$1.1 billion NPV
(8%) • 19.0% IRR • 22 year mine life • Opportunities for
exploration and optimization
February 4, 2021
– All figures in C$ unless otherwise
noted
TSX Venture Exchange Symbol: NCX
Highlights
- The 2021 PEA confirms that the North Island Project is one
of the most attractive copper-gold porphyry projects in
Canada:
-
- Long mine life of 22 years with average annual production of
177 mm lbs Cu Eq. over the first 6 years, including 112 mm lbs of
copper, 112 koz of gold and 2.7mm lbs of molybdenum
- Average annual after tax free cash flow of $321 million during the first 6 years and
$224 million over the life of the
operation
- First quartile AISC of $0.77/lb
Cu (net of by-products) and $2.01/lb
Cu Eq. over first 6 years
- Attractive economics with $1.1
billion After-tax NPV (8%) and 19% After-tax IRR
- Attractive payback of 3.9 years driven by modest capex of
$1.4 billion due to excellent
infrastructure from historical mining and other industrial
activity
- Northisle is committed to sustainable mine
development:
-
- Northisle will pursue a collaborative, inclusive approach to
consultation in order to develop a project which creates benefits
for First Nations, local communities, shareholders and project
stakeholders
- The Project benefits from renewable BC power and the Company
will investigate multiple opportunities to reduce overall impact
including electrified mining operations as part of trade-off
studies
- Multiple opportunities to further improve the Project
through optimization and exploration with prospective targets at
Pemberton Hills, Red Dog and Hushamu planned for 2021
drilling
VANCOUVER, BC, Feb. 4, 2021
/CNW/ - Northisle Copper and Gold Inc. (TSXV:
NCX) ("Northisle" or the "Company") is pleased to announce
that the positive results from a Preliminary Economic Assessment
(the "2021 PEA") for its 100% owned North Island Project confirm it
is one of the most attractive copper-gold porphyry projects in
Canada.
The 2021 PEA is based on the Company's 100% owned Red Dog and
Hushamu deposits and has been developed with a focus on processing
a target of 600MT of mineralized
material within estimated mineable pit shells. The PEA contemplates
a low strip ratio open pit mining operation which incorporates a
75,000 t/d concentrator and is anticipated to produce a
high-quality copper concentrate with a significant gold by-product
as well as a high-grade molybdenum concentrate.
Key performance indicators are summarized in Table
1 below.
Table 1: Summary
Project Metrics
|
|
Production
|
AISC
|
After-tax Avg.
Free Cash Flow
|
After-tax
NPV (8%)
|
After-
tax IRR
|
GHG
Emissions (kg CO2e/lb)
|
|
Cu
(mm lbs)
|
Au
(koz)
|
Cu Eq.
(mm lbs)
|
Cu
($/lb)
|
Cu Eq.
($/lb)
|
$ mm
|
$ mm
|
%
|
Cu
|
Cu Eq.
|
|
|
|
|
|
|
|
|
|
|
|
First 6 years
average
|
112.1
|
111.8
|
177.5
|
$0.77
|
$2.01
|
321
|
1,059
|
19.0
|
0.66
|
0.41
|
Life of mine ("LOM")
average
|
95.9
|
99.9
|
155.9
|
$0.90
|
$2.14
|
224
|
|
|
|
|
|
|
|
|
|
|
|
Note: Cu Eq. based on
Base Case metal prices and includes molybdenum and rhenium. See
Table 3 for details.
|
Sam Lee, President and CEO of
Northisle commented, "I am delighted with the progress we have made
in demonstrating that the North Island Project is one of the most
attractive copper and gold development projects today. The 2021 PEA
illustrates a significant improvement in the potential of the North
Island Project. Copper and gold production increased materially
resulting in a significant increase in NPV and IRR, while all-in
sustaining costs remain in the first quartile and initial capital
is modest for a long-life and significant copper and gold asset.
The concentrate planned to be produced by the North Island Project
is anticipated to be a premium product which would be highly
attractive to global smelters. Furthermore, the significant gold
production is anticipated to provide several options for lower cost
capital financings. We are excited to be advancing what we
believe is one of the most attractive Canadian copper projects
during the start of a new mining super cycle.
