GreenRoc
Mining Plc / EPIC: GROC / Market: AIM / Sector: Mining
07 May 2024
GreenRoc Mining
plc
("GreenRoc" or the "Company")
Amitsoq
Update
Feasibility Study Confirms
Compelling Case for GreenRoc Anode Plant
Notice of Final
Results
GreenRoc Mining plc (AIM: GROC), a
company focused on the development of critical mineral projects in
Greenland, is pleased to announce the results of a preliminary
feasibility study ("Feasibility Study") in respect of the
establishment of a downstream processing plant to produce graphite
active anode material from graphite concentrate produced from the
Company's planned graphite mine at Amitsoq, South
Greenland.
The Feasibility Study, completed
with a cost accuracy to AACE Class 4, was conducted by
SLR Consulting Ltd ("SLR"), an independent UK consulting firm with considerable global expertise in the field of mining and
mineral processing, and was supported by a ca. £250k grant from
Innovate UK's Automotive Transformation Fund.
GreenRoc also provides an update on
its expected financial results for the financial year ended 30
November 2023 at the end of this RNS.
Highlights
·
Pre-Tax Net Present Value at 8% discount rate
(NPV8) of US$837M with Internal Rate of Return (IRR) of
33.8%.
·
After-tax NPV8 of US$545M with IRR of
25.3%.
·
Total gross revenue of US$6.5Bn over the 22-year
period, with total gross profit totalling US$2.7Bn.
·
Years of operation set at 22 to match that planned
for the Amitsoq graphite mine.
·
4-year payback period on capital from start of
production.
·
Initial capital cost (Capex) of US$321M inclusive
of a 25% contingency.
·
Average operating cost (Opex) of US$2,211 per
tonne of CSPG.
·
Average annual processing of 80,000t of graphite
concentrate at 95% graphitic carbon (C(g)) with production of
39,700t of active anode material in the form of coated spherical
purified graphite (CSPG).
GreenRoc's CEO, Stefan Bernstein, commented:
"The Feasibility Study in respect of GreenRoc's planned
downstream processing plant has delivered excellent results, with
an after-tax NPV8 of more than half a billion US dollars. Having
employed the industry's standard techniques and premium
instrumentation where possible, we are confident of the robustness
of the Feasibility Study. This view is corroborated by the
inclusion of a 25% contingency which forms part of the modelled
capital cost of US$321M.
"This Feasibility Study firmly places GreenRoc as one of the
few contenders to supply the European EV Battery industry with
domestically produced active anode material. On behalf of GreenRoc,
I would like to extend our gratitude towards Innovate UK for the
generous support of a £250k grant towards this Feasibility Study
though its Automotive Transformation Fund.
"There are further possible improvements to the process design
which we will be looking into in a second stage, commencing
shortly, and we will provide updates on that in due
course.
"With the already positive Preliminary Economic Assessment of
the Amitsoq graphite mine and now this compelling assessment of the
economics of establishing a downstream anode processing plant for
our graphite, our confidence in our plans for a vertically
integrated production model for Amitsoq, from mine to battery anode
material production, has been greatly
reinforced."
Details
The Feasibility Study was project
managed by the Company and
conducted by SLR Consulting Ltd with
contributions from three expert consultants,
namely Benchmark Mineral Intelligence, ProGraphite and Decision
Risk Analytics.
A key component of Li-based
batteries is the active anode material ("AAM") which is composed of
graphite in the form of coated spherical purified graphite
("CSPG"). Presently, China has a near monopoly, delivering more
than 90% of the world's production of CSPG. With the energy
transition seeing a gradual replacement of the world's internal
combustion engine vehicles with electric vehicles and a growing
demand from Stationary Battery Storage Systems for solar energy
farms and other uses, a 400% growth in demand for battery grade
graphite is forecast by leading market analysts. There is therefore
a political desire to urgently initiate production of domestically
sourced and processed graphite for the European and North American
battery industries.
