TIDMTALV 
 
   Stock Exchange Release 
 
   Talvivaara Mining Company Plc 
 
   28 May 2014 
 
   Talvivaara Mining Company Interim Report for January-March 2014 
 
   Corporate reorganisation proceedings in progress 
 
   Metals recovery plant and bioheapleaching in stable operation 
 
   Highlights of Q1 2014 
 
 
   -- Nickel production of 3,068t and zinc production of 5,726t; best quarter 
      since Q3 2012 
 
   -- Net sales of EUR 29.0 million 
 
   -- Operating loss of EUR (7.1) million 
 
   -- New heaps leached well and provided most of the produced metals during 
      the quarter; 
 
 
   nickel grades in solution around 1.5g/l 
 
 
   -- Metals plant in stable operation throughout the quarter 
 
   -- Ore production remained suspended with re-start subject to securing 
      additional financing 
 
 
   Highlights after the reporting period 
 
 
   -- Loan and streaming holiday agreement with Nyrstar for an up to EUR 20 
      million loan facility and option to sell up to 80,000t of zinc to Nyrstar 
      at market price for an additional significant financing impact 
 
   -- Talvivaara Sotkamo was granted an environmental permit decision on 30 
      April 2014 relating to its whole operation and uranium recovery; however, 
      operations continue under the old permit for the time being, as the new 
      permit is not yet final and binding 
 
   -- Bioheapleaching and metals recovery operations continue steadily; 
      year-to-date metals production through 26 May amounted to 5,053t of 
      nickel and 9,592t of zinc 
 
 
   Corporate reorganisation 
 
 
   -- Reports by the Administrator on the financial status of Talvivaara Mining 
      Company Plc ("Talvivaara" or the "Company") and Talvivaara Sotkamo 
      completed on 14 April 2014 and conclude that executable restructuring 
      programmes can be set up for both companies subject to financing 
      solutions being achieved 
 
   -- The District Court of Espoo granted on 21 May 2014 an extension to the 
      deadlines for submitting the proposals for the respective reorganisation 
      programmes of the Company and Talvivaara Sotkamo until 30 September 2014 
      as applied by the Administrator 
 
   Guidance for 2014 
 
   Talvivaara's operational outlook in 2014 remains subject to the success 
to completion, timing and extent of the financing transactions that are 
currently being negotiated. In the absence of a comprehensive financing 
solution and related operational plan for the time being, Talvivaara is 
not in a position to give guidance on its production or its operational 
and capital expenditure for the current year. 
 
   Key figures 
 
 
 
 
                                          Q1         Q4        Q1        FY 
EUR million                              2014       2013       2013     2013 
Net sales                                  29.0        12.6     27.6      77.6 
Operating loss                            (7.1)     (628.7)   (20.0)   (701.8) 
     % of net sales                     (24.4)%  (4,988.7)%  (72.4)%  (904.7)% 
Loss for the period                      (17.1)     (731.8)   (23.9)   (812.4) 
Earnings per share, EUR                  (0.01)      (0.43)   (0.09)    (0.48) 
Equity-to-assets ratio                  (49.9)%     (46.1)%    25.5%   (46.1)% 
Net interest bearing debt                 552.1       548.7    530.1     548.7 
Debt-to-equity ratio                   (181.3)%    (190.9)%   159.1%  (190.9)% 
Capital expenditure                         1.5         7.4     17.3      60.5 
Cash and cash equivalents at the end 
 of the period                              1.1         5.9     68.7       5.9 
Number of employees at the end of the 
 period                                     516         549      583       549 
 
   All quarterly figures in this release are unaudited. Full year figures 
are audited. 
 
   CEO Pekka Perä comments: "Our first quarter 2014 results reflect an 
operationally steady period with best nickel and zinc production since 
Q3 2012. Our new ore heaps, primary heaps 1 and 4, demonstrated very 
good leaching performance after having started to contribute to our 
metals production towards the end of 2013. Our metals recovery plant 
also performed uneventfully, which, together with the improvements in 
bioheapleaching, gives us confidence that our processes have come of age 
and can be operated in a reliable, industrial fashion. 
 
   Our financial results continued to be impacted by the weak nickel price 
that persisted through most of the first quarter and the yet limited 
production volumes obtainable from the currently functioning two primary 
heaps, resulting in an operating loss of EUR 7.1 million. However, our 
cost profile compared to the year before confirmed substantial savings 
as a result of our on-going work towards better operational efficiency, 
and the write-downs recognized on our fixed assets at year-end 2013 
resulted in a considerable reduction in depreciation. All-in-all, though, 
we cannot be content with the results achieved, but must strive for 
further improvements with the target of eventually being able to operate 
profitably also during the lows of the commodity cycles. 
 
   Over the recent months, the sentiment in the nickel market has turned 
for the positive with prices improving from around USD 14,000/t in 
January and USD 15,000-16,000/t in March to around USD 19,500/t 
currently. The main stimulus for the improvement has been the Indonesian 
ban on nickel ore exports, which came into effect in January and which 
has had a particularly strong impact on the nickel ore supply to China. 
The market outlook is now more positive than in the last few years with 
the nickel over-supply being foreseen to turn into a deficit possibly as 
early as this year. 
 
   We believe the good results in bioheapleaching over the last several 
months as well as the recent improvement in the nickel market are 
helpful in our on-going financing efforts. As the first funding step 
since the commencement of both Talvivaara Mining Company and Talvivaara 
Sotkamo's corporate reorganisations in late 2013, we entered into a loan 
and streaming holiday agreement with our zinc client Nyrstar in the 
beginning of April. This entitles us to an up to EUR 20 million loan, 
drawn down in stages in relation to zinc deliveries, and an option to 
sell up to 80,000t of zinc to Nyrstar at market prices, which would have 
an additional financing impact of more than EUR 50 million at current 
zinc prices. Further financing negotiations are now also progressing and 
we hope to be in a position to announce positive news on their 
completion in the coming months. 
 
   The most important short term use of funds for us would be the re-start 
of mining and materials handling operations, which have been suspended 
since November 2013. The new Nyrstar agreement and the improvement in 
nickel price have already given us the opportunity to start reclaiming 
of the poorly leached primary heaps on a trial basis, but more funding 
needs to be secured before we can commit to full scale reclaiming and 
the re-start of mining new ore. 
 
   In longer term, financing will also be needed for our environmental 
commitments, particularly those relating to water management. Following 
a relatively light spring melt, the current status of the water balance 
is reasonably good with ample emergency volume in all ponds and dams. 
However, planning of longer term solutions, including e.g. discharge of 
treated water to an alternative waterway and additional reverse osmosis 
capacity, continues and must be financed in due course. 
 
   Talvivaara Sotkamo was granted an environmental permit decision relating 
to its whole operation and uranium recovery by the Northern Finland 
Regional State Administrative Agency on 30 April 2014. We have since 
assessed the decision and will appeal against several parts of the 
decision, including amongst other things the method of assessment of the 
securities to be set as well as some other permit conditions which are 
deemed to be against the prevailing permitting practice. As the new 
permit decision will only be applicable when the appeal processes have 
been completed, Talvivaara will continue to operate under the previously 
obtained, existing permits for the time being and continue its work 
towards increasingly sustainable operations." 
 
