TSXV: ARTG
Project Remains Fully Funded, Within Guidance
for Initial Capital Expenditure, and on Schedule
VANCOUVER, BC, Jan. 30,
2024 /CNW/ - Artemis Gold Inc. (TSXV: ARTG) ("Artemis
Gold" or the "Company") provides an update on Q4 construction
progress at the Blackwater Mine in central British Columbia. The project remains fully
funded, within the guidance for initial capital expenditure, and on
schedule for first gold pour in H2 2024.
At December 31, 2023, overall
construction was 59% complete, and approximately C$389 million of the guided initial capital
expenditure of C$730 to C$750 million had been spent. The lag between the
spend and percentage of completion is as planned and consistent
with a typical project S-curve. By the end of Q4 2023, the Company
had entered into contractual commitments for C$615 million (or 84% of the lower end of the
guided initial capital expenditure). The majority of the balance of
uncommitted expenditures for the guided initial capital relate to
owners cost and earthworks associated with mining pre-strip and
construction of the tailings storage facility ("TSF") and other
civil structures.
Artemis Gold Chairman and CEO Steven
Dean commented: "We remain focused on a disciplined approach
to development and remain on track for the first gold pour in H2
2024."
Construction Update
Earthworks continued in priority infrastructure areas, with
approximately 640 hectares logged and cleared. All access roads
needed for Phase 1 construction are now operable. Construction of
the site water management facilities, including the water
management pond, and Davidson Creek
diversion, is well advanced. Work associated with the transmission
line is progressing in accordance with the project schedule.
Total major works hours worked up to December 31, 2023, surpassed 1.1 million hours
with a zero LTIFR1 and an AIFR2 of 91.86.
Plant Site
Process plant construction progressed well on a number of
fronts, including the mill building foundation preparation,
reagents building foundations, ball mill pedestals, carbon in leach
("CIL") and detox tank erection, advancement of the primary,
secondary, and tertiary crushers structures, and the reclaim tunnel
civil works. Hydro testing within the CIL tank area commenced.
Construction of the run-of-mine ("ROM") wall and the initial ROM
dump slab earthworks have been completed. The focus has now moved
to concrete formwork to allow for the installation of the primary
crusher ROM slab and crusher vault. Steel structures for the
secondary and tertiary crusher and screening station have been
advanced and installation of the crushing mechanical packages
commenced in Q4. The erection of the mill building and installation
of the ball mill also commenced in late Q4.
Heavy Equipment
The construction fleet now includes 60 and 100 tonne rigid frame
haul trucks and 150 tonne excavators, providing more material
movement capability to key areas. Assembly and commissioning of the
owner's mining fleet is well advanced, including two 400 tonne
hydraulic backhoe excavators. Five 240 tonne rigid frame haul
trucks have been delivered to site, four of which have been
substantially assembled. The remainder of the fleet to support
operations will arrive predominately across the first half of
2024. Fleet assembly is expected to be completed well before
the commencement of pre-stripping, and equipment will be made
available to support earthworks if needed.
Engineering and
Procurement
At the end of December 2023, the
Sedgman EPC contract work was 75% complete overall, with
engineering, design and procurement substantially complete. Key
mechanical equipment packages, including the primary, secondary and
tertiary crushers, conveyor assemblies, dry screens, and ball
mill are all on site and are in various stages of
installation. The electrical machinery control centres are
also in various stages of delivery and installation.
Key mining-related contracts have been executed with detailed
mobilization plans for production drilling services well advanced.
In addition, equipment supply contracts have been awarded for the
oxygen plant and water treatment plant. Q4 also marked the arrival
onsite of the first delivery of the 225kV transmission line
conductor and poles.
Personnel
The Company's staffing numbers surpassed 320 employees in Q4
2023, with approximately 20% of the team female and over 30%
identifying as Indigenous. Approximately 50% of the development
team is from the local region and over 80% are B.C. residents. The
total workforce at the Blackwater Mine, including staff and
contractors, surpassed 550 towards the end of December.
Funding
At December 31, 2023, Artemis Gold
had estimated remaining Phase 1 capital expenditures of
C$341 to C$361
million. At the same date, the committed sources of funding
totalled C$432 million,
comprising:
- cash and cash equivalents of C$157 million;
- remaining drawdowns from the project loan facility of
C$235 million (including up to
C$25 million of capitalized
interest), and
- a cost overrun facility of C$40 million.
In addition, the Company had 26.2 million warrants outstanding
which are exercisable at C$1.08 per warrant before
August 27, 2024, for anticipated
proceeds of C$28 million.
Hedging
Artemis Gold has put in place a modest hedging program to secure
the returns on capital invested in the early years of operations
and further de-risk servicing of the Company's project loan
facility during the pay-back period. To date, the Company has
entered into forward sales agreements to deliver 190,000 ounces of
gold between March 2025 and
December 2027 at a weighted average
sales price of C$2,851 per ounce,
which is more than 40% higher than the gold price assumption in the
September 2021 Feasibility Study.
During Q4 2023, the Company also executed zero cost collars
associated with 30,000 ounces of gold with settlement dates from
December 2024 to February 2025. The collars have a weighted
average put price of C$2,600 per
ounce and a weighted average call price of C$3,353 per ounce.
Expansion Study
With Phase 1 fully funded and 59% complete at the end of
December 2023, a study to evaluate
the benefits of advancing the Phase 2 expansion earlier than
contemplated in the September 2021
Feasibility Study is progressing well. The results of this
expansion study are expected to be released later in
Q1 2024.
Artemis Gold President and COO Jeremy
Langford commented: "The fourth quarter was highlighted by
our workforce eclipsing one million hours worked without an LTI –
an important achievement that reflects the hard work and commitment
of our dedicated workforce. As we enter Q1 2024, our short-term
priorities will be to further progress the TSF infrastructure
areas, advance the construction of the 225Kv transmission line and
complete all essential concrete works within the process facility.
