(All dollar figures are in US dollars unless otherwise
indicated)
TORONTO, Sept. 6, 2017 /PRNewswire/ - New Gold Inc. ("New
Gold") (TSX:NGD) (NYSE American:NGD) today provides an update on
the construction of the company's Rainy
River project, located in northwestern Ontario. Both the project schedule and capital
cost estimate remain in line with New Gold's current plan
(announced in late January 2017).
Rainy River August Highlights
- The process plant underwent a successful closed loop mill test
run with low grade ore
-
- Ball mill and SAG mill tested successfully up to nameplate
capacity
- The mining rate during July averaged over 125,000 tonnes per
day and accelerated to an average of over 135,000 tonnes per day in
August
- Water management pond is complete
- All process facilities are mechanically complete
- Ball mill, SAG mill and the leach carbon-in-pulp process
circuits are fully commissioned
- Water, tails and air systems in the plant are fully
operational
- The refining portion of the process circuit is to be
commissioned in mid-September
- Construction of the tailings management area (TMA) start-up
cell is complete
- Earthworks are 90% complete
- Approval for design and construction of creek
closures using sheet pile was received from the Ontario Ministry of
Natural Resources and Forestry in August
2017
"We are very much looking forward to Rainy River's targeted start-up in the coming
weeks," stated Hannes Portmann,
President and Chief Executive Officer. "We made significant
progress in August. Our mining rate increased to over 135,000
tonnes per day, we completed construction of the TMA start-up cell,
and all process facilities are mechanically complete and in
testing."
Consistent with New Gold's plan, the company should begin
processing ore in mid-September. The estimated development capital
cost from the beginning of this year to the targeted November 2017 commercial production remains
$515 million.
Rainy River Project Photos
About New Gold Inc.
New Gold is an intermediate gold mining company. The company has
a portfolio of four producing assets and two significant
development projects. The New Afton Mine in Canada, the Mesquite Mine in the United States, the Peak Mines in
Australia and the Cerro San Pedro
Mine in Mexico (which transitioned
to residual leaching in 2016), provide the company with its current
production base. In addition, New Gold owns 100% of the Rainy River
and Blackwater projects located in Canada. New Gold's objective is to be the
leading intermediate gold producer, focused on the environment and
social responsibility. For further information on the company,
please visit www.newgold.com.
Cautionary Note Regarding Forward-Looking Statements
Certain information contained in this news release, including
any information relating to New Gold's future financial or
operating performance are "forward looking". All statements in this
news release, other than statements of historical fact, which
address events, results, outcomes or developments that New Gold
expects to occur are "forward-looking statements". Forward-looking
statements are statements that are not historical facts and are
generally, but not always, identified by the use of forward-looking
terminology such as "plans", "expects", "is expected", "budget",
"scheduled", "targeted", "estimates", "forecasts", "intends",
"anticipates", "projects", "potential", "believes" or variations of
such words and phrases or statements that certain actions, events
or results "may", "could", "would", "should", "might" or "will be
taken", "occur" or "be achieved" or the negative connotation of
such terms. Forward-looking statements in this news release include
among others, statements with respect to: planned development
activities for 2017 at the Rainy River project, including the
completion and commissioning of the processing facilities; planned
preparations for operations at the Rainy River project, including
the mining rate and removal of overburden; targeted timing for
permits; targeted timing for commissioning, start-up, production
and commercial production; and targeting timing for development and
other activities related to the Rainy River project.
