Bilbao Silver-Lead-Zinc Project - Preliminary Economic Assessment
TORONTO, ONTARIO--(Marketwired - Apr 28, 2014) - Xtierra Inc.
(TSX-VENTURE:XAG) ("Xtierra" or the "Company"), reports that it has
received an updated NI 43-101 compliant resource estimate and a
Preliminary Economic Assessment (PEA) on the Bilbao Project, both
prepared by RungePincockMinarco (Canada) Limited (RPM).
The Bilbao Project is a polymetallic sulphide and oxide
replacement silver-lead-zinc-copper deposit located approximately
500km northwest of Mexico City in the southeastern part of the
State of Zacatecas.
RPM updated the previous resource model taking into account
additional drilling completed in both 2012 and 2013 and coordinated
and supervised various third party independent consultants to carry
out various studies including: Nordmin Engineering Ltd. developed a
mine design and production schedule; DRA Americas Inc. analyzed
metallurgical testing and recovery methods and designed a process
plant; Golder Associates carried out various environmental studies
including the design of a tailings disposal facility; and Micon
International Limited carried out a high level review of metal
markets.
The following disclosure is based on and/or derived from the
PEA. The PEA is preliminary in nature in that it includes in part
inferred mineral resources that are considered too speculative
geologically to have the economic considerations applied to them
that would enable them to be categorized as mineral reserves.
Mineral resources that are not mineral reserves do not have
demonstrated economic viability. There is no certainty that the
results projected by the PEA will be realized with further work and
actual results may vary substantially. Because inferred resources
are speculative, the modifying factors that are applied to assess
the potential economic viability of the project are also
speculative.
Exploration and Drilling
RPM, after reviewing the extensive work previously completed and
the large amount of information generated, recommended extending
the scope of the previously completed infill drilling program by a
minimum of four holes and assaying historical core in strategic
locations.
Six infill holes were drilled in June 2013, completing an
additional drilling campaign in the southern part of the
silver-zinc-lead project. This drilling followed a 10 hole, 2032
metre infill drilling campaign during the third quarter of
2012.
Since 2006, Xtierra has drilled 113 diamond drill-holes in the
Bilbao deposit. All of the drill-holes are diamond NQ-HQ core holes
with most (104) being vertical. The drill campaigns defined a
general grid of 50 m by 50 m and a tighter drilling grid of 26
holes defining a 35 m by 35 m in the high grade core. The drilled
zone extends over an area of 530m along north-south axis and 580m
along east-west axis.
Mineral Resource Estimates
The new Zn/Pb/Ag/Cu resource estimation of the Bilbao deposit
was prepared by RPM to incorporate new drilling information
acquired during 2011-2013. The geological model was generated using
113 holes (all the logged drill holes). The block resource model
was estimated using 105 holes which had assays. A lithology model
was built and Indicator and Ordinary Kriging (OK) were used to
estimate Zn, Pb, Ag and Cu resources. Density measurements were
updated using 224 new density determinations completed since the
last 2010 model was constructed. The previous 2011 model was based
on the average of 14 measurements and assigned a density of 3.6g/cc
to sulphide blocks while the new 2013 model established a mean
density of 3.3 g/cc for the sulphide zone.
RPM used three year trailing average prices of US$0.94 lb/Zn,
US$1.01 lb/Pb and US$30.24 oz/Ag for purposes of determining cutoff
grades and Zn equivalent values. Metallurgical recoveries were
applied in the equivalent equation as 76.7%, 90.6% and 73.4% for
Zn, Pb, and Ag, respectively. The Zn equivalent equation used is as
follows: Zneq = Zn + 0.969*Pb + 0.09947*Ag.
The total resources by mineral type at 3% Zn equivalent cut-off,
excluding approximately 1 million tonnes of previously mined out
ore, estimated by RPM and reported in April 2014 are shown in the
following table:
Ore Type |
Zn equiv. (%) |
Indicated Tonnes |
Inferred Tonnes |
Total Tonnes |
Zn (%) |
Pb (%) |
Ag (ppm) |
Cu (%) |
Oxide |
6.50 |
791,082 |
3,069,582 |
3,860,664 |
1.70 |
2.33 |
42 |
0.17 |
Mixed |
7.10 |
778,336 |
238,923 |
1,017,259 |
2.06 |
2.17 |
52 |
0.18 |
Sulphide |
6.88 |
4,555,809 |
1,201,032 |
5,756,841 |
2.03 |
1.40 |
69 |
0.17 |
Total |
6.76 |
6,125,227 |
4,509,537 |
10,634,764 |
1.91 |
1.81 |
58 |
0.17 |
The previous resource estimation was originally carried out by
Richard Parker Consulting Geologist in 2011 and included 84 drill
holes. The resources reported in 2011 (including both oxide and
sulphide) were 10,617,891 tonnes @ 6.48% Zneq in the Indicated
category and 430,000 tonnes @ 5.19% Zneq in the Inferred category.
(Technical Report dated April, 2011 entitled "Geology and
revised Minerals resources of the Bilbao Silver-Lead-Zinc Deposit -
State of Zacatecas, Mexico" by RTG Parker, Consulting
Geologist).
