
From Apr 2024 to May 2024
Consolidated Edison (NYSE:ED)
Historical Stock Chart
From May 2023 to May 2024