The raw material for production of
CSPG is natural flake graphite concentrate. The production of CSPG
consists of a series of intermediate steps: first, the graphite
concentrate is micronised to a standard particle size using a
rotary impact mill. Then the graphite flake particles are
introduced to a rounding impact mill or shaping mill, which turns
the angular graphite flakes into rounded particles (speronized
graphite). Purification then takes place via chemical leaching. In
the Feasibility Study, this involved initially assessing a
two-stage leaching process using a mix of hydrofluoric,
hydrochloric and nitric acids to arrive at the required >99.95%
purity. Finally, the spherical purified graphite (SPG) is coated
with pitch and heated in kilns for about 24 hours before using
high-intensity magnet separation for the removal of any impurities
introduced during machining. The end-product CSPG is then sold to
the battery industry to serve as AAM in lithium-ion
batteries.
For the Feasibility Study, SLR has
used proven state-of-the-art technology based on the use of
equipment produced by Chinese manufacturers, including microniser
impact mills, impact rounding mills, cyclones and air classifiers
and filters, fitted with German electronic steering
systems.
The processing plant will consist of
16 parallel micronisation/spheronisation lines each equipped with
five microniser mills and 13 spheroniser mills. The micronisation and spheronisation circuit is designed to
provide a graphite product with high tap density (close to 1.0
g/cm3) and the ability to produce a range of
characteristic particle sizes of d50 of 10 µm to 20 µm
depending on specific settings and requirements from the battery
industry.
Purification will take place in four
parallel leaching lines with a final stage of coating taking place
in eight parallel lines with subsequent baking in kilns and final
magnetic removal of any metal particles introduced during the
processing.
The Discounted Cash Flow ("DCF")
model provided as part of the Feasibility Study shows a
Pre-Tax Net Present Value at 8% discount
rate (NPV8) of US$837M with an Internal Rate of Return
("IRR") of 33.8%, while the After-Tax NPV8 is US$545M
with an IRR of 25.3%. The corporate tax is set at 22%, which is an
average number for northern European Countries.
These NPV calculations are based on
a 22-year production of 39,700t of CSPG per annum (from 80,000t of
graphite concentrate at 95% graphitic carbon (C(g)), similar to the
life of mine provisionally planned for the Amitsoq mine.
However, as previously stated, the resource at Amitsoq could
sustain a longer mine life (see the RNS of 23 January 2023). Based
on 22 years of production, the total gross revenue for the anode
plant has been calculated at US$6.5Bn over that period, with total
gross profit totalling US$2.7Bn.
The initial capital cost is US$321M
which includes a 25% contingency, while the operating cost is
US$2,211 per tonne of produced CSPG. This results in a 4-year
payback period on capital from the start of production.
The DCF model is based on a forecast
price for CSPG of US$7,500 per tonne and with two types of
bi-product (undersize graphite material) attracting a forecast
price of US$300 per tonne.
The Feasibility Study has assumed
that the anode plant operation will purchase the key input raw
material, graphite concentrate, at a forecast market price of US$
1,100 per tonne. This is in keeping with the approach of
carrying out the Feasibility Study for the downstream anode plant
as an entirely stand-alone economic assessment, separate to the
economic assessment of the Amitsoq graphite mine and primary
processing plant (in relation to which, refer to the results of the
Preliminary Economic Assessment released by RNS on 31 October
2023). In practice, however, the cost to the anode plant
operation of the graphite concentrate feedstock is expected to be
determined by the cost of production of graphite concentrate from
the Amitsoq mine rather than by market prices.
One of the largest cost elements in
the economic model relates to power consumption (ca. 250 GWh per
annum) for all of the various stages of processing and amounts to
ca. US$318 per tonne of produced CSPG which is ca. 14% of the total
operating cost of US$ 2,211 per tonne of CSPG. This makes the
choice of a site very important in keeping operating costs down and
reducing CO2 emissions. Accordingly, GreenRoc is
reviewing several options for the location of the processing plant.
