FEASIBILITY STUDY HIGHLIGHTS
- Large-Scale Nevada-based Lithium Project: three-phase
production plan will generate a life-of-mine average of 34,000
tonnes per annum (tpa) of battery-quality lithium carbonate
(Li2CO3)
- Innovative Approach in Processing: patent-pending
chloride leaching process combined with Direct Lithium Extraction
(DLE), the Feasibility Study is supported by 2+ years of testing at
the Company's Pilot Plant
- Mineral Resource Estimate: Measured and Indicated
resources totaling 1,207.33 million tonnes (Mt) at an average grade
of 957 parts per million (ppm) lithium (Li) containing
1.155 Mt of Li or 6.148 Mt of lithium carbonate equivalent (LCE)
- Long 40-Year Mine Life: Proven and Probable Mineral
Reserve Estimate totaling 287.65 Mt at an average grade of 1,149
ppm Li containing 0.330 Mt of lithium
or 1.759 Mt of LCE
- Initial Project: Phase 1 Capital Cost $1.537 billion for production capacity of 13,000
tpa LCE
- Designed for Expansion: Phase 2 $0.651 billion for 28,000 tpa LCE, and Phase 3
$1.336 billion for 41,000 tpa LCE;
Project expansions are capitalized with Project cash flow
- Low Operating Cost: average operating cost $8,223/t of Li2CO3
produced, or $2,766/t after sales of
surplus sodium hydroxide (NaOH)
- After-tax IRR of 17.1% at $24,000/t Li2CO3:
$3.01 billion after-tax net present
value (NPV) at 8% discount rate and a 17.1% after-tax internal rate
of return (IRR), using price assumptions of $24,000/t for Li2CO3 and
$600/dry metric tonne (dmt) for
NaOH
VANCOUVER, BC, April 29,
2024 /CNW/ - Century Lithium Corp.
(TSXV: LCE) (OTCQX: CYDVF) (Frankfurt: C1Z)
(Century Lithium or the Company) is pleased to announce the results
of a National Instrument 43-101 (NI 43-101) feasibility study
(Feasibility Study, FS or Study) completed on its 100% owned
Clayton Valley Lithium Project (Project) in Nevada, USA. The Feasibility Study was
prepared by Wood Group USA, Inc.
(Wood) and Global Resource Engineering, Ltd. (GRE). All currency
amounts in this news release are presented in U.S. dollars.
"Century Lithium is proud to present our Feasibility Study. The
Study indicates our Project has robust economics, made possible
with our unique chlor-alkali and DLE processes" commented
Bill Willoughby, President, and CEO.
"Completion of the Study marks a major milestone for the Company
and is the result of the dedicated work and efforts of our team of
employees and consultants."
"Our process technology was developed by way of many trials and
successes at our Pilot Plant in Amargosa
Valley. As one of the few lithium-focused Pilot Plants in
North America, we continue to
operate safely and recently passed two years of testing. The data
generated to date supports the Feasibility Study, and we continue
to test various conditions and ideas to improve our process flow
sheet," said Bill Willoughby.
With the Feasibility Study completed, the Company will now
direct its focus on engineering and permitting. The Company is
concurrently advancing discussions with government agencies,
strategic partners, and other interested parties to provide funding
to advance the Project and maximize the value to the Company's
shareholders that is reflected in the FS.
FEASIBILITY STUDY SUMMARY
The information in the following tables highlight the Project's
production and economic summaries.
Production
Summary
|
Phase
|
Years
|
Mine tonnes per day
(tpd)
|
Li2CO3 (tpa)
|
Capital Cost
(B$)
|
1
|
1-5
|
7,500
|
13,000
|
$1.537
|
2
|
6-10
|
15,000
|
28,000
|
$0.651
|
3
|
11+
|
22,500
|
41,000
|
$1.336
|
Economic
Summary
|
Units
|
Amount
|
Operating Costs
(average)
|
$/t
|
8,223
|
Operating Costs
(average w/NaOH credit)
|
$/t
|
2,766
|
After-tax NPV @ 8%
Discount Rate
|
$ billion
|
3.01
|
After-tax
IRR
|
%
|
17.1
|
RESOURCE AND RESERVES
The Mineral Resource and Reserve Estimates for the Project were
updated for the Feasibility Study and built using geologic data and
1,318 lithium assays from 45 core holes drilled between 2017 and
2022. The constrained Measured and Indicated Resource Estimate is
1,207.33 Mt with an average grade of 957 ppm lithium and contains
1.155 Mt of Li or 6.148 Mt of LCE. The Proven and Probable Mineral
Reserve Estimate was derived from the constrained Mineral Resources
and contains 287.65 Mt with an average grade of 1,149 ppm lithium
and contains 0.330 Mt of Li or
1.759 Mt of LCE and reflects an
increase of 74.6 Mt and 0.48 Mt LCE compared to the 2021 Mineral
Reserve Estimate. The Mineral Resources were generated with a pit
shell that encompasses all mineralized material within the Property
excluding all areas that will be used for Project infrastructure
and placement of tailings, waste, and low-grade material.