Net Smelter Return Cut-off Value
The Net Smelter Return (NSR) cutoff value of US$45.21 per tonne
of ore used for the Bilbao Project stope tonnes and grade
determination is based on direct mining, processing and G&A
costs.
Potentially Mineable Resource
The potentially mineable underground resource is estimated by
RPM to be 5.2M tonnes at grades of 2.10 % Zn, 1.40 % Pb and 63.96
grams Ag per tonne. The tonnes and grade include an average
dilution of 10 percent, at zero grade, as well as mining losses of
5%. The RPM PEA relies on Indicated Mineral Resources
(approximately 75 percent of the total resource tonnes) as well as
Inferred Mineral Resources (approximately 25 percent of the total
resource tonnes).
Mine Design and Production Planning
The current mine plan incorporated in the PEA targets the
extraction of the sulphide zone only given the results of the
metallurgical test work on the oxide and transition zones completed
to date.
The mine production schedule is based on a production rate of
2,000 tpd of potentially economic mineralization, or 720,000 tonnes
per year. This provides for a mine life of approximately 8 years,
mining out the resources available.
Underground mining methods will be used to access the sulphide
zone located approximately 50 meters below surface, and accessed
via a portal and ramp system. The main access to the underground
mine will be via a main ramp from surface to the 1860 Level.
The main proposed mining method is Longhole Open Stoping using
downholes, while near the top of the deposit Longhole Open Stoping
using upholes will be employed. Longhole stopes will be backfilled
with a cemented rock fill.
Based on the selected mining method a dilution factor of 10% is
applied which allows for dilution from hanging and footwall wall
exposures and cemented backfill dilution which results from
blasting against backfilled stopes. Mining recovery of 95% is
assumed for this deposit.
Recovery Methods
The mineral processing plant described is for the treatment of a
silver-lead-zinc sulfide ore at a design throughput rate of 2,000
t/d. The mineral processing plant will produce lead-silver and zinc
concentrates which will be transported off-site.
The process flow sheet selected for the Bilbao process plant
comprises two stages of crushing, two stages of grinding, lead
rougher flotation, lead regrind, lead cleaner and lead concentrate
and dewatering stages, zinc rougher flotation, zinc regrind, zinc
cleaner flotation and zinc concentrate and dewatering stages.
The plant will be capable of processing 720,000 tonnes per year
with an average grade of 2.1%, 1.4% and 63.96 g/t of zinc, lead and
silver respectively. The plant has an operating regime of 360 days
per year, 7 days per week, 24 hours per day and a plant utilization
of 92%, resulting in an average nominal throughput of 91 tonnes per
hour.
The plant will produce, on average, 16,913 dry tonnes per year
of silver-rich lead concentrate, and 26,966 dry tonnes per year of
zinc concentrate. Plant recovery is estimated to be 76.7% for zinc,
90.6% for lead and 73.4% for silver over the life of the mine.
Capital and Operating Costs
Project capital costs, as of April 2014, are estimated by RPM to
be US$99.5 million including an allowance for contingencies of
US$8.7 million, equivalent to 8.8% of total capital expenditure.
The capital cost outlines total pre-production capital of US$91.2
million and remaining other capital and sustaining capital costs of
US$8.3 million for the eight year production life, including
acquisition to replace mine equipment fleet, plant and
infrastructure.
The operating expenditure is based on all development work in
waste being performed by contractors, and stope development by
Xtierra personnel and equipment fleets. The strategy was determined
as the most cost effective for the operation and ensures
sustainability of a skilled labor force. The average total unit
operating cost over the life of the project is US$66.90/t of ore,
including mining, processing, general and administration, freight
and insurance, smelting, refining and penalty costs.
Economic Analysis
The economic analysis was completed by RPM for a 720,000 tonne
per year processing plant capacity and is based on the potentially
mineable underground resource of 5.2 million tonnes at grades of
2.10 % Zn, 1.40 % Pb and 63.96 grams Ag per tonne.
At the request of Xtierra, RPM has based its economic analysis
of the Bilbao project on three-year average metal prices. For the
three-year period ending 31 October, 2013, the rolling average
prices based on LME cash buyer quotes for zinc and lead, and as
reported by Kitco on www.kitco.com for silver are as follows: Zinc
US$0.92/lb; Lead US$1.00/lb; and Silver US$30.38/oz.
Total revenue for the project is based on 720,000 tonnes per
year production to be reached in production year 2 and continuing
for the life of the project average US$73.6 million per year (gross
revenue). The current plan estimates 11,000 tonnes of zinc
concentrate and 7,000 tonnes of lead concentrate in the first
production year.
Cash Flow
Pre-tax earnings total US$59.9 million over the eight year
mining plan to extract the Indicated and Inferred potentially
minable resource. Economic results of the Bilbao Project pre-tax
cash flow model indicate an Internal Rate of Return (IRR) of 13.2%
and a Net Present Value (NPV) of US$11.0 million at a 10% discount
rate and a NPV of US$18.7 million at an 8% discount rate. RPM
considered the ten percent discount rate appropriate for this
evaluation as the overall project risks are considered to be
relatively low in terms of total capital committed, geological risk
and market risk.