There exists a multitude of opportunities to develop a mine that
is truly sustainable in all respects. We are excited to continue
our consultation work with First Nations, local communities,
governments, and key project stakeholders as we advance this
important and compelling project. We have direct access to clean
power in British Columbia that
will drive our project towards becoming a lower carbon emissions
operation. Over the coming months, we will continue to optimize key
project parameters to create additional value for shareholders
while focusing on reducing the impact of the North Island
Project.
Exploration activities will also be reactivated in 2021 with an
initial drill program focusing on three main areas: Red Dog,
Pemberton Hills, and Hushamu. Program objectives include
increasing tonnage and grade for the North Island Project,
confirming the existence of a larger, higher grade copper-gold
porphyry system at Pemberton Hills, and exploring multiple targets
over our vast 33,000 ha property.
Our leadership team is fully committed to realizing our vision
of making Northisle Canada's leading sustainable resource
development company."
The Company will host a conference call and webcast on
Thursday, February 4, 2021 at
11:00 AM Eastern time (8:00 AM Pacific time). Details to access the call
can be found below.
2021 PEA Summary
The 2021 PEA was prepared in
accordance with National Instrument 43-101 ("NI43-101") by M3
Engineering & Technology Corp. ("M3") in conjunction with an
updated mine plan prepared by John
Nilsson, an updated Mine Waste Facility ("MWF") design
prepared by Golder Associates Ltd. (Golder) and updated
metallurgical testwork performance by SGS Canada Inc. ("SGS"). The
team was led by Cam Brown, P. Eng.
(Nova Scotia) on behalf of
Northisle. The Company plans to file the complete 2021 PEA report
on SEDAR at www.sedar.com within 45 days of this press
release. The 2021 PEA updates the previously published study on the
North Island Project, titled "North Island Copper and Gold Project,
NI43-101 Technical Report, Preliminary Economic Assessment" and
dated October 24, 2017 (the "2017
PEA"). Table 2 summarizes the key findings of the 2021
PEA.
Table 2: 2021 PEA
Economic Highlights
|
Base Case
Economics
|
Units
|
Pre-tax
|
After-tax
|
|
|
|
|
Net Present Value
(NPV 8%)
|
$ millions
|
1,494
|
1,059
|
Net Present Value
(NPV 8%)
|
US$
millions
|
1,121
|
795
|
Internal Rate of
Return
|
%
|
21.7%
|
19.0%
|
Payback
|
Years
|
3.9
|
3.9
|
Initial Capital
Cost
|
$ millions
|
1,442
|
Sustaining Capital
Cost
|
$ millions
|
197
|
|
|
|
|
Economic
Assumptions
|
Units
|
Base
Case
|
|
|
|
|
Copper
|
US$/lb
|
$3.25
|
Gold
|
US$/oz
|
$1,650
|
Molybdenum
|
US$/lb
|
$10.00
|
Rhenium
|
US$/kg
|
$1,256
|
CAD:USD Exchange
Rate
|
US$/C$
|
0.75
|
|
|
|
|
Financial
Metrics
|
Units
|
First 6
years
|
LOM
|
|
|
|
|
Average Annual
Revenue
|
$ millions
|
740
|
649
|
Average Annual
Operating Costs
|
$ millions
|
340
|
301
|
Avg. Ann. Free Cash
Flow (after tax)
|
$ millions
|
321
|
224
|
|
|
|
|
The 2021 PEA is preliminary in nature and includes inferred
mineral resources that are considered too speculative geologically
to have the economic considerations applied to them that would
enable them to be categorized as mineral reserves. There is
no certainty that the project described in the 2021 PEA will be
realized. Mineral resources that are not mineral reserves do
not have demonstrated economic viability.
Table 3 provides a summary of the key operating metrics
from the 2021 PEA.
Table 3: 2021 PEA
Operating Highlights
|
Operating
Statistics
|
Units
|
Avg. First 6
years
|
|
Avg.