The cost of labour is set at that for an
average Northern European country.
In the near future, SLR will also
look at an alternative purification technique using a combination
of sodium hydroxide and acid mixtures other than hydrofluoric acid.
Such sodium hydroxide-based purification is likely to be
less expensive and have lower environmental impact
and regulatory requirements than the standard hydrofluoric acid
based technology. Early qualitative testwork conducted by
ProGraphite on Amitsoq graphite suggests that the high purity
requirement of 99.95% can be met using sodium hydroxide leaching
(see the RNS of 20 January 2023). ProGraphite is currently
undertaking a series of tests to constrain the use of chemicals for
this purification technique, the results of which will be
incorporated in an update to the Feasibility Study.
Another point of potential
refinement is the costing for an onsite nitrogen gas production
plant at the processing plant location. Nitrogen gas is used in the
kilns where the final CSPG material is baked, hindering the
oxidation (burning) of CSPG particles. In the current Feasibility
Study, nitrogen gas is purchased in tanks and makes up a
considerable portion of the consumables. Accordingly, a potential
cost saving may be achieved by establishing local production of
nitrogen gas.
With the completion of this
Feasibility Study for the Anode Processing Plant, GreenRoc can now
demonstrate that running a vertically integrated production of
graphite anode material, based on graphite concentrate mined at the
Company's planned Amitsoq mine, is a viable and potentially
profitable undertaking. The next milestone with regard to the
processing plant is identifying the site for the plant, and setting
up a pilot scale processing plant to start the qualification
process, which should lead to the signing of off-take agreements
with the battery industry.
Expected Final Results
The Company expects to report a
consolidated loss of £1,693,000 for the year to 30 November 2023
(2022: £1,230,000), including an exceptional £787,000 impairment
charge for the surrender of the Melville Bay project, which was
announced by GreenRoc on 7 February 2024. The Company expects to
report year-end consolidated net assets of approximately £9,027,000
(2022: £8,965,000), comprising non-current assets of £9,741,000 and
net current assets of £290,000 offset by a deferred tax liability
of £1,004,000. All of the aforementioned figures for the year to 30
November 2023 are unaudited.
Greenroc expects to announce its
final audited full year results for the year ended 30 November 2023
later this month.
This announcement contains
inside information for the purposes of the UK Market Abuse
Regulation and the Directors of the Company are responsible for the
release of this announcement.
Forward Looking
Statements
This announcement contains forward-looking statements relating
to expected or anticipated future events and anticipated results
that are forward-looking in nature and, as a result, are subject to
certain risks and uncertainties, such as general economic, market
and business conditions, competition for qualified staff, the
regulatory process and actions, technical issues, new legislation,
uncertainties resulting from potential delays or changes in plans,
uncertainties resulting from working in a new political
jurisdiction, uncertainties regarding the results of exploration,
uncertainties regarding the timing and granting of prospecting
rights, uncertainties regarding the timing and granting of
regulatory and other third party consents and approvals,
uncertainties regarding the Company's or any third party's ability
to execute and implement future plans, and the occurrence of
unexpected events.
Actual results achieved may vary from the information provided
herein as a result of numerous known and unknown risks and
uncertainties and other factors.