   Enquiries: 
 
   Talvivaara Mining Company Plc. Tel. +358 20 712 9800 
 
   Pekka Perä, CEO 
 
   Saila Miettinen-Lähde, Deputy CEO and CFO 
 
   Webcast and conference call on 28 May 2014 at 11:00 am Finland (EET) / 
9:00 am UK (GMT) 
 
   A combined webcast and conference call on the January-March 2014 Interim 
Result will be held on 28 May 2014 at 11:00am Finland (EET) / 9:00 am UK 
(GMT). The call will be held in English. 
 
   The webcast can be accessed through: 
http://qsb.webcast.fi/t/talvivaara/talvivaara_2014_0528_q1/ 
 
   A conference call facility will be available for a Q&A with senior 
management following the presentation. 
 
   Participant - Finland: +358 (0)9 2313 9201 
 
   Participant - UK: +44 (0)20 7162 0077 
 
   Participant - US: +1 334 323 6201 
 
   Conference ID: 945070 
 
   The webcast will also be available for viewing on the Talvivaara website 
shortly after the event. 
 
   Financial review 
 
   Q1 2014 (January-March) 
 
   Net sales and financial result 
 
   Talvivaara's net sales for nickel and cobalt deliveries to Norilsk 
Nickel during the quarter ended 31 March 2014 amounted to EUR 29.0 
million (Q1 2013: EUR 27.6 million). No zinc deliveries to Nyrstar Sales 
and Marketing AG under the zinc streaming agreement were made. Compared 
to Q4 2013, net sales increased by 130% due to increased nickel product 
deliveries enabled by stable production throughout the quarter. Nickel 
prices remained depressed at around USD 14,000/t for most of the quarter, 
hence the sharp increase in nickel price seen towards the end of Q1 2014 
and thereafter did not yet have a material impact on the first quarter 
revenues and financial results. Product deliveries in Q1 2014 amounted 
to 3,107t of nickel and 63t of cobalt (Q1 2013: 2,746t of nickel, 2,217t 
of zinc, 88t of cobalt). 
 
   The Group's other operating income amounted to EUR 0.5 million (Q1 2013: 
EUR 0.7 million) and mainly resulted sales of trees. 
 
   Changes in inventories of finished goods and work in progress amounted 
to EUR (1.2) million (Q1 2013: EUR 7.3 million). Due to the temporary 
suspension of mining and materials handling operations, no new ore was 
stacked on leaching heaps during Q1 2014. The change in work in progress 
therefore primarily reflected the removal of metals from the existing 
heaps as a result of metal sulphide production. 
 
   Personnel expenses were EUR (6.2) million in Q1 2014 (Q1 2013: EUR (7.3) 
million). The decrease in the personnel expenses compared to the year 
before reflects a decrease in the number of employees as well as the 
lay-offs implemented subsequent to the conclusion of the Group's 
co-operation consultations on 7 January 2014. 
 
   Operating loss for Q1 2014 was EUR (7.1) million (Q1 2013: EUR (20.0) 
million). Materials and services were EUR (14.9) million in Q1 2014 (Q1 
2013: EUR (22.6) million) and other operating expenses were EUR (8.4) 
million (Q1 2013: EUR (12.6) million). Metals production in Q1 2014 was 
higher than that the year before, yet a substantial reduction in costs 
was seen. This reflects the savings and improved operating efficiency in 
metals recovery realized through the Company's Turnaround project in 
2013. Mining and materials handling were suspended throughout Q1 2014 as 
well as the first quarter of the year before with the exception of 
reclaiming, which was operational in January 2013. Depreciation 
decreased from EUR (12.6) million in Q1 2013 to EUR (8.4) million in Q1 
2014 as a result of the impairment charges on property, plant and 
equipment recognised at the end of 2013. The reduction in depreciation 
is, however, not directly proportional to the impairment charge, as 
depreciations on leased equipment continued unaffected. 
 
   Finance income for Q1 2014 was EUR 0.2 million (Q1 2013: EUR 0.3 
million). Finance costs of EUR (10.2) million (Q1 2013: EUR (12.1) 
million) were mainly related to interest accrued on borrowings. However, 
due to the ongoing corporate reorganisation proceedings of the Company 
and Talvivaara Sotkamo, no interest payments on borrowings, with the 
exception of leasing arrangements, were made. The eventual treatment of 
interests and repayment of restructuring debt will be decided as a part 
of the reorganisation programmes, the proposals for which are due to be 
submitted by 30 September 2014. 
 
   Loss for the period and the total comprehensive income amounted to EUR 
(17.1) million (Q1 2013: EUR (23.9) million). Earnings per share were 
EUR (0.01) in Q1 2014 (Q1 2013: EUR (0.09)). 
 
   Balance sheet 
 
   Capital expenditure in Q1 2014 totalled EUR 1.5 million (Q1 2013: EUR 
17.3 million). The expenditure primarily related to water management. On 
the consolidated statement of financial position as at 31 March 2014, 
property, plant and equipment totalled EUR 300.5 million (31 December 
2013: EUR 305.0 million), reflecting the EUR 499.3 million impairment 
charge recognized at year-end 2013. 
 
   In the Group's assets, inventories amounted to EUR 259.9 million on 31 
March 2014 (31 December 2013: EUR 261.5 million). At year-end 2013, an 
impairment charge of EUR 93.7 million was recognized on the inventory. 
Subsequently, the decrease in inventory in Q1 2014 reflects metals 
production from the heaps while no new ore was added to the inventory 
due to the temporary suspension of ore production. 
 
   Trade receivables amounted to EUR 16.3 million on 31 March 2014 (31 
December 2013: EUR 10.4 million). The increase compared to the year 
before was attributable to the discontinuation of the sale of 
receivables and higher amount of product deliveries. Nickel price was, 
however, lower than in Q1 2013, which on the other hand had a decreasing 
impact on the receivables. 
 
   On 31 March 2014, cash and cash equivalents totalled EUR 1.1 million (31 
December 2013: EUR 5.9 million). 
 
   In equity and liabilities, total equity amounted to EUR (304.6) million 
on 31 March 2014 (31 December 2013: EUR (287.5) million). 
 
   Provisions decreased from EUR 13.3 million on 31 December 2013 to EUR 
10.9 million at the end of March 2014, reflecting costs related to water 
management and the gypsum pond leakage of November 2012, and the 
corresponding de-recognition of provisions. The incurred costs came from 
the treatment of excess waters with limestone and milk of lime. 
 
   Borrowings decreased from EUR 554.6 million on 31 December 2013 to EUR 
553.1 million at the end of March 2014. The changes in borrowings during 
Q1 2014 mainly related to finance lease liabilities. Most of the Group's 
other debts are restructuring debts, the payment terms of which, 
including repayment amounts, interests and repayment schedules, will be 
decided as part of the Company and Talvivaara Sotkamo's reorganisation 
programmes. Proposals for the reorganisation programmes are due to be 
submitted by the Administrator by 30 September 2014. 
 
   Total advance payments as at 31 March 2014 amounted to EUR 286.1 million, 
which is the same value as at 31 December 2013, as no zinc deliveries to 
Nyrstar took place during the quarter. 
 