LOM
|
|
|
|
|
|
Mine Life
|
Years
|
|
22
|
|
Tonnes
Processed
|
KT
|
27,060
|
|
27,289
|
Strip
Ratio
|
W:O
|
1.04
|
|
0.71
|
Production
|
|
|
|
|
Copper
|
mm lbs
|
112.1
|
|
95.9
|
Gold
|
koz
|
111.8
|
|
99.9
|
Molybdenum
|
klbs
|
2,726
|
|
2,954
|
Cu Eq.
|
mm lbs
|
177.5
|
|
155.9
|
Cash Cost – Cu with
by-products
|
$/lb
|
$0.75
|
|
$0.81
|
Cash Cost – Cu
Eq
|
$/lb
|
$2.00
|
|
$2.09
|
AISC – Cu with
by-products
|
$/lb
|
$0.77
|
|
$0.90
|
AISC – Cu
Eq
|
$/lb
|
$2.01
|
|
$2.14
|
By-products and Cu
Eq. calculated at Base Case metal prices
|
Economic Sensitivity
Table 4 summarizes the
after-tax sensitivities of NPV and IRR to metal prices.
Table 4: Economic
Sensitivity to Metal Prices
|
Metal
Prices
|
After- tax NPV
(5%)
$
millions
|
After-tax NPV
(8%)
$
millions
|
After-tax NPV
(10%)
$
millions
|
IRR
(%)
|
|
|
|
|
|
Spot
Prices1
|
$2,116.4
|
$1,396.1
|
$1,049.0
|
22.3%
|
Base Case +
20%
|
$2,682.7
|
$1,833.7
|
$1,425.0
|
26.5%
|
Base Case +
10%
|
$2,182.6
|
$1,447.2
|
$1,092.9
|
22.8%
|
Base Case
|
$1,682.5
|
$1,059.4
|
$759.1
|
19.0%
|
Base Case –
10%
|
$1,180.2
|
$666.8
|
$419.3
|
15.0%
|
Base Case –
20%
|
$674.1
|
$265.4
|
$68.9
|
10.8%
|
|
|
|
|
|
Note: Economic
assumptions are detailed in Table 14
|
1. Spot prices
as of February 2, 2021.
|
Sustainability
Northisle intends to integrate a
sustainable approach to mine development into every part of its
corporate culture. This means that monitoring, disclosing, and
improving on ESG performance is as critical as operating
metrics. As a result, Northisle has summarized preliminary
sustainability metrics for the North Island Project in Table
5 below.
Table 5:
Preliminary Sustainability Metrics
|
Sustainability
Statistics
|
Units
|
LOM Total /
Avg.
|
|
|
|
Direct local job
creation (permanent)
|
FTE
|
450
|
Site Energy
Consumption
|
|
|
Fuel
(annual)
|
000s
liters
|
21,000
|
Electricity
(annual)
|
MWh
|
794,000
|
Energy
Intensity
|
kWh/lb Cu
|
10.5
|
Environmental
|
|
|
Net water
consumption
|
liters / lb
Cu
|
99.6
|
GHG Emissions – Scope
1
|
kg CO2e / lb
Cu
|
0.66
|
Total Material to
MWF
|
MT
|
1,020
|
The above sustainability metrics were determined on a
preliminary basis by referencing publicly available benchmarks for
emissions related to key project energy sources. The selected
metrics will evolve as the project is developed, to incorporate
additional measures of ESG performance.
Opportunities
The PEA demonstrates the potential for
further development of the North Island Project and indicates a
number of additional opportunities for further study which may
contribute to further enhanced value, including:
- Evaluate the opportunity for sale of pyrite concentrate:
Preliminary study and test work indicates that a substantial
quantity of high-grade pyrite concentrate can be recovered.
Additional studies are required to determine the marketability of
pyrite concentrate.
- Consider use of historical Island Copper Pit for mine
tailings storage: The existing pit at the former BHP Island
Copper Operation could potentially be re-purposed to store most of
the tailings from the North Island Project development, which
represents an opportunity to reduce the risk profile for the
project.
- Trolley-assisted haulage: The current project uses
electrical power for the mining shovels and drills at Hushamu and
an opportunity exists to consider trolley-assisted haulage to
reduce emissions from the proposed diesel-electric fleet.
- Reduce carbon emissions: Northisle will conduct an
energy audit to evaluate available technologies and best practices
to drive the project development towards attaining carbon emission
reduction goals.
- Metallurgical optimization: Future test work will target
improved recoveries, refined reagent regimes, optimization of grind
versus recovery in both primary and regrind circuit to drive lower
energy and media consumption while maintaining mineral recovery
effectiveness.
- Engineering trade-off studies: Conduct engineering
trade-off studies to improve plant performance, reduce operating
and maintenance cost and enhance on-line availability as well as
opportunities to optimize plant throughput.
