TIDMBZM
RNS Number : 6504E
Bellzone Mining PLC
11 April 2011
11 April 2011
Bellzone Mining plc
("Bellzone" or the "Company")
Kalia Mine Project Operating Update
Bellzone Mining plc (AIM:BZM), the iron ore and nickel/copper
company developing the Kalia Mine Project, the Forecariah JV and
the Sadeka nickel/copper project in the Republic of Guinea, West
Africa, is pleased to present an operational update for the Kalia
Mine Project.
The resource development plans and detailed feasibility study
("DFS") at the Kalia Mine Project have been progressing well
through 2011 and remain on schedule. A number of key project
activities have been undertaken, as per the project plan, all of
which provide valuable detail to the engineering and cost estimates
required to complete the DFS and further extend our extensive iron
ore resources.
DFS activity highlights:
-- Completion of airborne Lidar surveys, providing 0.5m
topographic contours of the Kalia permit area to provide critical
input to plant layout design, bulk earthworks costing as well
tailings storage facility site selection and design
-- Contracts awarded to undertake the site geotechnical and
hydrological engineering providing key inputs to finalise the mine
plan and site civil engineering requirements
-- Magnetite bulk testwork completed validating the production
of a +68% Fe concentrate with low deleterious elements
-- Magnetite metallurgical test-work completed which is critical
to the design of flowsheets and equipment requirements
-- Preliminary Whittle shell models supporting mine planning
completed
-- Oxide metallurgical test-work undertaken confirming a quality
product is achievable through standard processing techniques
-- Oxide testwork conducted for ore with beneficiation potential
providing input into the flowsheet development and equipment
selection
-- Draft Socio Economic Impact Assessment and Environmental
Impact Assessment reports completed
Magnetite Resource Development
Kalia I
Since the release of the 3.74 billion tonne JORC update in
September 2010, the magnetite resource development programme
focussed on completing and infill plan to further upgrade the
existing 670 million tonne measured and indicated JORC resource.
This programme was completed in the first week of April 2011 and
the Kalia I JORC resource upgrade is expected to be completed in
Q3, 2011.
Magnetite Resource Development Highlights since September 2010
upgrade:
-- 13,022m diamond drilling completed on infill programme
-- 4,188 samples sent for assay
Kalia II
The Kalia magnetite development plan now is to undertake a wide
spaced drilling campaign of the Kalia II magnetite. This drilling
campaign, the first on Kalia II, has commenced and will take
approximately six months to complete.
-- 800m of 17,000m programme completed at Kalia II (as at 8
April 2011)
Oxide Resource Development
Bellzone has mapped 55 km(2) of surface oxide material over the
100% Bellzone Kalia permit. The maiden oxide JORC campaign has been
focused on a 2.3km(2) area located above the existing 3.74 billion
tonne magnetite JORC resource. This material has to be removed
prior to the start of the magnetite operations. Targeting this
material as the initial production source supports the optimisation
of the mining plan and reduces operating cost.
Due to the large number of samples processed in support of the
JORC resource and the unusual congestion in the laboratories in
Perth, Western Australia, we have experienced a delay in finalising
the JORC resource. Currently all metallurgical assay and testwork
has been compiled and is under review prior to issue CSA Global,
Bellzone's independent geologists, for assimilation into the JORC
resource estimation. Taking into account the upcoming Easter
period, Bellzone expects to release the JORC resource estimation in
May 2011.
Oxide Resource Development Highlights:
Kalia I
-- 20,139m reverse circulation drilling completed at Kalia I
-- 7,905 samples from Kalia I sent for assay
Kalia II
-- 4,404m of a 28,000m programme of reverse circulation drilling
completed at Kalia II
-- 796 from Kalia II samples sent for assay
Oxide resource development is ongoing with a drilling campaign
targeting the 13km(2) Kalia II oxides. Current results from Kalia
II are encouraging with thickness of the oxides of over 30m being
measured.
Graham Fyfe, Chief Operating Officer commented: "The start of
2011 has been a very busy period for the company. Not only have we
raised sufficient funds to ensure the Forecariah JV project is
financed to completion, but our various project specific teams have
ensured that all our projects are running full steam ahead. We are
confident of achieving our study and resource development
objectives and moving towards construction start at the Kalia Mine
Project before year end, while continuing the parallel development
of the near term production target Q1, 2012 of the Forecariah JV
project."
Enquiries:
Bellzone Mining plc
Graham Fyfe/Terry Larkan +61 8 9420 8900
Canaccord Genuity Limited
Nominated Adviser and Joint Broker
to Bellzone +44 (0)20 7050 6500
Andrew Chubb/Tarica Mpinga
Renaissance Capital Limited
Joint Broker to Bellzone +44 (0)20 7367 7777
Simon Matthews/Thomas Beattie
Tavistock Communications
Jos Simson/Paul Youens +44 (0)20 7920 3150
+44 (0)7899 870 450
Bellzone Mining plc
Bellzone Mining plc is an exploration and resource development
company with iron ore and nickel / copper permits in the Republic
of Guinea, West Africa.
The Company's flagship project, the Kalia Mine Project has a
JORC resource of 3.74 billion tonnes, located on the Kalia I
prospect. Drilling results and internal estimates indicate that
Kalia Prospect has the potential to host more than 10 billion
tonnes of magnetite and 2.55 billion tonnes of oxide at
surface.
Exploration work continues to further define the potential at
Kalia I on both the magnetite and oxide at surface.
Bellzone is committed to the staged development of the Kalia
Iron Project, which includes a 50mtpa iron ore facility, rail and
port, with initial production scheduled in 2014. Stage one is
planned to bring online 20mtpa oxide production capacity in 2014
and a 10mtpa magnetite concentrator in 2015. Stage two increasing
the oxide output to 30mtpa in 2017 and doubling the concentrate
capacity to 20mtpa by 2018
Bellzone signed an Infrastructure Accord with the Republic of
Guinea giving the Company exclusive rights to the designated port
and rail areas for purposes of conducting studies for the
development of the infrastructure leading to the signing of a
convention and concession. The infrastructure forms a key part of
the Guinea Government's infrastructure strategy and will support
the development of iron ore, bauxite and other minerals in Guinea
through its availability for 3rd party use.
On 2 August 2010, Bellzone signed definitive agreements with
China International Fund ('CIF'). CIF will finance and develop the
rail and port infrastructure and offer a finance package to
Bellzone for the development of the Kalia Mine in exchange for the
first right to purchase 100% of the off--take of the Kalia Mine at
market price.
An exploration programme is currently underway at the Forecariah
Iron Permits that lie between 60 and 80kms from the Guinea south
coast. Bellzone and CIF will jointly develop these permits which
are prospective for oxide and magnetite. The oxide has the
potential to deliver cash flow from a Direct Shipping Ore project
in the short term.
Bellzone has competed an intensive mapping and surface sampling
programme and has defined highly prospective drilling targets at
its Sadeka Nickel/Copper Project. Drilling has commenced and
results are expected in Q2 2011.
This information is provided by RNS
The company news service from the London Stock Exchange
END
DRLGLGDSSGBBGBB
Bellzone Mining (LSE:BZM)
Historical Stock Chart
From Jun 2024 to Jul 2024
Bellzone Mining (LSE:BZM)
Historical Stock Chart
From Jul 2023 to Jul 2024