In parallel with this the teams will look to progress the
structural, mechanical, platework, piping and electrical
construction activities within the process plant and electrical
substation areas. Operations team members are scheduled to commence
pre-production planning, which will prepare the teams for initial
mining operations and plant commissioning."
Video
Watch here for a Q4 project update
video: https://youtu.be/LIKtgXHlOJs
Artemis Gold
Artemis Gold is a well-financed, growth-oriented gold
development company with a strong financial capacity aimed at
creating shareholder value through the identification, acquisition,
and development of gold properties in mining-friendly
jurisdictions. The company's current focus is the construction of
the Blackwater Mine project in central British Columbia approximately 160km southwest
of Prince George and 450km
northeast of Vancouver. The
project is one of the largest capital investments in the
Bulkley-Nechako, Fraser-Fort George
and Cariboo regions of B.C. in the last decade. The first pour of
gold and silver from Blackwater Mine is expected in H2 2024 and the
mine is expected to be in production for a minimum of 22 years.
Artemis Gold trades on the TSX-V under the symbol ARTG. For more
information visit www.artemisgoldinc.com.
Qualified Person
Jeremy Langford, FAUSIMM, a Qualified Person as defined by
National Instrument 43-101, has reviewed and approved the
scientific and technical information in this press release.
On behalf of the Board of Directors
Steven Dean
Chairman and Chief Executive Officer
+1 604 558 1107
Neither the TSX Venture Exchange nor its Regulation Services
Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or
accuracy of this news release.
Cautionary Note Regarding
Forward-looking Information
This press release contains certain forward-looking
statements and forward-looking information as defined under
applicable Canadian and U.S. securities laws. Statements contained
in this press release that are not historical facts are
forward-looking statements that involve known and unknown risks and
uncertainties. Any statements that refer to expectations,
projections or other characterizations of future events or
circumstances contain forward-looking statements. In certain cases,
forward-looking statements and information can be identified using
forward-looking terminology such as "may", "will", "expect",
"intend", "estimate", "anticipate", "believe", "continue", "plans",
"potential" or similar terminology. Forward-looking statements and
information are made as of the date of this press release, and
include, but are not limited to, statements regarding the potential
of the Blackwater mine project; the jobs to be created in
connection with the project; the contribution of the project to the
economy; opinions of the Province of British Columbia regarding the project and the
region; agreements and relationships with Indigenous partners; the
future of mining in British
Columbia; the plans of the Company with respect to the
project, including construction, site preparation, clearing,
consultation with indigenous groups, and other plans and
expectations of the Company with respect to the project.
These forward-looking statements represent management's
current beliefs, expectations, estimates and projections regarding
future events and operating performance, which are based on
information currently available to management, management's
historical experience, perception of trends and current business
conditions, expected future developments and other factors which
management considers appropriate. Such forward-looking statements
involve numerous risks and uncertainties, and actual results may
vary. Important risks and other factors that may cause actual
results to vary include, without limitation: risks related to the
ability of the Company to accomplish its plans and objectives with
respect to the development of the project within the expected
timing or at all, the timing and receipt of certain required
approvals, changes in commodity prices, changes in interest and
currency exchange rates, risks inherent in exploration estimates
and results, risks inherent in exploration and development
activities, changes in development or mining plans due to changes
in logistical, technical or other factors, unanticipated
operational difficulties (including failure of plant, equipment or
processes to operate in accordance with specifications, cost
escalation, unavailability of materials, equipment or third party
contractors, delays in the receipt of government approvals,
industrial disturbances, job action, and unanticipated events
related to heath, safety and environmental matters), changes in
governmental regulation of mining operations, political risk,
social unrest, changes in general economic conditions or conditions
in the financial markets, and other risks related to the ability of
the Company to proceed with its plans for the project and other
risks set out in the Company's most recent MD&A, which is
available on the Company's website at
www.artemisgoldinc.com and on SEDAR+ at
www.sedarplus.ca
In making the forward-looking statements in this press
release, the Company has applied several material assumptions,
including without limitation, the assumptions that: (1) market
fundamentals will result in sustained mineral demand and prices;
(2) any necessary approvals and consents in connection with the
development of the project will be obtained; (3) financing for the
development, construction and continued operation of the project
will continue to be available on terms suitable to the Company; (4)
sustained commodity prices will continue to make the project
economically viable; and (5) there will not be any unfavourable
changes to the economic, political, permitting and legal climate in
which the Company operates. Although the Company has attempted to
identify important factors that could affect the Company and may
cause actual actions, events, or results to differ materially from
those described in forward-looking statements, there may be other
factors that cause the actual results or performance by the Company
to differ materially from those expressed in or implied by any
forward-looking statements. Accordingly, no assurances can be given
that any of the events anticipated by the forward-looking
statements will transpire or occur, or if any of them do so, what
impact they will have on the results of operations or the financial
condition of the Company. Investors should therefore not place
undue reliance on forward-looking statements. The Company is under
no obligation and expressly disclaims any obligation, to update,
alter or otherwise revise any forward-looking statement, whether
written or oral, that may be made from time to time, whether
because of new information, future events or otherwise, except as
may be required under applicable securities laws.
_____________________________
|
1 LTIFR or
Lost Time Injury Frequency Rate refers to the number of lost time
injuries occurring per million man-hours worked, divided by total
man-hours worked.
|
2 AIFR or
All Injury Frequency Rate refers to the total number of recordable
incidents occurring per million man-hours worked, divided by total
man-hours worked.
|
SOURCE Artemis Gold Inc.