Next Steps
With the completion of the 2021 PEA,
Northisle intends to continue to advance the North Island Project.
Key next steps and milestones include:
- Commencement of planned 2021 drill program which will include
exploration drilling at Pemberton Hills, Red Dog and NW Expo, as
well as in fill and step-out drilling at Hushamu
- Additional extensive surface mapping and sampling of several
additional prospective porphyry targets (H2)
- Commencement of critical trade-off studies, environmental
baseline work and other long-lead items in support of determining
the scope of a pre-feasibility study in H2 2021.
- Northisle will continue to proactively engage with First
Nations, local communities, government and key project stakeholders
in support of the responsible development of the project.
Webcast Details
The Company will host a conference
call on Thursday, February 4, 2021 at
11:00 AM Eastern time (8:00 AM Pacific time). Details to access the call
live are as follows:
- Via telephone, toll free, by calling 1-416-764-8659 in
Toronto or internationally,
1-778-383-7413 in Vancouver and
1-888-664-6392 toll free in North
America
- Via webcast at: Webcast
The webcast will be archived for 365 days following the call at
the above-noted link and on the Company's website. The conference
call will also be available for replay until Thursday, February 11, 2021. To access the
replay, dial 1-416-764-7677 or 1-888-390-0541 and use Playback
Passcode 784988# to hear the recording.
2021 PEA Details
The 2021 represents an update of the
2017 PEA, with the primary changes including updated recoveries,
metal prices, operating and capital costs, and an updated mine
plan. The study was prepared independently by M3 and incorporates
results from independent metallurgical testing by SGS and MWF
design by Golder, and mine plan developed by John Nilsson. The Company now intends to
commence important work to prepare for initiation of a
pre-feasibility study, while accelerating the exploration program
throughout the property.
Mineral Resources
Mineral Resources for the Hushamu
deposit were updated for the purpose of the 2021 PEA by
incorporating 5 drill holes completed in 2017 which had not been
incorporated in earlier estimates. These drill holes had the
anticipated impact of converting several Inferred blocks into the
Indicated category. In addition, the cut-off grade for the resource
was revised to 0.10% which had the result of increasing tonnage in
both Indicated and Inferred Resources while reducing grade.
Table 6: Combined
Summary Resource Estimate
|
Category
|
Tonnes
|
%
Cu
|
g/t
Au
|
%
Mo
|
g/t
Re
|
|
|
|
|
|
|
Indicated
|
|
|
|
|
|
Hushamu
|
472,854,000
|
0.20%
|
0.23
|
0.008%
|
0.35
|
Red Dog
|
54,490,000
|
0.22%
|
0.31
|
0.004%
|
*
|
Total
Indicated
|
527,344,000
|
0.20%
|
0.24
|
0.008%
|
0.31
|
|
|
|
|
|
|
Inferred
|
|
|
|
|
|
Hushamu
|
414,293,000
|
0.15%
|
0.18
|
0.006%
|
0.29
|
Red Dog
|
2,979,000
|
0.17%
|
0.25
|
0.002%
|
*
|
Total
Inferred
|
417,272,000
|
0.15%
|
0.18
|
0.006%
|
0.29
|
Note: Resources shown
at a 0.10% Cu cut-off grade.
* Not assayed
|
A complete summary of mineral resources can be found at the end
of this release.
Mining
Preliminary mine designs have been developed
for Red Dog and Hushamu deposits based upon Indicated and Inferred
Resources. Resource models were imported to Minesight® mine
planning software where a Lerchs Grossman algorithm was applied to
an NSR model to determine possible pit limits.
The mine plan was developed to mine Red Dog concurrently with
Hushamu in the early years of the mine life until Red Dog Resources
were depleted. The assumed processing rate is 75,000 t/d; Red Dog
contributes 24,000 t/d while in operation. The overall mining rate
peaks at 64 million t/a in the initial years averaging 47 million
t/a over the total mine life of 22 years. The effective strip ratio
after stockpile reclaim was 0.71:1.
The mine is planned to be a conventional truck and shovel
operation with electrified pit operations at Hushamu. Waste rock
will be placed during construction and operation within the
MWF. A low-grade stockpile will be located at the pit rim on
the northwest side of Hushamu. An overburden stockpile will be
located adjacent to the low-grade stockpile for use in reclamation
of the MWF at the end of the mine life.