Mineral Resource
Estimate
|
Domain
|
Tonnes
Above
Cut-off
(millions)
|
Li Grade
(ppm)
|
Li
Contained
(million
t)
|
LCE (million
t)
|
Measured
|
858.38
|
990
|
0.849
|
4.524
|
Indicated
|
348.95
|
875
|
0.305
|
1.625
|
Measured &
Indicated
|
1,207.33
|
957
|
1.155
|
6.148
|
Inferred
|
119.03
|
827
|
0.098
|
0.524
|
The effective date of
the Mineral Resource Estimate is December 15, 2022. The QP for the
estimate is Ms. Terre Lane, MMSA, an
employee of GRE and independent of Century. The Mineral Resources
are constrained by a pit shell with a 200 ppm Li cut-off and
density of 1.505 g/cm3. The cut-off grade considers an operating
cost of $16.90/t mill feed, process recovery of 83% and a long-term
lithium carbonate price of $20,000/t. The Mineral Resource estimate
was prepared in accordance with CIM Definition Standards (CIM,
2014) and the CIM Estimation of Mineral Resources and Mineral
Reserves Best Practice Guidelines (CIM, 2019). Mineral Resource
figures were rounded. One tonne
of lithium = 5.323 tonnes lithium carbonate. Mineral Resources are
inclusive of Mineral Reserves.
|
Mineral Reserve
Estimate
|
Domain
|
Tonnes Above
Cut-
off
(millions)
|
Li Grade
(ppm)
|
Li
Contained
(million
t)
|
LCE (million
t)
|
Proven
|
266.39
|
1,147
|
0.306
|
1.626
|
Probable
|
21.26
|
1,174
|
0.025
|
0.133
|
Proven &
Probable
|
287.65
|
1,149
|
0.330
|
1.759
|
The effective date of
the Mineral Reserve Estimate is December 15, 2022. The QP for the
estimate is Ms. Terre Lane, MMSA, an employee of GRE and
independent of Century. The Mineral Reserve estimate was prepared
in accordance with CIM) Definition Standards (CIM, 2014) and the
CIM Estimation of Mineral Resources and Mineral Reserves Best
Practice Guidelines (CIM, 2019). Mineral Reserves are reported
within the final pit design at a mining cut-off of 900 ppm. The
cut-off grade considers a mine operating cost of $1.98/t, a process
operating cost of $14.27/t milled, a G&A cost of $0.65/t
milled, process recovery of 83% and a long-term lithium carbonate
price of $20,000/t. The cut-off of 900 ppm is an elevated cut-off
selected for the mine production schedule as the elevated cutoff is
4.5 times higher than the break-even cut-off grade. Mineral Reserve
figures have been rounded. One tonne of lithium = 5.323 tonnes
lithium carbonate. Mineral Resources are inclusive of Mineral
Reserves.
|
PROCESS METALLURGY &
CHLOR-ALKALI PLANT
Metallurgical testing through 2020 focused on using sulfuric
acid (H2SO4) to extract lithium from the
clay. In late 2020, testing shifted to hydrochloric acid (HCl) for
its improved compatibility with the deposit's chemistry. These
benefits included higher lithium extractions, lower reagent
consumptions, significantly better filtration of solids, and the
ability to utilize certain DLE technologies in the recovery and
concentration of lithium from the leach solutions.