All forward-looking statements in this news release are based on
the opinions and estimates of management as of the date such
statements are made and are subject to important risk factors and
uncertainties, many of which are beyond New Gold's ability to
control or predict. Certain material assumptions regarding such
forward-looking statements are discussed in this news release, New
Gold's latest annual management's discussion and analysis
("MD&A"), Annual Information Form and Technical Reports filed
at www.sedar.com and on EDGAR at www.sec.gov. In addition to, and
subject to, such assumptions discussed in more detail elsewhere,
the forward-looking statements in this news release are also
subject to the following assumptions: (1) there being no
significant disruptions affecting New Gold's operations; (2)
political and legal developments in jurisdictions where New Gold
operates, or may in the future operate, being consistent with New
Gold's current expectations; (3) the accuracy of New Gold's current
mineral reserve and mineral resource estimates; (4) the exchange
rate between the Canadian dollar, Australian dollar, Mexican peso
and U.S. dollar being approximately consistent with current levels;
(5) prices for diesel, natural gas, fuel oil, electricity and other
key supplies being approximately consistent with current levels;
(6) equipment, labour and materials costs increasing on a basis
consistent with New Gold's current expectations; (7) arrangements
with First Nations and other Aboriginal groups in respect of the
Rainy River project being consistent with New Gold's current
expectations; and (8) all required permits, licenses and
authorizations being obtained from the relevant governments and
other relevant stakeholders within the expected timelines.
Forward-looking statements are necessarily based on estimates
and assumptions that are inherently subject to known and unknown
risks, uncertainties and other factors that may cause actual
results, level of activity, performance or achievements to be
materially different from those expressed or implied by such
forward-looking statements. Such factors include, without
limitation: significant capital requirements and the availability
and management of capital resources; additional funding
requirements; price volatility in the spot and forward markets for
metals and other commodities; fluctuations in the international
currency markets and in the rates of exchange of the currencies of
Canada, the United States, Australia and Mexico; discrepancies between actual and
estimated production, between actual and estimated mineral reserves
and mineral resources and between actual and estimated
metallurgical recoveries; fluctuation in treatment and refining
charges; changes in national and local government legislation in
Canada, the United States, Australia and Mexico or any other country in which New Gold
currently or may in the future carry on business; taxation;
controls, regulations and political or economic developments in the
countries in which New Gold does or may carry on business; the
speculative nature of mineral exploration and development,
including the risks of obtaining and maintaining the validity
and enforceability of the necessary licenses and permits and
complying with the permitting requirements of each jurisdiction in
which New Gold operates, including, but not limited to: in
Canada, obtaining the necessary
permits for the Rainy River project; the lack of certainty with
respect to foreign legal systems, which may not be immune from the
influence of political pressure, corruption or other factors that
are inconsistent with the rule of law; the uncertainties inherent
to current and future legal challenges New Gold is or may become a
party to; diminishing quantities or grades of mineral reserves and
mineral resources; competition; inherent uncertainties with cost
estimates and estimated schedule for the construction and
commencement of production at Rainy
River as contemplated; loss of key employees; rising costs
of labour, supplies, fuel and equipment; actual results of current
exploration or reclamation activities; uncertainties inherent to
mining economic studies including the feasibility studies for the
Rainy River project; changes in project parameters as plans
continue to be refined; accidents; labour disputes; defective title
to mineral claims or property or contests over claims to mineral
properties; unexpected delays and costs inherent to consulting and
accommodating rights of Indigenous groups; risks, uncertainties and
unanticipated delays associated with obtaining and maintaining
necessary licenses, permits and authorizations and complying with
permitting requirements. In addition, there are risks and hazards
associated with the business of mineral exploration, development
and mining, including environmental events and hazards, industrial
accidents, unusual or unexpected formations, pressures, cave-ins,
flooding and gold bullion losses and risks associated with the
start of production of a mine, such as Rainy River, (and the risk of inadequate
insurance or inability to obtain insurance to cover these risks) as
well as "Risk Factors" included in New Gold's Annual Information
Form, MD&A and other disclosure documents filed on and
available at www.sedar.com and on EDGAR at www.sec.gov.
Forward-looking statements are not guarantees of future
performance, and actual results and future events could materially
differ from those anticipated in such statements. All of the
forward-looking statements contained in this news release are
qualified by these cautionary statements. New Gold expressly
disclaims any intention or obligation to update or revise any
forward-looking statements whether as a result of new information,
events or otherwise, except in accordance with applicable
securities laws.
SOURCE New Gold Inc.