   Total equity and liabilities as at 31 March 2014 amounted to EUR 610.7 
million (31 December 2013: EUR 623.3 million). 
 
   Going concern 
 
   Talvivaara's interim results for the first quarter of 2014 have been 
prepared on a going concern basis, which assumes that the Company will 
be able to realise its assets and discharge its liabilities in the 
normal course of business for the foreseeable future. 
 
   The Company is working together with the Administrator towards finding 
appropriate financing solutions for the Group going forward. On 1 April 
2014, Talvivaara entered into a loan and streaming holiday agreement 
with Nyrstar Sales and Marketing AG ("Nyrstar") for a loan facility of 
up to EUR 20 million and an arrangement whereby, subject to Talvivaara 
securing a long-term financial solution, the Group also has an option to 
enter into a streaming holiday for delivery volumes of up to 80,000 
tonnes of zinc in concentrate. During the streaming holiday, Nyrstar 
commits, outside the framework of the original contract between the 
parties, to purchase zinc concentrate from Talvivaara at market terms 
for an additional financing impact of more than EUR 50 million at 
current market prices for zinc. 
 
   The agreement with Nyrstar, together with the recent positive 
development in nickel price, have provided Talvivaara with sufficient 
liquidity to continue the corporate reorganisation and its operations in 
the short term. To secure the Group's long term viability, Talvivaara 
also explores the options of identifying potential investor(s) to 
participate in a medium term bridge financing and/or a long-term, 
overall financial solution for the Group. 
 
   As of the date of the announcement of the Company's Q1 2014 interim 
results, the Directors, Management and the Administrator do not 
contemplate the liquidation of the Company or Talvivaara Sotkamo. As 
such, Directors and Management believe that the going concern basis of 
presentation is appropriate regardless of the on-going financing 
discussions and commencement of the reorganisation proceedings. However, 
the Company's liquidity situation continues to cause material 
uncertainty that casts significant doubt upon the Company and Talvivaara 
Sotkamo's ability to continue as a going concern and that, therefore, 
the Group may be unable to realise its assets and discharge its 
liabilities in the normal course of business. Should the going concern 
basis prove inappropriate in the foreseeable future, adjustments to the 
carrying amounts and/or classifications of Talvivaara's assets and 
liabilities would be necessary. 
 
   The Group's ability to continue as a going concern is dependent on the 
successful completion of the contemplated financing transactions as well 
as the development and authorisation of executable restructuring 
programmes for both the Company and Talvivaara Sotkamo. Furthermore, 
Talvivaara's future profitability is dependent on the prevailing market 
conditions and the Group's ability to successfully implement its 
business plan at the Talvivaara mine.  At the time of the Company's Q1 
2014 interim results on 28 May 2014, it is not possible to foresee 
whether Talvivaara will be able to execute its financing, reorganisation 
and operational plans or whether the execution of these will improve the 
Group's financial condition sufficiently to allow it to continue as a 
going concern. 
 
   The corporate reorganisation plans to be authorised by the District 
Court of Espoo could materially change the carrying amounts and 
classifications reported in the Group's financial statements. The assets 
and liabilities in the Company's Q1 2014 interim results do not reflect 
any adjustments potentially proposed or authorised as part of such 
reorganisation plans. Furthermore, the interim results do not aim to 
reflect or provide for the consequences of the corporate reorganisation 
proceedings, such as: (i) the realisable value of the Group's assets on 
a liquidation basis or their availability to satisfy liabilities, (ii) 
the amounts of loans and debts subject to reorganisation and priority 
thereof, (iii) or the effect on the Group's consolidated income 
statement of any changes potentially made to its business as a result of 
the final corporate reorganisation plan. However, in view of the 
inherent uncertainty brought about by the corporate reorganization 
proceedings, operational challenges caused by and partly continuing as a 
result of water balance issues, and the weak nickel price environment 
that prevailed for most of 2013 and into early 2014, the Group has made 
substantial impairment charges in its FY 2013 financial statements 
related to its tangible assets, inventories and deferred tax assets. 
Further, the challenging liquidity position and the commencement of the 
corporate reorganisation proceedings for the Company and Talvivaara 
Sotkamo have resulted in breach of covenants and default events in 
accordance with the respective terms and conditions of the companies' 
loan agreements resulting in adjustments to the carrying values and 
classifications of such loans. 
 
   Progress of corporate reorganisation 
 
   Upon deciding to commence the reorganisation proceedings of the Company 
and Talvivaara Sotkamo on 
 
   29 November 2013 and 17 December 2013, respectively, the District Court 
of Espoo, Finland, appointed Mr. Pekka Jaatinen, Attorney-at-Law, from 
Castrèn & Snellman Attorneys Ltd. to act as the Administrator for 
both processes. 
 
   On 17 January 2014, the District Court of Espoo issued a ruling in 
respect of certain deadlines in connection with the Company and 
Talvivaara Sotkamo's respective corporate reorganisations. According to 
the Court's ruling, reports on the financial status of both companies 
were to be completed by 28 March 2014, and proposals for their 
respective reorganisation were to be submitted by the Administrator by 
28 May 2014. However, the District Court has since amended these 
deadlines such that the reports on the financial status of the companies 
were completed on 14 April 2014, and the new deadline for the submission 
of the reorganisation proposals is 30 September 2014. 
 
   The District Court has also appointed creditor committees, which will 
act as the joint representatives of the creditors in the reorganisation 
proceedings of both companies. Various creditor groups, including 
secured creditors, other debt financiers, as well as business partners 
and subcontractors essential for the operations of both companies, are 
represented in the creditor committees. The creditor committees of the 
Company and Talvivaara Sotkamo have the same composition. 
 
   Production review 
 
   Talvivaara produced 3,068t (Q1 2013: 2,732t) of nickel and 5,726t (Q1 
2013: 3,128t) of zinc during Q1 2014. Metals production was stable with 
good leaching performance from the two new heaps and high availability 
of the metals plant. Mining and materials handling processes have been 
suspended since November 2013. Subject to financing, re-start of these 
functions is planned to take place in stages during the coming summer 
and autumn. 
 
   As a result of the improved grades in leach solution from the new 
primary heaps 1 and 4, the nickel grade in solution pumped to the metals 
plant rose from around 1.0g/l at the end of 2013 to 1.5-1.6g/l in 
February, allowing 45-55t of nickel production on a daily basis at 
solution flow rates of around 1,400 m3/h through the metals plant. 
 
   The old primary heaps 2 and 3 continued to suffer from the effects of 
excess water and remained largely inactive. Consequently the decision 
was taken to cease acid addition to these heaps until they are reclaimed 
and re-stacked on the secondary leaching area. 
 
   The cost efficiency of production at the metals plant improved 
significantly as a result of the higher metal grades in solution as well 
as the substantially higher temperature of the leach solution compared 
to the winter of 2013. The increased solution temperature, around 20degC 
this winter vs. 6degC the year before, reflects the high level of 
chemical and biological activity in the new primary heaps 1 and 4. 
 
   The steady production over the recent months demonstrates that the 
technologies applied by Talvivaara are functional and have matured to a 
stage where they can be considered reliable industrial processes. 
 