A key component of the Project with chloride-based leaching is a
chlor-alkali plant. The chlor-alkali plant provides the ability to
produce the key reagents HCl and NaOH on-site from the electrolysis
of a sodium chloride (NaCl) solution. A chlor-alkali plant
represents a greater capital investment relative to that of a
sulfuric acid plant but has important environmental and economic
benefits for the sustainability of the Project. These benefits
include replacing the purchase and transportation of sulfur with
regionally sourced salt, and a reduction in emissions and the
physical footprint of the operation with dryer, non-sulfate
tailings.
Additionally, the chlor-alkali plant will generate significant
quantities of NaOH surplus to the Project's operational needs and
therefore available for sale. The chlor-alkali plant will utilize
modern electrochemical cell technology thereby producing membrane
grade sodium hydroxide without the energy consumption and
environmental problems of older technologies. The surplus amounts
of NaOH are inherent to the operation of the plant and the sales
represent a significant offset to the Project's operating
costs.
PILOT PLANT
In 2021, Century Lithium constructed a Pilot Plant in
Nevada to leach one tonne per day
of lithium clay and produce a high-grade lithium chloride solution
which is processed off-site at Saltworks Technologies, Inc.
(Saltworks), at their Richmond, British
Columbia processing plant to make battery-quality
Li2CO3. To maximize lithium recovery, the
Company purchased the license rights and pilot-stage equipment to
DLE an ion-exchange-based process and incorporated it into the
Pilot Plant. The DLE license is held in perpetuity and royalty free
by the Project.
Throughout its Pilot Plant program, the Company has sought
improvement in its process methods. The Company obtained a
provisional patent in 2023 with the U.S. Patent and Trademark
Office, U.S. Department of Commerce. The provisional patent is
titled System and Method for Extracting Lithium from Clay and
Other Materials in a Chloride Solution Using Individualized
Pretreatments. The patent pending process encompasses the
Company's flowsheet and protects its methods of leaching
lithium-bearing solids and handling solutions, precipitates, and
residues.
LITHIUM EXTRACTION, RECOVERY &
Li2CO3 PRODUCTION
A lithium recovery of 78% is used in the Feasibility Study,
based on the data collected in over two years of operations at the
Pilot Pant.
- Feed material grades averaged 1,100 ppm
- Leach solution samples varied from 200 to 320 ppm Li
- Lithium extractions averaged 88% and varied from 80 to 95%
- DLE lithium recoveries were typically above 90%
- 10% of the lithium in solution is retained in the moisture
remaining in the tailings
Extraction rates do not account for losses downstream and are
only indicative of the potential overall recovery. Work at the
Pilot Plant continues to focus on reducing losses of lithium to
tailings. A small loss of lithium from processing the DLE product
solutions into Li2CO3, and the recycling of
process solutions to the DLE and leach areas is anticipated.
During 2022 and 2023, Saltworks processed the DLE product
solutions from the Pilot Plant and made battery-quality
Li2CO3 at greater than 99.5% purity.
Modifications at the Pilot Plant in mid-2023 increased lithium
solution grades to over 14 grams per liter which simplified the
flowsheet and eliminated the evaporation stage for production of
Li2CO3.
PRODUCTION PLAN
The Project's production plan comprises three equal phases of
production rate increases, Phase 1 and Phase 2 production rates are
maintained over five years each and Phase 3 is maintained for 30
years. This approach was selected to reduce capital exposure and
risk by dividing the Project's production schedule into realistic
phases of construction and equipment installation. The plan fully
utilizes the Project's Mineral Reserve.
Phase 1 includes all work required to implement the Initial
Project Plan including all necessary mining and processing
infrastructure. The Phase 2 cost estimate focuses on an expansion
within the footprint of Phase 1. Phase 3 development includes an
additional processing plant and facilities not built in the
previous phases and allows for a fourth phase of expansion.
LITHIUM CARBONATE AND SODIUM
HYDROXIDE SALES PRICES
A price of $24,000/t of
Li2CO3 is used in the Feasibility Study as
the Project base case. This price is selected as a conservative
mid-point between current market prices which are under
$20,000/t
Li2CO3 and forecast prices obtained from
Benchmark Mineral Intelligence which are in the range of
$23,000 to $39,000/t Li2CO3 during
Phase 1 and $29,000 to $31,000/t Li2CO3 thereafter
(Benchmark Mineral Intelligence, Lithium Forecast Q1 2024). The
sales price is free on board (FOB) the Project site for battery
quality Li2CO3.