Table 7: Key
mining statistics
|
Metric
|
Units
|
Quantity
|
|
|
|
Mine life
|
Years
|
22
|
Milling
rate
|
t/d
|
75,000
|
Strip
Ratio
|
W:O
|
0.71
|
Total Tonnage
Mined
|
MT
|
1,032.3
|
Total Mineralized
Material Mined
|
MT
|
602.3
|
LOM Average
Grades
|
|
|
Copper
|
%
|
0.18%
|
Gold
|
g/t
|
0.24
|
Molybdenum
|
%
|
0.008%
|
|
|
|
The total resources processed in the conceptual mine plan are
shown in the following tables. The quantity of mineralized material
was estimated and included in the mine plan using an NSR threshold
approach, rather than a copper cut-off grade. The Hushamu Leached
Zone (denoted LEA in Table 15 and Table 16) is excluded from
the 2021 PEA mine plan. Tonnages in the mine plan are
summarized in Table 8 and Table 9 while mine operating
costs are summarized in Table 10.
Table 8: Indicated
Mineral Resources Included in the Mine Plan
|
Indicated
Resources
|
ROM t x
1000
|
Cu
(%)
|
Au
(g/t)
|
Mo
(%)
|
NSR
($/t)
|
|
|
|
|
|
|
Hushamu Starter
Pit
|
83,530
|
0.24
|
0.27
|
0.007
|
22.76
|
Hushamu Phase 1
Expansion
|
96273
|
0.20
|
0.19
|
0.007
|
17.68
|
Hushamu Phase 1.5
Expansion
|
126,312
|
0.18
|
0.27
|
0.011
|
18.33
|
Hushamu Phase 2
Expansion
|
115,483
|
0.17
|
0.25
|
0.008
|
17.77
|
Red Dog
|
50,885
|
0.22
|
0.32
|
0.005
|
24.82
|
Total
|
472,483
|
0.20
|
0.25
|
0.008
|
19.54
|
|
|
|
|
|
|
Table 9: Inferred
Mineral Resources Included in the Mine Plan
|
Inferred
Resources
|
ROM t x
1000
|
Cu
(%)
|
Au
(g/t)
|
Mo
(%)
|
NSR
($/t)
|
|
|
|
|
|
|
Hushamu Starter
Pit
|
2,973
|
0.12
|
0.15
|
0.016
|
11.40
|
Hushamu Phase 1
Expansion
|
13,068
|
0.13
|
0.13
|
0.010
|
11.64
|
Hushamu Phase 1.5
Expansion
|
35,037
|
0.14
|
0.23
|
0.012
|
15.00
|
Hushamu Phase 2
Expansion
|
76,598
|
0.14
|
0.20
|
0.007
|
14.44
|
Red Dog
|
2,172
|
0.17
|
0.27
|
0.003
|
19.91
|
Total
|
129,848
|
0.14
|
0.20
|
0.009
|
14.33
|
|
|
|
|
|
|
Table 10: Mining
Costs
|
Area
|
Unit Cost (C$/t
mined)
|
|
|
Drilling
|
0.13
|
Blasting
|
0.35
|
Loading
|
0.24
|
Hauling
|
0.69
|
Support
|
0.49
|
Mine
General
|
0.21
|
Total Mining Cost
excl. equipment lease
|
2.11
|
Mine equipment
lease
|
0.21
|
|
|
Note: totals may not
add due to rounding
|
Processing
The 2021 PEA contemplates a concentrator
and related facilities processing mineralized material at a nominal
rate of 75,000 t/d through a grinding circuit comprised of a
single SAG mill and two ball mills, flotation facilities and
regrind facilities to recover copper and molybdenum concentrates
for export. Gold reports primarily to the copper concentrate while
rhenium reports primarily to the molybdenum concentrate. Processing
costs are summarized in Table 11.