   Production key figures 
 
 
 
 
                                 Q1     Q4     Q1      FY 
                                 2014   2013   2013   2013 
Mining 
Ore production         Mt           -    1.6      -     7.4 
Waste production       Mt           -    0.9      -     3.1 
Materials handling 
Stacked ore            Mt           -    1.7      -     7.6 
Bioheapleaching 
Ore under leaching     Mt        51.8   51.8   44.3    51.8 
Metals recovery 
Nickel metal content   Tonnes   3,068  1,559  2,732   8,662 
Zinc metal content     Tonnes   5,726  4,179  3,128  17,418 
 
 
   Sustainable development, safety and permitting 
 
   Safety 
 
   With respect to safety issues, Talvivaara's goal is a safe and healthy 
working environment, and the Company continued to develop its safety 
culture based on zero accident philosophy. 
 
   At the end of the first quarter, the injury frequency among the 
Talvivaara personnel was 34.9 lost time injuries/million working hours 
on a rolling 12 month basis (31 March 2013: 15.7 lost time 
injuries/million working hours). 
 
   Environment 
 
   Talvivaara continues to focus on minimising the environmental impact of 
its operations. Current primary focus is on water balance management and 
purification and discharge of excess waters from the mine site. 
 
   During the first quarter of 2014, significant effort was made to 
ascertain sufficient emergency volumes in ponds and dams ahead of the 
spring melt and in case of any leakages. Particular focus was on the 
Kortelampi dam, from where water was treated and released directly to 
the southern Vuoksi waterways as well as through the Tammalampi water 
treatment unit to the northern Oulujoki water system. Removal of excess 
water from the gypsum ponds also continued with the target of having all 
excess water removed by the end of August 2014 (see also Permitting). 
 
   Hydrogen sulphide (odour) emissions have been largely addressed. Odour 
complaints from nearby residents reduced further from five in Q1 2013 to 
three in Q1 2014. Notices of noise increased, however, from one to seven 
as a result of an increased number of blowers used for the aeration of 
leaching heaps. 
 
   Talvivaara continues to place significant emphasis on timely and 
transparent communication on environmental matters with the neighbouring 
communities and other interested stakeholders. During the first quarter, 
a new text message service targeted for nearby neighbours was 
implemented. Furthermore, the Company's first ever Twitter question and 
answer session with Talvivaara's sustainability experts was successfully 
held. 
 
   Permitting 
 
   At the end of May 2013, Talvivaara received from the Northern Finland 
Regional State Administrative Agency ("AVI") an environmental permit 
decision relating to the storage, treatment and discharge of waters to 
the Oulujoki and Vuoksi water systems. Among other regulations, the 
decision required the Company to direct the water contained in the 
existing gypsum ponds to neutralisation or back to leach solution 
circulation by 31 October 2013. The Vaasa Administrative Court 
subsequently extended the deadline until the end of 2013. After this, 
the Company applied for and obtained permission from the AVI for a 
two-staged emptying schedule such that section 5 of the gypsum pond 
should be void of excess water by the end of January 2014, and section 6 
by the end of August 2014. Prior to the end of January, Talvivaara 
notified the Kainuu Centre for Economic Development, Transport and the 
Environment ("Kainuu ELY-Centre") of its inability to comply with the 
interim deadline of January, however stating that the Company believes 
the final emptying deadline for the entire pond to be achievable. After 
this, the Kainuu ELY-Centre has requested section 5 of the gypsum pond 
to be emptied of excess water and sufficient emergency volume to be 
arranged in the Kortelampi dam for all waters contained in the gypsum 
pond by 1 April 2014. Talvivaara noted, in turn, to the ELY-Centre that 
the requested timetable was not technically feasible and that a 
realistic deadline would rather be 15 May 2014. 
 
   Subsequently the Kainuu ELY-Centre gave a ruling on 25 April 2014 
stating that, under a threat of a fine, Talvivaara would have to reduce 
the amount of water in gypsum pond section 6 to below 500,000 cubic 
metres by 15 May 2014. As at 7 May 2014, the amount of water in the pond 
was measured to be approximately 407,000 cubic metres and in compliance 
with the requirement. Gypsum pond section 5 had been emptied of excess 
water already in April. On 15 May 2014, Kainuu ELY-Centre confirmed the 
removal of the threat of a fine. 
 
   On 5 December 2013 the Supreme Administrative Court returned the permit 
to extract uranium granted to Talvivaara Sotkamo under the Nuclear 
Energy Act on 1 March 2012 for reassessment by the Finnish Government. 
According to the Supreme Administrative Court there had been several 
changes in the operations of Talvivaara Sotkamo following the permit 
decision, including the filing for corporate reorganization. Therefore, 
the Government should reassess the permit application documentation and, 
if needed, obtain additional information on the economical and safety 
related requirements. During the first quarter of 2014, preliminary 
discussions with the Ministry of Employment and the Economy were held to 
prepare for the re-application. 
 
   Business development and commercial arrangements 
 
   Participation in Fennovoima nuclear power project 
 
   Talvivaara announced on 21 February 2014 its support for the Fennovoima 
nuclear power project, but noted that under the current circumstances 
the Company focuses all its financial resources on the Sotkamo operation 
and the ongoing corporate reorganisation process. For the time being 
Talvivaara is not in a position to commit to additional funding of the 
Fennovoima project, but will reassess its ability for further 
participation once more clarity into its financing situation is obtained 
and the corporate reorganisation process proceeds. 
 
   Risk management and key risks 
 
   In line with current corporate governance guidelines on risk management, 
Talvivaara carries out an on-going process endorsed by the Board of 
Directors to identify risks, measure their impact against certain 
assumptions and implement the necessary proactive steps to manage these 
risks. During 2013, the Company's focus was on developing its hazardous 
risk management and contingency planning. As a result, a new risk 
register for environmental, safety and accident risks was introduced. 
Contingency planning focused primarily on hazard risks such power 
failure and dam or pond leakages. 
 
   Talvivaara's operations are affected by various risks common to the 
mining industry, such as risks relating to the development of 
Talvivaara's mineral deposits, estimates of reserves and resources, 
infrastructure risks, and volatility of commodity prices. There are also 
risks related to counterparties, currency exchange ratios, management 
and control systems, historical losses and uncertainties about the 
future profitability of Talvivaara, dependence on key personnel, effect 
of laws, governmental regulations and related costs, environmental 
hazards, and risks related to Talvivaara's mining concessions and 
permits. 
 
   Liquidity and refinancing risks may arise as a result of the Company's 
inability to produce sufficient volumes of its saleable products, 
particularly nickel, unexpected increase in production costs, and sudden 
or substantial changes in the prices of commodities or currency exchange 
rates. In the second half of 2013, the liquidity and refinancing risks 
realized as a result of persistent production problems relating to 
excess water, and due to a substantial fall in the nickel price. As a 
result, Talvivaara and its operating subsidiary Talvivaara Sotkamo were 
unable to obtain new financing and applied for corporate reorganisation, 
which for the two companies commenced on 29 November 2013 and 17 
December 2013, respectively. Going forward, Talvivaara's key financial 
and operational risks relate to the on-going corporate reorganisation 
proceedings and Talvivaara's ability to obtain sufficient additional 
funding to continue its operations and to return to the planned ramp-up 
of production. 
 