NaOH is a product of the chlor-alkali process and a sales price
of $600/dmt FOB the Project is used
in the Feasibility Study as the Project base case. Based on the
material mass balance, it is expected that surplus NaOH will be
available for sale at rates of 120,000 to 360,000 dmt per annum,
depending on Project Phase. This price is based on a February 2023 market study by Global Exchange and
Trading, Inc. where it was determined the Project's surplus NaOH
can be readily sold in the western U.S. which currently relies
heavily on imports arriving at west coast ports.
CAPITAL COST ESTIMATE
The basis for the capital cost estimate follows AACE Class 3 for
feasibility studies. Contributors to the estimates are GRE
(mining), Wood (process plant and infrastructure), ThyssenKrupp
Nucera (chlor-alkali plant) and Century Lithium (property
information and owners' costs). The capital cost estimates by phase
are summarized as follows.
Installed Capital
Costs
|
Initial
Phase 1
($M)
|
Expansion
Phase 2
($M)
|
Expansion
Phase 3
($M)
|
Mining & Site
Preparation
|
$64
|
$7
|
$27
|
Process
Facilities
|
$517
|
$205
|
$477
|
Chlor-Alkali
Plant
|
$496
|
$336
|
$496
|
Buildings, Services
& Infrastructure
|
$130
|
$5
|
$42
|
Indirect & Owners
Costs
|
$234
|
$72
|
$190
|
Contingency
|
$96
|
$27
|
$105
|
Total Capital
Cost
|
$1,537
|
$651
|
$1,336
|
Notes: Totals may not
sum due to rounding, Contingency and site Indirects for
chlor-alkali plant is included in the Chlor-Alkali Plant line
item, contingency for mining is included in the Contingency
line item, indirect costs for mining are not included in the
Indirects and Owner's Costs line item
|
The Phase 2 capital costs represent the expansion of the process
facilities and infrastructure established in Phase 1. The Phase 3
capital costs support an additional processing plant and facilities
not built in the previous phases. In the Project schedule, a 2-year
period is allocated for the time to construct and commission each
phase.
Sustaining capital over the life of the Project is estimated at
$315 million for tailings facility
expansion and equipment replacements. These costs are in addition
to the expansion capital costs shown above.
OPERATING COST ESTIMATES
The following information highlights the operating cost
estimates for each phase in dollars per tonne of
Li2CO3, before and after deducting sales of
surplus NaOH.
Initial Phase
1
(7,500 tpd mill
feed)
|
$
(000s)/y
|
$/t mill
feed
|
$/t
LCE
|
Mining
|
$13,754
|
$5.43
|
$1,205
|
Processing and
G&A
|
$57,515
|
$21.01
|
$4,428
|
Chlor-Alkali
Plant
|
$61,787
|
$22.57
|
$4,757
|
Total Operating
Cost
|
$133,056
|
$49.01
|
$10,390
|
Less NaOH Sales (FOB
mine)
|
$78,272
|
$28.95
|
$6,026
|
Net Operating
Cost
|
$54,784
|
$20.06
|
$4,364
|
Note: Totals may not
sum due to rounding
|
Expansion Phase
2
(15,000 tpd mill
feed)
|
$
(000s)/y
|
$/t mill
feed
|
$/t
LCE
|
Mining
|
$24,901
|
$4.26
|
$766
|
Processing and
G&A
|
$82,018
|
$14.98
|
$3,157
|
Chlor-Alkali
Plant
|
$105,138
|
$19.20
|
$4,047
|
Total Operating
Cost
|
$212,057
|
$38.44
|
$7,970
|
Less NaOH Sales (FOB
mine)
|
$142,350
|
$26.00
|
$5,479
|
Net Operating
Cost
|
$69,707
|
$12.44
|
$2,491
|
Note: Totals may not
sum due to rounding
|
Expansion Phase
3
(22,500 tpd mill
feed)
|
$
(000s)/y
|
$/t mill
feed
|
$/t
LCE
|
Mining
|
$22,064
|
$2.70
|
$561
|
Processing and
G&A
|
$119,945
|
$14.60
|
$3,078
|
Chlor-Alkali
Plant
|
$151,325
|
$18.43
|
$3,884
|
Total Operating
Cost
|
$293,334
|
$35.73
|
$7,523
|
Less NaOH Sales (FOB
mine)
|
$213,525
|
$25.99
|
$5,479
|
Net Operating
Cost
|
$79,809
|
$9.74
|
$2,044
|
Note: Totals may not
sum due to rounding
|
ECONOMIC MODEL AND SENSITIVITY
The cash flow model is developed using base prices of
$24,000/t for
Li2CO3 and $600/dmt for NaOH.