Table 11:
Processing Costs
|
Area
|
Unit Cost (C$/t
processed)
|
|
|
Salaries &
Wages
|
0.50
|
Power
|
1.84
|
Liners
|
0.36
|
Grinding
Media
|
1.03
|
Reagents
|
1.20
|
Maintenance Parts
& Repairs
|
0.48
|
Supplies &
Services
|
0.10
|
Total Processing
Cost
|
5.52
|
|
|
Metallurgy
Additional metallurgical test work was
undertaken in 2020 by SGS to target better recoveries of the
principal minerals. M3 reviewed and interpreted the test work and
incorporated the results into the process plant design criteria,
flowsheet development, and process equipment selection. The design
basis for the processing plant is 75,000 t/d or 27,375,000 t/a at
93% availability. Design mineral grades to the process plant are
estimated at 0.18% copper, 0.24 g/t gold and 0.008% molybdenum with
overall estimated recoveries of approximately 86.4% for copper,
46.8% for gold, and 59.5% for molybdenum.
Operating Cost Summary
A preliminary operating cost
estimate was prepared for the North Island Project based on a
75,000 t/d mine/mill operation. Total site operating costs are
summarized in Table 12.
Table 12: Total
Site Operating Costs
|
Area
|
Units
|
Cost
|
|
|
|
Mining
Cost1
|
$/tonne
processed
|
$3.84
|
Processing
|
$/tonne
processed
|
$5.52
|
G&A
|
$/tonne
processed
|
$0.38
|
Water
Treatment
|
$/tonne
processed
|
$0.06
|
Total Site
Operating Costs
|
$/tonne
processed
|
$9.81
|
|
|
|
1. Including
leased mining equipment
|
Capital Cost and Infrastructure Summary
The capital
cost estimate was developed by M3 using an EPCM project development
approach. Golder developed a conceptual design for the MWF and
provided estimated quantities of construction material required to
construct the facility. M3 then estimated the associated initial
and sustaining capital cost based on the quantities provided. The
mine plan and associated mine initial and sustaining capital was
prepared by John Nilsson using
current equipment prices and leasing terms & conditions
provided by the mine equipment procurement consultant retained by
Northisle. The process facilities and other related facilities were
designed and estimated by M3. The capital cost of these facilities
was developed using budgetary quotes obtained for major process and
infrastructure facility equipment requirements, and construction
labour rates obtained from a BC contractor experienced in the scope
and scale of the North Island Project. The 2021 PEA capital
cost estimate is summarized in Table 13 below.
Table 13: Capital
Cost Summary
|
Area
|
$
million
|
|
|
Mine1
|
17.8
|
Pre-production
|
130.9
|
Process
|
1,235.4
|
Owner's
Cost
|
57.9
|
Total
|
1,442.0
|
|
|
1. Mine
equipment is included primarily on a leased basis in the financial
model.
|
The nearby town of Port Hardy
is a main distribution centre for the north end of Vancouver
Island. It has an airport with regular flights to Vancouver, a hospital, schools, and a college.
The North Island Project is generally accessible for exploration
purposes from Port Hardy through a
network of logging roads.
BHP is in the process of reclaiming its historical marine load
out infrastructure from its past-producing Island Copper Mine. The
2021 PEA contemplates the construction of a new marine load-out
facility on the reclaimed site, which would be used to load
concentrate onto ocean-going vessels for shipment to smelters in
Asia. One of BC's largest wind
farm complexes is situated adjacent to the northwest end of the
property and the 138 KV power line connecting the wind farm to the
main BC power grid passes immediately north of the North Island
Project. The 2021 PEA contemplates connecting to the BC Hydro grid
via the existing main substation near the highway into Port Hardy.
Economic Analysis
Economic evaluations were generated
incorporating forecasts for economic inputs using the Base Case and
Spot Price. The spot price case is based on prices as of
February 2, 2021. See Table
14 for the results of the economic analysis.