   Operationally, the Company has to date demonstrated that all of its 
production processes work and can be operated on industrial scale, 
however the rate of ramp-up is still subject to risk factors including 
the reliability and sustainable capacity of production equipment, and 
eventual speed of leaching and rates of metals recovery in 
bioheapleaching. In addition, the return to production ramp-up remains 
subject to further financing for the time being and there may also be 
production and ramp-up related risks that are currently unknown or 
beyond the Company's control. 
 
   The market price of nickel has historically been volatile and in the 
Company's view this is likely to persist, driven by shifts in the 
supply-demand balance, macroeconomic indicators and variations in 
currency exchange ratios. Nickel sales currently represent close to 90% 
of the Company's revenues and variations in the nickel price therefore 
have a direct and significant effect on Talvivaara's financial result 
and economic viability. Talvivaara is, since February 2010, unhedged 
against variations in metal prices. Full or substantially full exposure 
to nickel prices is in line with Talvivaara's strategy and supported by 
the Company's view that it can operate the Talvivaara mine, once it has 
been fully ramped up, profitably also during the lows of commodity price 
cycles. 
 
   Talvivaara's revenues are almost entirely in US dollars, whilst the 
majority of the Company's costs are incurred in Euro. Potential 
strengthening of the Euro against the US dollar could thus have a 
material adverse effect on the business and financial condition of the 
Company. Talvivaara hedges its exposure to the US dollar on a case by 
case basis with the aim of limiting the adverse effects of US dollar 
weakness as considered justified from time to time. 
 
   Personnel and management 
 
   Wages and salaries 
 
   The number of personnel employed by the Group on 31 March 2014 was 516 
(Q1 2013: 583). 
 
   Wages and salaries paid during the three months to 31 March 2014 
totalled EUR 5.1 million (Q1 2013: EUR 4.2 million). 
 
   Conclusion of co-operation consultations 
 
   Talvivaara concluded its co-operation consultations on 7 January 2014. 
All personnel groups in the Company and its subsidiaries Talvivaara 
Sotkamo and Talvivaara Exploration were within the scope of the 
consultations. Following the consultation process, Talvivaara decided to 
gradually lay off 246 employees for an indefinite period. The lay-offs 
support the Company and Talvivaara Sotkamo's corporate reorganisation 
and adjust the number of personnel to the current operating scheme under 
which ore production is temporarily suspended. 
 
   As at 31 March 2014 2014, 97 employees were laid off, which is less than 
anticipated when the co-operation consultations were concluded due to 
previously subcontracted work having been taken in-house and done by the 
Group's own workforce. 
 
   Management changes 
 
   Lassi Lammassaari, M.Sc. (Environmental Engineering) was appointed Chief 
Corporate Development Officer as of 27 February 2014. He leads a newly 
established Corporate Development function, which focuses on industrial 
engineering, planning and development. Lassi Lammassaari has held 
several positions at Talvivaara since 2005, most lately as Senior Vice 
President - Projects. In his new position he is a member of the 
Executive Committee and reports to CEO Pekka Perä. 
 
   Chief Operating Officer Darin Cooper resigned from his position on 7 
March 2014 to pursue his career outside the Company. Chief Technology 
Officer Pertti Pekkala subsequently assumed interim responsibility for 
the Sotkamo mine's operations until a new COO is appointed. In addition, 
the Company's Technical Executive Committee, consisting of CEO Pekka 
Perä, Chief Corporate Development Officer Lassi Lammassaari, CTO 
Pertti Pekkala and Environmental Manager Veli-Matti Hilla as a newly 
appointed member, takes an increasingly active role in the management of 
the operations at the Sotkamo mine. 
 
   Non-Executive Director Kirsi Sormunen announced her resignation from the 
Company's Board of Directors due to personal reasons on 7 March 2014. 
 
   Shares and shareholders 
 
   The number of shares issued and outstanding and registered on the 
Euroclear Shareholder Register as of 31 March 2014 was 1,906,167,480. 
Including the effect of the EUR 225 million convertible bond of 16 
December 2010 and the stock options of 2007 and 2011, the authorised 
full number of shares of the Company amounted to 2,041,901,379. 
 
   After the adjustments to the terms and conditions of the 2007 stock 
options in April 2013 as a consequence of the Company's rights issue, a 
total of 16,289,000 option rights 2007C have been issued to employees 
and the subscription period for stock options 2007C was between 1 April 
2012 and 31 March 2014. No new shares of Talvivaara were subscribed for 
under the stock option rights 2007C between 1 January and 31 March 2014. 
A total of 16,289,000 stock option rights 2007C remained unexercised 
following the end of the subscription period and expired. 
 
   Of the stock options of 2011, option rights 2011A and 2011B have expired 
due to the agreed implementation criteria having not been met. Option 
rights 2011C have not been allocated. 
 
   As at 31 March 2014, the shareholders who held more than 5% of the 
shares and votes of Talvivaara were Solidium Oy (16.7%) and Pekka 
Perä (6.5%). 
 
   Legal proceedings 
 
   On 19 March 2014, the Kainuu ELY Centre issued an administrative 
injunction, requesting Talvivaara Sotkamo to carry on the neutralization 
of metal and sulphate containing waters at the site under all 
circumstances. Further, the ELY Centre requested Talvivaara Sotkamo to 
immediately continue and complete negotiations on the supply of 
additional water purification capacity at the site, as well as on the 
construction of new pond capacity for purified waters. Should Talvivaara 
Sotkamo fail to comply with the request, the Kainuu ELY Centre may 
consider having the investments completed at the cost of Talvivaara 
Sotkamo. In addition, the Kainuu ELY Centre required that the weekly 
utilization rate of Talvivaara Sotkamo's existing reverse osmosis plants 
must stay on or above 60 per cent, failing which could give rise to an 
administrative penalty of EUR 100,000. Talvivaara Sotkamo has appealed 
the injunction to Vaasa Administrative Court. 
 
   Kainuu ELY Centre prohibited on 5 March 2014 Talvivaara Sotkamo to 
discharge raffinate or secondary leach solution into the open pit and 
issued a threat of an administrative penalty of 150,000 euros to enforce 
its decision. Due to the improved water balance situation Talvivaara 
Sotkamo no longer has any need to discharge untreated solutions into the 
open pit. 
 
   In addition, as at the date of these interim results, there are a number 
of on-going legal proceedings and police investigations in relation to 
Talvivaara's mining, environmental and occupational health and safety 
issues. In addition, Talvivaara is subject to, or may become subject to, 
private claims seeking compensation for damages caused by environmental 
issues originating from the Talvivaara mine, although Talvivaara 
currently believes that such claims are not material. The current legal 
proceedings are further discussed in the Company's financial statements 
for 2013. 
 
   Events after the review period 
 
   Loan and streaming holiday agreement with Nyrstar 
 
   On 1 April 2014, the Company and Talvivaara Sotkamo entered into a loan 
and streaming holiday agreement ('the Agreement') with Nyrstar Sales and 
Marketing AG ("Nyrstar"). Under the Agreement, Nyrstar makes available 
to Talvivaara a loan facility of up to EUR 20 million. Nyrstar makes the 
facility available in several tranches with the amount of each advance 
calculated with reference to a corresponding delivery by Talvivaara 
Sotkamo of zinc in concentrate under the original zinc streaming 
agreement of February 2010. 
 
