KBR to Execute Equipment Installation at One of the Nation’s Largest Power Generating Stations
August 15 2011 - 4:05PM
Business Wire
KBR (NYSE: KBR) today announced that it has been awarded a
contract by Southern Company for the installation of flue gas
desulfurization (FGD) and selective catalytic reduction (SCR)
equipment, related ductwork, and auxiliaries at two 880,000
kilowatt coal-fired units at Georgia Power’s Plant Scherer. Plant
Scherer is a 3,520,000-kilowatt coal-fired facility located near
Macon, Ga. and is one of the largest single generating stations in
the nation.
KBR will provide installation of all equipment and associated
piping, steel, ductwork, electrical, instrumentation and related
work. KBR will also be responsible for the procurement of piping
and valves; receive all equipment and materials at the site; and
provide storage, rigging, assembly of modules, lifting, placing,
connecting and other services as necessary. The contract award
follows the completion of various projects for Southern Company by
KBR, most recently the Heavy Structural Steel construction project
at Plant Scherer.
“This project continues a successful relationship with Southern
Company and expands KBR’s presence in the U.S. domestic power
industry,” said Danny Hicks, Senior Vice President, KBR
Construction. “KBR has assembled a highly-experienced project team
with intimate knowledge of Plant Scherer. Additionally, we have
developed an innovative execution plan that will enable us to
provide the quickest, most efficient execution of the project,
while employing the highest standard of safety and quality
processes.”
KBR is a global engineering, construction and services company
supporting the energy, hydrocarbon, government services, minerals,
civil infrastructure, power, industrial, and commercial markets.
For more information, visit www.kbr.com.