Table 14: Economic
Analysis
|
Parameter
|
Unit
|
Base
Case
|
Spot
Price1
|
|
|
|
|
Copper
Price
|
US$/lb
|
$3.25
|
$3.51
|
Gold Price
|
US$/oz
|
$1,650.00
|
$1,835.60
|
Molybdenum
Price
|
US$/lb
|
$10.00
|
$10.03
|
Rhenium
Price
|
US$/kg
|
$1,256.00
|
$1,256.00
|
CAD:USD Exchange
rate
|
US$/C$
|
0.75
|
0.75
|
Average Annual
Revenue
|
$ million
|
$648.6
|
$704.9
|
Economic Result
(before tax)
|
|
|
|
Avg. Free Cash
Flow
|
$ million
|
$277.1
|
$321.2
|
NPV (5%)
|
$ million
|
$2,296.9
|
$2,871.8
|
NPV (8%)
|
$ million
|
$1,494.3
|
$1,937.3
|
NPV (10%)
|
$ million
|
$1,109.9
|
$1,489.6
|
IRR
|
%
|
21.7%
|
25.5%
|
Payback
|
Years
|
3.9
|
3.4
|
Economic Result
(after tax)
|
|
|
|
Avg. Free Cash
Flow
|
$ million
|
$223.6
|
$256.7
|
NPV (5%)
|
$ million
|
$1,682.5
|
$2,116.4
|
NPV (8%)
|
$ million
|
$1,059.4
|
$1,396.1
|
NPV (10%)
|
$ million
|
$759.1
|
$1,049.0
|
IRR
|
%
|
19.0%
|
22.3%
|
Payback
|
Years
|
3.9
|
3.5
|
|
|
|
|
The 2021 PEA is preliminary in nature and includes inferred
mineral resources that are considered too speculative geologically
to have the economic considerations applied to them that would
allow them to be categorized as mineral reserves and there is no
certainty that the preliminary economic assessment will be
realized. Mineral resources that are not mineral reserves do
not have demonstrated economic viability.
Technical Report and Qualified Persons
A National
Instrument 43-101 (NI 43-101) compliant technical report entitled
"North Island Project PEA" prepared by the following Qualified
Persons will be filed by the Company within 45 days of this release
on www.sedar.com:
- Laurie Tahija, MMSA – M3
Engineering – Recovery Methods and Process Operating Costs
- Daniel Roth, P.Eng. – M3
Engineering – Project Plant and Infrastructure Costs, Economic
Analysis
- Brian Game, P. Geo. – Principal
of GeoMinEx Consultants – Geology, Exploration and
Environmental
- Phil Burt, P. Geo. – CEO of Burt
Consulting Services – Mineral Resource Estimates
- John Nilsson, P. Eng. – Mining
Methods
- Ben Wickland, P.Eng. of Golder
Associates Ltd. – Mine Waste Facility
The Qualified Persons have reviewed and approved the scientific,
technical, and economic information obtained in this news
release.
About Northisle
Northisle Copper and Gold Inc. is a
Vancouver based company whose
mission is to become Canada's
leading sustainable mineral resource company for the future.
Northisle owns the North Island Project, which is one of the most
promising copper and gold porphyry deposits in Canada. The North Island Project is located
near Port Hardy, British Columbia
on a 33,149-hectare block of mineral titles 100% owned by Northisle
stretching 50 kilometres northwest from the now closed Island
Copper Mine operated by BHP Billiton. The Company recently
completed a preliminary economic assessment which demonstrated the
potential of the Red Dog and Hushamu deposits and is aggressively
advancing its exploration and development program in 2021.
For more information on Northisle please visit the
Company's website at www.northisle.ca.
On behalf of Northisle Copper and Gold Inc.
Nicholas Van Dyk, CFA
Vice President, Corporate Development and Investor Relations
Tel: (778) 655-9582
Email: info@northisle.ca
www.northisle.ca
This news release does not constitute an offer to sell or a
solicitation of an offer to buy any of the securities in
the United States. The securities
have not been and will not be registered under the United States
Securities Act of 1933, as amended (the "U.S. Securities Act") or
any state securities laws and may not be offered or sold within
the United States or to U.S.
Persons unless registered under the U.S. Securities Act and
applicable state securities laws or an exemption from such
registration is available.
Cautionary Statements regarding Forward-Looking
Information
Certain information in this news release
constitutes forward-looking statements under applicable securities
law. Any statements that are contained in this news release that
are not statements of historical fact may be deemed to be
forward-looking statements. Forward-looking statements are often
identified by terms such as "may", "should", "anticipate",
"expect", "intend" and similar expressions. Forward-looking
statements in this news release include, but are not limited to,
statements relating to the anticipated timing of the 2021 PEA,
anticipated 2021 PEA results, anticipated 2021 activities, the
Company's plans for advancement of the North Island Project,
including the potential use of existing infrastructure,
expectations regarding the 2021 drill program; the Company's plans
for engagement with Indigenous nations, communities and key
stakeholders, and the Company's anticipated exploration activities.