   In the short term, the Agreement enables the continuation of the Company 
and Talvivaara Sotkamo's corporate reorganisation and the process, 
whereby Talvivaara explores the options of identifying potential 
investor(s) to participate in a long-term, overall financial solution 
for the Group. 
 
   Subject to Talvivaara securing the overall financial solution, the 
Company also has an option to enter into a streaming holiday for 
delivery volumes of up to 80,000 tonnes of zinc in concentrate. During 
the streaming holiday, Nyrstar commits, outside the framework of the 
original contract, to purchase zinc concentrate from Talvivaara at 
market terms. The streaming holiday, if used in full, has an over EUR 50 
million additional financing impact for the Company at current zinc 
prices. 
 
   In return for the holiday, the value sharing mechanism of the original 
zinc streaming agreement will be amended to reduce on a pro rata basis 
such that, if the full holiday period is elected, the value sharing 
mechanism thereafter becomes nil. When applied, the value sharing 
mechanism allows Talvivaara to receive a cash consideration for its 
deliveries that is higher than the extraction and processing fee 
determined in the zinc streaming agreement. 
 
   Nyrstar's obligation to extend financing under the loan facility will 
cease at the earlier of the aggregate amount outstanding including 
accrued interest exceeding EUR 20 million or the commencement of a 
streaming holiday. The zinc concentrate deliveries entitling Talvivaara 
to the full loan amount are estimated to be made during the remainder of 
2014. As at the date of these interim results, Talvivaara has drawn down 
EUR 6.7 million of the Nyrstar loan facility. 
 
   Corporate reorganisation 
 
   The reports on the financial status of the Company and Talvivaara 
Sotkamo were completed by the Administrator of the corporate 
reorganisation on 14 April 2014. According to the Administrator, an 
executable restructuring programme can be set up for both companies, 
provided that financing solutions for an interim period and for the 
longer term are achieved. 
 
   On 21 May 2014 the District Court of Espoo granted an extension to the 
deadlines for submitting the proposals for the respective reorganisation 
programmes of the Company Talvivaara Sotkamo until 30 September 2014. 
According to the prior District Court ruling, the proposals for the 
reorganisation programmes were to be submitted by 28 May 2014. 
 
   The Administrator and Talvivaara are engaged in discussions with 
potential financing and industrial partners for a long-term financing 
solution for the Talvivaara Group. Certain industrial and financial 
arrangements for the continuation of operations of the Company and 
Talvivaara Sotkamo have already been reached so that the restructuring 
programmes can be set up. The extension was applied for as submission of 
the restructuring programme proposals is not considered feasible until 
sufficient long-term financing has been secured. 
 
   Environmental permit decision 
 
   Talvivaara Sotkamo was granted an environmental permit decision relating 
to its whole operation and uranium recovery by the Northern Finland 
Regional State Administrative Agency on 30 April 2014. Talvivaara has 
assessed the decision and will appeal against several parts of the 
decision, including amongst other things the method of assessment of the 
securities to be set as well as some other permit conditions which are 
deemed to be against the prevailing permitting practice. The permit 
decision will only be applicable when the appeal processes have been 
completed and Talvivaara will operate under the previously obtained, 
existing permits until the new permit is final. 
 
   Production update 
 
   Talvivaara's year-to-date production through 26 May 2014 has reached 
5,053t of nickel and 9,592t of zinc. Metals production has continued 
stable with good leaching performance from the two new heaps and high 
availability of the metals plant. However, during the second quarter, 
nickel grade in leach solution has declined slightly to a level of 
1.2-1.3g/l due to continued heavy depletion from the two new heaps. 
 
   Mining and materials handling processes have been suspended since 
November 2013. Since mid-May 2014, preparatory work has been undertaken 
to re-commence reclaiming of old primary heaps, and as at the date of 
these interim results, reclaiming is ongoing on a trial basis. However, 
more funding needs to be secured before commitment to full scale 
reclaiming can be made or the mining of new ore re-started. 
 
   Short-term outlook 
 
   Market outlook 
 
   The LME nickel price has shown an approximately 40% recovery since the 
implementation of the Indonesian nickel ore export ban in January 2014, 
moving from levels below USD 14,000/t to around USD 19,500/t currently. 
The surplus in nickel production that has been prevailing over the last 
few years is now expected to turn into a deficit possibly as early as 
this year, which further underpins the recent price development and may 
offer additional upside potential going forward. Provided the Indonesian 
ore export ban stays in force, the nickel price can be anticipated to 
start reflecting also the increasing marginal cost of production across 
the nickel industry and lack of new committed nickel projects to replace 
depleting supply from the existing operations. 
 
   Operational outlook 
 
   The operational outlook for Talvivaara is greatly dependent on the 
success to closing, timing and extent of the short as well longer term 
financing solutions currently under negotiation. The key operational 
priority of the Company has been to start reclaiming old primary heaps 2 
and 3 as soon as possible, preferably during Q2 2014. Moving these heaps 
to the secondary pad will allow the so far poorly leached ore to be 
reconditioned and leaching to be restarted. There is significant 
unleached nickel in these two heaps, which will improve production in 
the coming months prior to leaching from any newly mined and stacked ore 
can start contributing to production. The recent increase in nickel 
price and the loan agreement with Nyrstar have allowed Talvivaara to 
re-start reclaiming on a trial basis during the latter half of May. 
However, further funding will need to be secured before commitment to 
full scale reclaiming can be made. Similarly subject to financing, the 
Company plans to re-start mining of new ore during the summer or early 
autumn. 
 
   Talvivaara believes the pre-requisites for continued production ramp-up 
are in place with substantial improvements having been made over the 
recent months in bioheapleaching, as well as in mining and materials 
handling prior to their suspension in November 2013. Furthermore, the 
metals plant is currently operating uneventfully. 
 
   28 May 2014 
 
   Talvivaara Mining Company Plc. 
 
   Board of Directors 
 
 
 
 
CONSOLIDATED INCOME STATEMENT 
(Applications for corporate reorganisation proceeding 
 filed on 15 Nov 2013) 
                                                     Unaudited     Unaudited 
                                                       three         three 
                                                     months to     months to 
                                                      31 March      31 March 
(all amounts in EUR '000)                               2014          2013 
Net sales                                                 29,014        27,605 
Other operating income                                       547           729 
Changes in inventories of finished goods and work 
 in progress                                             (1,185)         7,288 
Impairment charges on inventories                              -             - 
Materials and services                                  (14,896)      (22,614) 
Personnel expenses                                       (6,188)       (7,285) 
Depreciation and amortization                            (6,032)      (13,099) 
Impairment charges on PPE                                      -             - 
Other operating expenses                                 (8,353)      (12,612) 
Operating loss                                           (7,092)      (19,988) 
Finance income                                               169           339 
Finance cost                                            (10,195)      (12,080) 
Finance income (cost) (net)                             (10,026)      (11,741) 
 
