Q3 Production Summary
----------------------------------------------------------------------------
Silver
Tonnes Grade Grade Recovery Recovery Silver Gold Eq
Mine Processed Ag g/t Au g/t Ag % Au % oz oz oz(1)
----------------------------------------------------------------------------
Guanajuato 43,714 188 2.22 90.9 91.9 239,992 2,866 411,959
Topia 14,593 316 0.55 89.0 57.8 131,865 149 180,627
Consolidated 58,307 n/a n/a n/a n/a 371,857 3,015 592,586
----------------------------------------------------------------------------
Below is a snapshot of production results for Q3 2012 compared
to Q3 2011:
-- Ore processed at the two operations was up 9% to 58,307 tonnes;
-- Overall metal production was up 22% to 592,586 Ag eq oz;
-- Gold production was up 102% to 3,015 ounces ("Au oz");
-- Silver production was up 8% to 371,857 ounces ("Ag oz");
-- Guanajuato ore grades of 188 g/t Ag and 2.22g/t Au, or 321g/t Ag eq,
were up 32%;
-- Guanajuato achieved very good metallurgical recoveries of 90.9% and
91.9% for silver and gold respectively;
-- Ore processed at Topia was up 22% from Q3 2011, to 14,593 tonnes; and
-- Topia ore grades were down 19% to 442g/t Ag eq.
1. Silver equivalent ounces in 2012 were established using prices of US$28
per oz, US$1,680 per oz, US$0.85 per lb, and US$0.85 per lb for silver,
gold, lead & zinc, respectively, and applied to the recovered metal
content of the concentrates that were produced by the two operations.
Guanajuato Mine Complex
The Guanajuato operation processed 43,714 tonnes (up 6% from Q3
2011) at ore grades of 188g/t Ag and 2.22g/t Au, or 321g/t Ag eq
(up 32% from Q3 2011). Metal production included 239,992 Ag oz and
2,866 Au oz or 411,959 Ag eq oz, up 44% from Q3 2011.
The Guanajuato plant achieved very good silver and gold
recoveries of 90.9% and 91.9% respectively, due to the additional
of a re-grind mill which was commissioned in April and improved
process control.
Development and production in the lower levels of Cata yielded
14,785 tonnes grading 331g/t Ag and 1.87g/t Au and constituted 51%
of total metal production. Ore development on the 525 metre level
in Cata will commence before the end of the year. The current
production from three levels in Santa Margarita area continues to
add to gold production with 9,549 tonnes averaging 5.39g/t Au and
26g/t Ag during the quarter. Similar tonnages and grades are
expected for the fourth quarter.
Ore produced from Los Pozos totaled 11,962 tonnes at grades of
173g/t Ag and 0.77g/t Au. The 420 metre level has been accessed to
allow development along strike during the fourth quarter.
Production stoping in the Guanajuatito area continued from the
160 metre level and development on ore in the north zone on level
200 with ore production totaling 3,407 tonnes at grades of 174g/t
Ag and 0.89g/t Au. During the fourth quarter, stoping will begin in
the north zone with the development of the new 245 metre level
stoping block. Ramp development continues towards both the lower
levels of this mine and towards Valenciana.
The Rayas shaft was closed for maintenance during the latter
part of the third quarter, primarily to enhance the overall safety
conditions. A thorough assessment is underway and, when complete,
will determine the cost and length of time required for
rehabilitative work. In the interim, workers are accessing the mine
via the main Guanajuato Ramp. While this has had a minor impact on
productivity, steps are being taken to mitigate the situation until
such time as the Rayas shaft is back in operation.
San Ignacio Project
On August 21st, the Company announced it had signed a definitive
agreement for the purchase of a 100% interest in certain surface
rights on its wholly-owned San Ignacio Project ("San Ignacio") in
Guanajuato, Mexico. A total of 19.4 hectares have been purchased,
thereby allowing sufficient space for access to and construction of
a portal for the development of a ramp, for waste dumps, and for
auxiliary infrastructure. With the acquisition of the surface
rights, the Company has now applied for the permits required for
the underground development.
The next steps towards the advancement of San Ignacio are as
follows: Phase V drill program is being planned for 2013,
consisting of approximately 7,000 metres of drilling including
approximately 6,000 metres of detailed infill drilling; permitting
is anticipated to be completed by first quarter, 2013; new portal
and ramp construction expected to begin early second quarter, 2013;
first vein development to be extracted by fourth quarter, 2013; and
production anticipated to begin to ramp up early in 2014.