Forward-looking statements necessarily involve known and unknown
risks, including, without limitation, Northisle's ability to
implement its business strategies; risks associated with mineral
exploration and production; risks associated with general economic
conditions; adverse industry events; stakeholder engagement;
marketing and transportation costs; loss of markets; volatility of
commodity prices; inability to access sufficient capital from
internal and external sources, and/or inability to access
sufficient capital on favourable terms; industry and government
regulation; changes in legislation, income tax and regulatory
matters; competition; currency and interest rate fluctuations; and
other risks. Readers are cautioned that the foregoing list is not
exhaustive.
Readers are further cautioned not to place undue reliance on
forward-looking statements as there can be no assurance that the
plans, intentions or expectations upon which they are placed will
occur. Such information, although considered reasonable by
management at the time of preparation, may prove to be incorrect
and actual results may differ materially from those anticipated.
Forward-looking statements contained in this news release are
expressly qualified by this cautionary statement.
The forward-looking statements contained in this news release
represent the expectations of management of Northisle as of the
date of this news release, and, accordingly, are subject to change
after such date. Northisle does not undertake any obligation to
update or revise any forward-looking statements, whether as a
result of new information, future events or otherwise, except as
expressly required by applicable securities law.
Neither the TSX Venture Exchange nor its Regulation Services
Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or
accuracy of this news release.
Table 15: 2021
Hushamu Resource Estimate – Indicated Resource
|
Mineral
Domain
|
Tonnes
|
%
Cu
|
g/t
Au
|
%
Mo
|
g/t
Re
|
|
|
|
|
|
|
LEA
|
8,843,000
|
0.14
|
0.22
|
0.008
|
0.29
|
CMG-SCP-PRO
|
462,475,000
|
0.20
|
0.24
|
0.008
|
0.35
|
QFP
|
1,536,000
|
0.11
|
0.08
|
0.004
|
0.03
|
Total Indicated
Resource
|
472,854,000
|
0.20
|
0.23
|
0.008
|
0.35
|
|
|
|
|
|
|
1.
|
Tonnages have been
rounded to the nearest 1,000 tonnes so may not add up.
|
2.
|
Classification is
compliant with the "CIM Resource Definition Standards,
2014"
|
3.
|
It is assumed that
with continued exploration, most of the Inferred Resource could be
upgraded to an Indicated Resource category.
|
Note: Resources shown
at a 0.10% Cu cut-off grade.
|
Table 16: 2021
Hushamu Resource Estimate – Inferred Resource
|
Mineral
Domain
|
Tonnes
|
%
Cu
|
g/t
Au
|
%
Mo
|
g/t
Re
|
|
|
|
|
|
|
LEA
|
2,169,000
|
0.13
|
0.18
|
0.008
|
0.26
|
CMG-SCP-PRO
|
410,265,000
|
0.15
|
0.18
|
0.006
|
0.30
|
QFP
|
1,859,000
|
0.12
|
0.10
|
0.005
|
0.15
|
Total Inferred
Resources
|
414,293,000
|
0.15
|
0.18
|
0.006
|
0.29
|
|
|
|
|
|
|
1.
|
Tonnages have been
rounded to the nearest 1,000 tonnes so may not add up.
|
2.
|
Classification is
compliant with the "CIM Resource Definition Standards,
2014"
|
3.
|
It is assumed that
with continued Exploration, most of the Inferred Resource could be
upgraded to an Indicated Resource category.
|
Note: Resources shown
at a 0.10% Cu cut-off grade.
|
Table 17: 2017 Red
Dog Resource Summary
|
|
Tonnes
|
%
Cu
|
g/t
Au
|
%
Mo
|
|
|
|
|
|
Indicated
Resource
|
54,490,000
|
0.22
|
0.31
|
0.004
|
Inferred
Resource
|
2,979,000
|
0.17
|
0.25
|
0.002
|
Game, B. and
Burt, P. 2017
|
Note:
Resources shown at a 0.10% Cu cut-off grade.
|
View original content to download
multimedia:http://www.prnewswire.com/news-releases/northisle-announces-positive-pea-for-the-north-island-project-which-confirms-it-is-one-of-the-most-attractive-cu-au-projects-in-canada-301221887.html
SOURCE NorthIsle Copper and Gold Inc.