Loss before income tax                                  (17,118)      (31,729) 
Income tax expense                                             -         7,797 
Loss for the period                                     (17,118)      (23,932) 
Attributable to: 
Owners of the parent                                    (14,570)      (21,005) 
Non-controlling interest                                 (2,549)       (2,927) 
                                                        (17,118)      (23,932) 
Earnings per share for profit (loss) attributable 
 to the owners of the parent (expressed in EUR per 
 share) 
Basic and diluted                                         (0.01)        (0.07) 
 
 
 
 
CONSOLIDATED STATEMENT OF COMPREHENSIVE INCOME 
(Applications for corporate reorganisation proceeding 
 filed on 15 Nov 2013) 
                                         Unaudited   Unaudited 
                                            three       three 
                                          months to   months to 
(all amounts in EUR '000)                 31 Mar 14   31 Mar 13 
Loss for the period                        (17,118)    (23,932) 
Other comprehensive income, net of tax            -           - 
Total comprehensive income                 (17,118)    (23,932) 
Attributable to: 
Owners of the parent                       (14,570)    (21,005) 
Non-controlling interest                    (2,549)     (2,927) 
                                           (17,118)    (23,932) 
 
 
 
 
CONSOLIDATED STATEMENT OF FINANCIAL POSITION 
(Applications for corporate reorganisation proceeding 
 filed on 15 Nov 2013) 
                                              Unaudited    Audited 
(all amounts in EUR '000)                      31 Mar 14   31 Dec 13 
ASSETS 
Non-current assets 
Property, plant and equipment                    300,485     304,956 
Biological assets                                  6,488       6,641 
Intangible assets                                  6,520       6,582 
Investments in associates                          6,968       6,968 
Other receivables                                  8,267       8,412 
Available-for-sale financial assets                    2           2 
                                                 328,729     333,560 
Current assets 
Inventories                                      259,816     261,451 
Trade receivables                                 16,327      10,389 
Other receivables                                  4,723      12,047 
Cash and cash equivalent                           1,070       5,867 
                                                 281,937     289,754 
Total assets                                     610,666     623,314 
EQUITY AND LIABILITIES 
Equity attributable to owners of the parent 
Share capital                                         80          80 
Share premium                                      8,086       8,086 
Other reserves                                   764,626     764,603 
Retained deficit                               (940,423)   (925,854) 
                                               (167,631)   (153,085) 
Non-controlling interest in equity             (136,927)   (134,378) 
Total equity                                   (304,558)   (287,463) 
Non-current liabilities 
Borrowings                                        15,264      30,592 
Advance payments                                 270,641     270,641 
Other payables                                        11         270 
Provisions                                        10,891      10,785 
                                                 296,807     312,288 
Current liabilities 
Borrowings                                       537,875     524,011 
Advance payments                                  15,456      15,456 
Trade payables                                    32,376      37,426 
Other payables                                    32,710      19,065 
Provisions                                             -       2,531 
                                                 618,418     598,489 
Total liabilities                                915,224     910,777 
Total equity and liabilities                     610,666     623,314 
 
   CONSOLIDATED STATEMENT OF CHANGES IN SHAREHOLDERS' EQUITY 
 
   (Applications for corporate reorganisation proceeding filed on 15 Nov 
2013) 
 
   A.Share capital 
 
   B. Share issue 
 
   C. Share premium 
 
   D. Invested unrestricted equity 
 
   E. Other reserves 
 
   F. Retained deficit 
 
   G. Total 
 
   H Non-controlling interest 
 
   I. Total equity 
 
 
 
 
(all amounts in 
 EUR '000)        A     B       C       D       E         F        G      H      I 
                                                                  304,     1,   306, 
1 Jan 2013        80       -  8,086  490,749  48,810  (242,962)    763    989    752 
Loss for the                                                      (21,    (2,   (23, 
period             -       -      -        -       -   (21,005)   005)   927)   932) 
Total 
comprehensive 
income for the                                                    (21,    (2,   (23, 
period             -       -      -        -       -   (21,005)   005)   927)   932) 
Transactions 
with owners 
Perpetual 
 capital loan      -       -      -        -   2,612    (1,851)    761      -    761 
                                                                   49,           49, 
Rights issue       -  49,463      -        -       -          -    463      -    463 
Incentive 
 arrangement for 
 Executive 
 Management        -       -      -        -      23          -     23      -     23 
Employee share 
 option scheme 
- value of 
 employee 
 services          -       -      -        -      61          -     61      -     61 
Total 
 contribution by 
 and 
 distribution to                                                   50,           50, 
 owners            -  49,463      -        -   2,696    (1,851)    308      -    308 
Total 
 transactions                                                      50,           50, 
 with owners       -  49,463      -        -   2,696    (1,851)    308      -    308 
                                                                  334,          333, 
31 Mar 13         80  49,463  8,086  490,749  51,506  (265,818)    066  (938)    128 
                                                                 (153,  (134,  (287, 
31 Dec 13         80       -  8,086  741,576  23,028  (925,854)   085)   378)   463) 
                                                                 (153,  (134,  (287, 
1 Jan 14          80       -  8,086  741,576  23,028  (925,854)   085)   378)   463) 
Loss for the                                                      (14,    (2,   (17, 
period             -       -      -        -       -   (14,570)   570)   549)   118) 
Total 
comprehensive 
income for the                                                    (14,    (2,   (17, 
period             -       -      -        -       -   (14,570)   570)   549)   118) 
Transactions 
with owners 
Incentive 
 arrangement for 
 Executive 
 Management        -       -      -        -      23          -     23      -     23 
Total 
 contribution by 
 and 
 distribution to 
 owners            -       -      -        -      23          -     23      -     23 
Total 
 transactions 
 with owners       -       -      -        -      23          -     23      -     23 
                                                                 (167,  (136,  (304, 
31 Mar 14         80       -  8,086  741,576  23,051  (940,423)   631)   927)   558) 
 
 
 
 
CONSOLIDATED STATEMENT OF CASH FLOWS 
(Applications for corporate reorganisation proceeding 
 filed on 15 Nov 2013) 
                                                      Unaudited    Unaudited 
                                                         three        three 
                                                       months to    months to 
(all amounts in EUR '000)                              31 Mar 14   31 Mar 2013 
Cash flows from operating activities 
Loss for the period                                     (17,118)      (23,932) 
Adjustments for 
Tax                                                            -       (7,797) 
Depreciation and amortization                              6,032        13,099 
Impairment charges on PPE                                      -             - 
Impairment charges on inventories                              -             - 
Other adjustments                                            861       (6,758) 
Interest income                                            (169)         (339) 
Interest expense                                          10,195        12,080 
                                                           (199)      (13,647) 
Change in working capital 
Decrease(+)/increase(-) in other receivables               1,527         8,291 
Decrease (+)/increase (-) in inventories                     322       (8,702) 
Decrease(-)/increase(+) in trade and other payables      (2,116)       (4,305) 
Change in working capital                                  (267)       (4,716) 
                                                           (466)      (18,363) 
Interest and other finance cost paid                       (409)         (789) 
Interest and other finance income                             12           213 
Net cash used in operating activities                      (863)      (18,939) 
Cash flows from investing activities 
Investments in associates                                      -         (486) 
Purchases of property, plant and equipment               (1,471)      (17,085) 
Purchases of biological assets                                 -          (52) 
Purchases of intangible assets                              (29)         (176) 
Proceeds from sale of biological assets                      644            92 
Net cash used in investing activities                      (856)      (17,707) 
Cash flows from financing activities 
Proceeds from share issue net of transactions costs            -        54,035 
Related party investment in Talvivaara shares                  -             - 
Proceeds from advance payments                                 -        19,480 
Payment of interest-bearing liabilities                  (1,366)       (1,317) 
Payment of financial leasing liabilities                 (1,712)       (2,919) 
Net cash generated from financing activities             (3,078)        69,279 
Net increase (decrease) in cash and cash equivalents     (4,797)        32,633 
Cash and cash equivalents at beginning of the period       5,867        36,058 
Cash and cash equivalents at end of the period             1,070        68,691 
 
   NOTES 
 
   1.     Basis of preparation 
 
   This interim report has been prepared in compliance with IAS 34 
 
   The interim financial information set out herein has been prepared on 
the same basis and using the same accounting policies as were applied in 
drawing up the Group's statutory financial statements for the year ended 
31 December 2013. 
 