This preliminary economic assessment is preliminary in nature.
It includes inferred mineral resources that are considered too
speculative geologically to have the economic considerations
applied to them that would enable them to be categorized as mineral
reserves, and there is no certainty that the preliminary economic
assessment will be realized.
After-tax net cash flow totals US$32.6 million over the eight
year mine plan. Economic results of the Project after-tax cash flow
model indicate an IRR of 8.1% and an after-tax NPV of negative
US$5.8 million at a 10% discount rate and a NPV of US$359,000 at an
8% discount rate.
RPM also developed a sensitivity analysis to the Project's IRR
and NPV to +/- 15 percent changes to key assumptions in the cash
flow model based on variations in key project elements of metal
price, operating and capital costs. The Bilbao Project was found to
be most sensitive to changes in operating costs where a 15%
reduction in operating costs would result in pre-tax NPV of US$45.0
million and a pre-tax IRR of 22.0%. RPM noted that there may be
opportunity to reduce operating costs significantly (~US$5/t to
US$6/t) by reducing the number of stopes filled with backfill. With
regard to changes in metal prices, the Bilbao Project was found to
be most sensitive to movements in the price of silver.
Recommendations by RPM
Recommendations have been made by RPM in the PEA identifying
various opportunities to increase the mineable resource and reduce
operating costs through additional exploration and engineering,
improving the overall economics of the project. RPM recommendations
include:
- Additional definition drilling targeted at the Bilbao
transition and sulphide zones could lead to re-classification of
inferred resources to indicated resources, potentially contributing
to the total mineable resource studied at the pre-feasibility
level;
- The potential to increase level spacing and correspondingly
reduce level development, through use of cable bolts, may lead to
lower mine development costs and should be further assessed;
- Further analysis of hydraulic and sand backfilling options, in
terms of preparation and distribution, may further reduce overall
operating costs;
- There may also be opportunity to reduce operating costs
significantly (~US$5/t to US$6/t) by reducing the number of stopes
filled with backfill all together. Further geotechnical study would
need to be carried out for this scenario to better understand
possible ore losses with pillars left in place, and possible
recovery of these pillars through caving activity. Potential also
exists for deferral of ramp and associated development;
- Inclusion of transition zone material in the mine plan should
be investigated (requiring additional metallurgical testwork) to
extend the life of mine and/or potentially increase the mining rate
per year;
- Further optimization of stope sequencing could lead to improved
cash flow and should be studied;
- Exploration drilling at the Bilbao 2 area, approximately 1.5 km
south of Bilbao, has potential to offer additional mineral
resources to the project due to the fact that current trenching,
sampling and resulting soil geochemistry information identifies
similarities between the two areas. An additional source of feed to
the designed plant could lengthen the overall life of the mine,
increase the daily production rate, or result in a combination of
the two, improving the NPV and IRR of the project.
RPM noted that the Bilbao deposit contains a reasonable quantity
of mineral resources between the oxide, transition, and sulphide
mineral zones; however, the lack of metallurgical test data
available for the transition zone and identified recovery
challenges for the oxide zone currently limit the scope of this PEA
to the total mineable sulphide resources to offset the capital
costs associated with the project.
A Technical Report in compliance with NI 43-101 has been filed
on SEDAR.
Future Plans
Having now received the completed Preliminary Economic Analysis
for the Bilbao Project from RPM, the Company's focus going forward
is to seek alternatives to maximize the value of Bilbao including
seeking to develop Bilbao either alone or in joint venture with a
partner or through corporate transactions.
RPM have made numerous recommendations throughout the PEA
identifying various opportunities to increase the mineable resource
and reduce operating costs through additional exploration and
engineering, improving the overall economics of the Bilbao
project.
Further metallurgical test work on the oxide ore to optimize
economic metal recoveries, including the recovery of lead by means
of gravity separation, has shown some promise and further
metallurgical test-work on the oxide ore should be undertaken.
The continuing operations of the Company are dependent upon its
ability to raise adequate financing and additional funding will be
required for working capital, optimisation and feasibility studies,
further exploration and for financing in the longer term to develop
the Bilbao project.
Cautionary
Notes:
This press release may contain "forward-looking information"
within the meaning of applicable Canadian securities legislation.
The TSX Venture Exchange has not reviewed and does not accept
responsibility for the adequacy or accuracy of the content of this
release.
For further information visit www.xtierra.ca.
Xtierra Inc.Gerald GauthierPresident & Chief Operating
Officer+1 (416) 362-8243Xtierra Inc.Tim GallagherDirector+1 (416)
925-0090Xtierra Inc.Luis De La FuenteDirector Mining (Mexico)+52
(492) 924-4254info@xtierra.cawww.xtierra.ca
Xtierra (TSXV:XAG)
Historical Stock Chart
From Dec 2024 to Jan 2025
Xtierra (TSXV:XAG)
Historical Stock Chart
From Jan 2024 to Jan 2025