Edenville Energy plc (AIM: EDL), the company developing a coal to power project in south western Tanzania, is pleased to update shareholders on the status of the Rukwa Coal to Power Project near Sumbawanga.

The Company has made good progress in partnership discussions since the last project update provided on 8(th) July 2015, specifically in the following areas:

- Cost analyses have been received from several EPC (Engineering, Procurement and Construction) groups, with details of key modules including BTG (boiler, turbine, generator) and BOP (balance of plant) components. Further refinement of costs is expected as work continues. Additional visits to Tanzania by potential partners are expected and continuing technical and commercial analysis by the groups concerned is being undertaken in conjunction with the Edenville team.

- Further development of relationships and discussions with banks for the provision of debt finance to the Rukwa Power Project. Providers of debt finance often work alongside EPC groups to ensure adequate project finance is available when needed throughout the project build.

Edenville Energy is pursuing an integrated approach to project development, with the potential EPC partners and financial institutions involved being progressed in parallel at this stage, working alongside the Tanzanian government to execute its Power System Master Plan. The Power System Master Plan includes transmission expansion and upgrade, along with selection of the most suitable power generation solution for each region. Edenville's Rukwa coal deposit is considered an ideal platform to provide much needed electricity in the Rukwa and surrounding regions. The project's location next to the planned grid expansion gives the potential for provision of baseload power, providing a long term solution to energy needs in the Rukwa region.

Rufus Short, CEO of Edenville commented, "Edenville continues to progress the Rukwa Coal to Power project, with attention focused on the selection of EPC and financial partners. We have made significant progress in this area over the past 6 months and aim to complete the process during Q4, 2015, but external factors beyond our control may influence timing. We will pursue an integrated approach to project development, with the aim of implemention alongside the Tanzanian authorities, to provide a successful outcome for all stakeholders. During Q4, when all interested parties will have concluded meetings and put forward formal proposals, we expect our discussions to reach a point where a structured, multi-party plan can allow the project to progress to the stage where advanced discussions on timing for project development can be entered into with the Tanzanian authorities.

We will continue to update our shareholders on developments relating to the Rukwa Coal to Power Project as they occur. "

 
 Contact 
 Edenville Energy Plc                            +44 (0) 20 7652 
  Rufus Short - CEO                               9788 
 Cantor Fitzgerald Europe 
  (Nominated Advisor and Corporate 
  Broker) 
  Stewart Dickson 
  Philip Davies                                  +44 (0) 20 7894 
  Jeremy Stephenson                               7000 
 IFC Advisory 
  (Financial PR and IR) 
  Tim Metcalfe 
  Graham Herring                                 +44 (0) 20 3053 
  Heather Armstrong                               8671 
 

This information is provided by RNS

The company news service from the London Stock Exchange

END

MSCUGUACBUPAGQM

(END) Dow Jones Newswires

September 08, 2015 02:00 ET (06:00 GMT)

TV Commerce (LSE:TVC)
Historical Stock Chart
From May 2024 to Jun 2024 Click Here for more TV Commerce Charts.
TV Commerce (LSE:TVC)
Historical Stock Chart
From Jun 2023 to Jun 2024 Click Here for more TV Commerce Charts.