Average Annual
Values
|
Units
|
Initial
Phase
1
|
Expansion
Phase
2
|
Expansion
Phase
3
|
Li2CO3 Sales
|
t
|
11,885
|
26,753
|
39,098
|
NaOH
Sales
|
dmt
|
130,488
|
237,250
|
355,875
|
Gross
Sales
|
$ million
|
$282.4
|
$635.7
|
$929.0
|
Before-tax Cash
Flow
|
$ million
|
$231.3
|
$553.3
|
$825.3
|
Lithium carbonate sales are the average over each Phase
including ramp up to the stated production rate. Gross sales
are revenues from Li2CO3 and NaOH sales are
before operating costs and after royalty. Before-tax Cash Flow is
gross sales minus operating costs. Taxes are applied at federal,
state and county rates after allowances for amortization,
depletion, and depreciation only. Possible tax credits under the
U.S. Inflation Reduction Act or other programs are not
included.
The Project base case generates a 17.1% after-tax IRR and NPV-8%
of $3.01 billion. These results are
sensitive to changes in operating assumptions including the sales
price of Li2CO3.
- At 75% of the base case, or $18,000/t LCE, the after-tax NPV@ 8% is
$1.52 billion, and the after-tax IRR
is 12.9%.
- At 125% of the base case, or $30,000/t LCE, the after-tax NPV@ 8% is
$4.47 billion, and the after-tax IRR
is 20.9%.
- For every $1,000/t change in the
price of lithium carbonate, the after-tax NPV@8% changes by about
$250 million.
Project
Sensitivity
|
Units
|
75 %
|
Base
Case
|
125 %
|
Lithium
Price
|
$/t LCE
|
$18,000
|
$24,000
|
$30,000
|
NPV-8%
|
$ billion
|
$1.52
|
$3.01
|
$4.47
|
IRR
|
%
|
12.9
|
17.1
|
20.9
|
PROJECT ADVANCEMENT
The Company has completed multiple environmental studies in
advance of permitting and is examining ways to optimize power
requirements and incorporate alternative energy solutions.
The recommendations of the FS include continuing the permitting
process, engaging with governmental agencies and other parties, and
proceeding with detailed engineering to further advance the
Project.
Among these steps, the Company has contacted the U.S. Department
of Energy's (DOE) Loan Programs Office (LPO) and plans to initiate
the pre-application process under the Title Seven Clean Energy
Financing program when the Feasibility Study report is
complete.
CONFERENCE CALL
Century Lithium will host a live webcast and conference call for
analysts and investors on Monday, April 29,
2024, at 11:00 am ET
(8:00 am PT), followed by a
question-and-answer session.
To register for the webcast, link here:
https://events.6ix.com/preview/century-lithium-announces-positive-feasibility-study
A replay of the webcast will be available on our website shortly
following the conclusion of the conference call.
QUALITY ASSURANCE
The data in this news release was prepared in accordance with NI
43-101 standards by the following Qualified Persons (QP).
- Terre Lane, Principal Mining
Engineer, GRE, is an independent QP as defined by NI 43-101 and has
reviewed and approved the contents of this news release and
verified by site visits and personal examination the information
and original documents that relate to preparation of the Mineral
Resource Estimate, Mineral Reserve Estimate, mine plan, mine
capital and operating cost estimation, economic analysis, and
marketing.
- Hamid Samari, Principal
Geologist, GRE, is an independent QP as defined by NI43-101 and has
reviewed and approved the contents of this news release and
verified by site visits and personal examination the information
and original documents that relate to preparation of the
description of the deposit, geological setting, and mineralization,
deposit type, exploration, drilling, sample preparation, analyses
and security, and data verification.
- Todd Fayram, Senior Vice
President Metallurgy, Century Lithium, is a non-independent QP as
defined by NI 43-101 and has reviewed and approved the contents of
this news release and verified by site visits and personal
examination the information and original documents that relate to
preparation of the description of metallurgical testing, lithium
recovery, and design operation and results of the Pilot Plant.