**ENDS**
For further information,
please contact:
GreenRoc Mining Plc
Stefan Bernstein,
CEO
|
+44 20 3950
0724
|
Cairn Financial Advisers LLP (Nomad)
James Caithie / Sandy Jamieson / Louise
O'Driscoll
|
+44 20 7213
0880
|
Oberon Capital (Broker)
Nick Lovering / Adam
Pollock
|
+44 20 3179
5300
|
St
Brides Partners Ltd (Financial PR &
IR)
Paul Dulieu / Isabel De Salis /
Isabelle Morris
|
+44 20 7236
1177
greenroc@stbridespartners.co.uk
|
About
GreenRoc
GreenRoc Mining plc is an AIM-quoted company which is
developing mining projects in Greenland in critical, high-demand
and high-value minerals. Led by a group of highly experienced
mining industry professionals, GreenRoc has 100% ownership of the
following high-grade critical mineral projects both of which
benefit from defined Resources:
·
The Amitsoq Graphite
Project, the Company's flagship project and one of the highest-grade
graphite deposits in the world with a combined Measured, Indicated
and Inferred JORC Resource of 23.05 million tonnes (Mt) at an
average grade of 20.41% graphite, giving a total graphite content
of 4.71 Mt; and
·
The Thule Black Sands Ilmenite
Project ('TBS'), which has an
initial Mineral Resource of 19Mt at 43.6% Total Heavy Minerals with
an in-situ ilmenite grade of 8.9%.
Key Points about Amitsoq,
GreenRoc's Flagship Asset
1. Amitsoq is located in the Nanortalik
region of southern Greenland, in year-round ice-free waters and on
the same latitude as far northern Scotland.
2. GreenRoc is focused on fast-tracking the
development of Amitsoq into a producing mine in the shortest
possible timeframe to meet critical demand from Electric Vehicle
('EV') manufacturers in Europe and North America for new, high
grade and conflict-free sources of graphite.
3. The Amitsoq Island Deposit
has a total inferred, indicated and measured JORC Resource of 23.05
million tonnes (Mt) at an average grade of 20.41% Graphitic Carbon
("C(g)"), giving a total graphite content of 4.71 Mt. This makes
Amitsoq one of the highest-grade graphite projects in the
world.
4. Significant further resource upside exists at
Amitsoq as the Amitsoq Island Deposit is open in at least two
directions, with potential for considerable further expansion via
the similarly high-grade Kalaaq Mainland Deposit as well as a
series of other high-grade targets within GreenRoc's licence
package.
5. The Amitsoq Island Deposit was in small-scale
production about 100 years ago, and there remains considerable
underground mine development in place from that time, which will be
of considerable benefit to GreenRoc in the mine construction
phase.
6. In GreenRoc's test work
programmes:
a. Micronisation and spheronisation test work has
proven that Amitsoq graphite can be readily upgraded to high-grade,
anode-quality graphite, known as high purity spherical graphite or
cSPG, a critical component in the Li-ion battery of an
EV.
b. Amitsoq spheronised graphite has achieved higher
than 99.95% purity with relatively little energy input and
processing and using a milder alkaline purification method compared
to the industry standard hydrofluoric acid, boding well for future
production costs and sustainability
commitments.
c. Electrochemical testing of Amitsoq graphite
anode material within a test Li-ion battery cell has shown that it
performs very well, in part due to its good
crystallinity.
7. The results of a Preliminary
Economic Assessment (or PEA) for Amitsoq released on 31 October
2023 give a post-tax NPV8 for the Project of US$179M, an IRR of
26.7% and capex estimated at US$131M (including a 25%
contingency). These figures solely relate to the economics of
a mining and primary processing operation in South Greenland and do
not take into account any potential upside from a downstream
processing operation which GreenRoc intends to establish in Europe
or the USA.
8. In relation to that downstream business,
GreenRoc is currently undertaking a Feasibility Study into the
establishment of a graphite spheronisation processing plant to
produce cSPG from graphite concentrate delivered from Amitsoq. This
Feasibility Study, which is expected to be completed in H1, 2024,
has been part-financed by a grant of approximately £250,000 from
the UK's Automotive Transformation Fund.
9. Following a detailed evaluation process, the
European Raw Materials Alliance has expressed its support of
GreenRoc and its Amitsoq graphite project, stating that:
"GreenRoc's graphite resource is of global importance and, together
with the Company's strategy, will enable the European Union to
achieve a certain level of independence for the electrical vehicle
supply chain. ERMA has approved the Amitsoq Graphite project and
will engage to support its development and financing to produce
these critical raw materials for the benefit of the European Union
goals." (see RNS dated 8 February 2023).