Topia Mine
The Topia operation processed 14,593 tonnes (up 22% from Q3
2011) at ore grades of 316g/t Ag, 0.55g/t Au, 1.69% Pb and 2.78%
Zn, or 442g/t Ag eq (down 19% from Q3 2011). Metal production
included 131,865 Ag oz, 149 Au oz, 497,819 Pb lbs and 812,445 Zn
lbs or 180,627 Ag eq oz, down 9% from Q3 2011.
Silver recovery was 89.0%, gold recovery was 57.8%, lead
recovery was 91.4% and zinc recovery was 90.9%. In addition to
processing the Company's ore, 1,496 tonnes were custom milled for a
local miner. Following the drought in the first half of 2012 that
impeded plant operations, heavy rains in the third quarter caused
humidity problems for crushing and screening. Despite this, overall
throughput was increased due to the draw-down on ore stockpiles.
The inventory of ore at the plant will continue to be depleted
throughout the fourth quarter and is anticipated to be completely
processed by year-end.
Outlook
Metal production for the first nine months of the year totaled
1,705,974 Ag eq oz as compared to 1,654,719 Ag eq oz for the first
nine months of 2011, a 3% increase. Metal production for the third
quarter of 2012 increased 7% over the second quarter of 2012 as
several operating efficiencies, implemented earlier in the year,
began to positively impact operations.
However, based upon production to date, and expectations for
production for the remainder of the fourth quarter, the Company is
adjusting its guidance for metal production to a range of 2.2 to
2.4 million Ag eq oz for fiscal 2012 as compared to 2.5 to 2.75 as
previously anticipated.
Great Panther continues to seek out opportunities to add
production in the districts within which it is already operating.
To that end, the Company has purchased a 100% interest in the 7,900
hectare, El Horcon Property, within trucking distance of the
Company's Guanajuato Complex. El Horcon is a past producing mine
and the Company expects to commence a drill program in the first
quarter of 2014 to delineate a resource.
Robert F. Brown, P. Eng., Vice President of Exploration for the
Company is the Qualified Person for both the Guanajuato Mine
Complex and the Topia Mine, under the meaning of NI 43-101. Aspects
of both mines relating to mining and metallurgy are overseen by
Graham Parsons, Vice President, Operations for Great Panther Silver
Limited and its Mexican subsidiary, Minera Mexicana El Rosario,
S.A. de C.V.
ABOUT GREAT PANTHER
Great Panther Silver Limited is a profitable, primary silver
mining and exploration company listed on the Toronto Stock Exchange
trading under the symbol GPR, and on the NYSE MKT trading under the
symbol GPL. The Company's current activities are focused on the
mining of precious metals from its two wholly-owned operating mines
in Mexico, including the development stage San Ignacio Project. In
addition, the Company is also pursuing acquisition opportunities
throughout Latin America to add additional mines to its portfolio
of properties. Great Panther's mission is to become a leading
primary silver producer by acquiring, developing and profitably
mining precious metals.
For further information, please visit the Company's website at
www.greatpanther.com, or e-mail info@greatpanther.com.
This news release contains forward-looking statements within the
meaning of the United States Private Securities Litigation Reform
Act of 1995 and forward-looking information within the meaning of
the Securities Act (Ontario) (together, "forward-looking
statements"). Such forward-looking statements may include but are
not limited to the Company's plans for production at its Guanajuato
and Topia Mines in Mexico, exploring its other properties in
Mexico, the overall economic potential of its properties, the
availability of adequate financing and involve known and unknown
risks, uncertainties and other factors which may cause the actual
results, performance or achievements expressed or implied by such
forward-looking statements to be materially different. Such factors
include, among others, risks and uncertainties relating to
potential political risks involving the Company's operations in a
foreign jurisdiction, uncertainty of production and cost estimates
and the potential for unexpected costs and expenses, physical risks
inherent in mining operations, currency fluctuations, fluctuations
in the price of silver, gold and base metals, completion of
economic evaluations, changes in project parameters as plans
continue to be refined, the inability or failure to obtain adequate
financing on a timely basis, and other risks and uncertainties,
including those described in the Company's Annual Report on Form
20-F for the year ended December 31, 2011 and reports on Form 6-K
filed with the Securities and Exchange Commission and available at
www.sec.gov and Material Change Reports filed with the Canadian
Securities Administrators and available at www.sedar.com.
Contacts: Great Panther Silver Limited Robert Archer Chief
Executive Officer 1-888-355-1766 Great Panther Silver Limited
Rhonda Bennetto Vice President Corporate Communications
1-888-355-1766info@greatpanther.com www.greatpanther.com
Great Panther Mining (AMEX:GPL)
Historical Stock Chart
From Apr 2024 to May 2024
Great Panther Mining (AMEX:GPL)
Historical Stock Chart
From May 2023 to May 2024