- Alan Drake, Manager – Process
Engineering, Wood, is an independent QP as defined by NI 43-101 and
has reviewed and approved the contents of this news release and
verified by site visits and personal examination the information
and original documents that relate to preparation of the
description and estimates related to recovery methods.
- Haiming (Peter) Yuan, PE, PhD, Principal Geotechnical Engineer,
WSP USA Environment &
Infrastructure Inc., is an independent QP as defined by NI 43-101
and has reviewed and approved the contents of this news release and
verified by site visits and personal examination the information
and original documents that relate to preparation of the
description related to infrastructure, environment and
permitting.
- Paul Baluch, Technical Director,
Civil, Wood, is an independent QP as defined by NI 43-101 and has
reviewed and approved the contents of this news release and
verified by personal examination the information and original
documents that relate to preparation of the description and
estimates of infrastructure.
- Farzad Kossari, Cost Estimating
Manager, Wood, is an independent QP as defined by NI 43-101 and has
reviewed and approved the contents of this news release and
verified by personal examination the information and original
documents that relate to preparation of the description and summary
of capital and operating cost estimates.
Further information about the Project, including a description
of the key assumptions, parameters, description of sampling
methods, data verification and quality assurance (QA) / quality
control (QC) programs, methods relating to Mineral Resources and
Mineral Reserves and factors that may affect those estimates will
be contained in a NI 43-101 Technical Report on the Feasibility
Study of the Clayton Valley Lithium Project. Following Section 3.4
of NI 43-101 the report will be available on SEDAR+ and on the
Company's website within 45 days of the date of this news
release.
ABOUT CENTURY LITHIUM CORP.
Century Lithium Corp. is
an advanced stage lithium company, focused on developing its
100%-owned Clayton Valley Lithium Project in west-central
Nevada, USA. Century Lithium
recently completed a Feasibility Study on its Clayton Valley
Lithium Project and is currently in the permitting stage, with the
goal of becoming a domestic producer of lithium for the growing
electric vehicle and battery storage market.
ON BEHALF OF CENTURY LITHIUM CORP.
WILLIAM WILLOUGHBY, PhD., PE
President & Chief Executive Officer
centurylithium.com
NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES
PROVIDER ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THE
CONTENT OF THIS NEWS RELEASE.
Cautionary Note Regarding
Forward-Looking Statements
This release contains certain forward-looking statements
within the meaning of applicable Canadian securities legislation.
In certain cases, forward-looking statements can be identified by
the use of words such as "plans", "expects" or "does not
anticipate", or "believes", or variations of such words and phrases
or statements that certain actions, events or results "may",
"could", "would", "might" or "will be taken", "occur" or "be
achieved" and similar expressions suggesting future outcomes or
statements regarding an outlook.
Forward-looking statements relate to any matters that are not
historical facts and statements of our beliefs, intentions and
expectations about developments, results and events which will or
may occur in the future, without limitation, statements with
respect to the potential development and value of the Project and
benefits associated therewith, statements with respect to the
expected project economics for the Project, such as estimates of
life of mine, lithium prices, production and recoveries, capital
and operating costs, IRR, NPV and cash flows, any projections
outlined in the Feasibility Study in respect of the Project, the
permitting status of the Project and the Company's future
development plans.
These and other forward-looking statements and information
are subject to various known and unknown risks and uncertainties,
many of which are beyond the ability of the Company to control or
predict, that may cause their actual results, performance or
achievements to be materially different from those expressed or
implied thereby, and are developed based on assumptions about such
risks, uncertainties and other factors set out herein. These
risks include those described under the heading "Risk Factors" in
the Company's most recent annual information form and its other
public filings, copies of which can be under the Company's profile
at www.sedarplus.com. The Company expressly disclaims any
obligation to update-forward-looking information except as required
by applicable law. No forward-looking statement can be guaranteed
and actual future results may vary materially. Accordingly, readers
are advised not to place reliance on forward-looking statements or
information. Furthermore, Mineral Resources that are not Mineral
Reserves do not have demonstrated economic viability.
View original content to download
multimedia:https://www.prnewswire.com/news-releases/century-lithium-announces-positive-feasibility-study-for-the-clayton-valley-lithium-project-nevada-302129324.html
SOURCE Century Lithium Corp.