 
 
 
2. Property, plant and equipment 
                                                    Machinery   Construction     Land       Other 
                                                        and          in           and      tangible 
(all amounts in EUR '000)                            equipment    progress     buildings    assets     Total 
Gross carrying amount at 1 Jan 14                      407,003       105,154     294,482    242,147  1,048,786 
Additions                                                   77         1,395           -          -      1,472 
Gross carrying amount at 31 Mar 14                     407,080       106,549     294,482    242,147  1,050,258 
Accumulated depreciation and 
 impairment losses at 1 Jan 14                         293,759        67,305     204,757    178,010    743,831 
Depreciation for the period                              3,911             -       1,200        831      5,942 
Accumulated depreciation and impairment losses at 
 31 Mar 14                                             297,670        67,305     205,957    178,841    749,773 
Carrying amount at 1 Jan 14                            113,244        37,849      89,725     64,137    304,955 
Carrying amount at 31 Mar 14                           109,410        39,244      88,525     63,306    300,485 
 
 
 
 
3. Trade receivables 
(all amounts in EUR '000) 
                                     As at                   As at 
                                   31 Mar 14                31 Dec 13 
Nickel-Cobalt sulphide                       15,952                   9,977 
Zinc sulphide                                   375                     375 
Copper sulphide                                   -                      37 
Total trade receivables                      16,327                  10,389 
 
 
 
 
4. Inventories 
(all amounts in EUR '000) 
                                As at 31 March 2014    As at 31 Dec 2013 
Raw materials and consumables                 24,350                24,800 
Work in progress                             231,625               234,193 
Finished products                              3,841                 2,457 
Total inventories                            259,816               261,451 
 
 
 
 
5. Borrowings 
(all amounts in EUR '000) 
 
                                                As at      As at 
Non-current                                    31 Ma 14   31 Dec 13 
Finance lease liabilities                        15,264      17,000 
Other                                                 -      13,593 
                                                 15,264      30,592 
Current 
Capital loans                                     1,405       1,405 
Perpetual capital loan                           35,106      35,106 
Investment and Working Capital loan              57,855      57,855 
Finance lease liabilities                         7,052       7,032 
Revolving Credit Facility                        70,000      70,000 
Senior Unsecured Bonds due 2017                 110,000     110,000 
Senior Unsecured Convertible Bonds due 2015     244,230     242,613 
Other                                            12,227           - 
                                                537,875     524,011 
Total borrowings                                553,139     554,603 
 
 
 
 
6. Advance payments 
(all amounts in EUR '000) 
 
                                   As at       As at 
Non-current                       31 Mar 14   31 Dec 13 
Deferred zinc sales revenue         216,713     216,713 
Deferred uranium sales revenue       53,928      53,928 
                                    270,641     270,641 
Current 
Deferred zinc sales revenue          15,456      15,456 
                                     15,456      15,456 
Total advance payments              286,097     286,097 
 
 
 
 
7. Provisions 
                             Gypsum      Water 
                              pond      balance    Environmental  Mining 
                             leakage  management    restoration    fee     Total 
31 Dec 13                      3,775        2,531          6,849     162   13,316 
Charged/(credited) to the 
 income statement: 
Additional provisions              -            -            106       8      114 
Unwinding of discount              -            -              1       -        1 
Used during the period                    (2,531)              -       -  (2,531) 
31 Dec 14                      3,775            -          6,956     170   10,901 
The non-current and current portions of provisions 
 are as follows: 
 
                                            As at          As at 
                                        31 Mar 14       31 Dec 3 
Non-current 
Gypsum pond leakage                         3,775          3,775 
Environmental restoration                   6,956          6,849 
Mining fee                                    170            161 
                                           10,901         10,785 
Current 
Water balance management                        -          2,531 
                                                -          2,531 
Total                                      10,901         13,316 
 
 
 
 
 
8. Changes in the number of shares issued 
                             Number 
                            of shares 
31 Dec 13                      1,906,167,480 
Changes                                    - 
31 Dec 14                      1,906,167,480 
 
 
 
 
9. Contingencies and commitments 
(all amounts in EUR '000) 
The future aggregate minimum lease payments under 
 non cancellable 
operating leases 
                                    As at       As at 
                                   31 Mar 14   31 Dec 13 
Not later than 1 year                  1,812       1,812 
Later than 1 year and not later 
 than 5 years                            549         552 
Later than 5 years                        25          29 
                                       2,386       2,393 
 
   Capital commitments 
 
   At 31 March 2014, the Group had capital commitments amounting to EUR 0.8 
million (31 December 2013: EUR 1.2 million) principally relating to the 
completion of the Talvivaara mine, improving the reliability and 
expansion of production capacity. These commitments are for the 
acquisition of new property, plant and equipment. 
 
 
 
 
Talvivaara Mining Company Plc 
                                               Three       Three      Twelve 
                                           months to   months to   months to 
Key financial figures of the Group         31 Mar 14   31 Mar 13   31 Dec 13 
Net sales                       EUR '000      29,014      27,605      77,572 
Operating loss                  EUR '000     (7,092)    (19,988)   (701,801) 
Operating loss percentage                    -24.4 %     -72.4 %    -904.7 % 
Loss before tax                 EUR '000    (17,118)    (31,729)   (758,043) 
Loss for the period             EUR '000    (17,118)    (23,932)   (812,447) 
Return on equity                                   -      -7.5 %     -12.9 % 
Equity-to-assets ratio                       -49.9 %      25.5 %     -46.1 % 
Net interest-bearing debt       EUR '000     552,069     530,063     548,736 
Debt-to-equity ratio                        -181.3 %     159.1 %    -190.9 % 
Return on investment                          -2.7 %      -1.3 %      -1.2 % 
Capital expenditure             EUR '000       1,471      17,313      60,535 
Property, plant and equipment   EUR '000     300,485     813,604     304,956 
Borrowings                      EUR '000     553,139     598,754     554,603 
Cash and cash equivalents at 
 the end of the period          EUR '000       1,070      68,691       5,867 
 
 
 
 
 
Share-related key 
figures 
                                         Three         Three        Twelve 
                                       months to     months to     months to 
                                       31 Mar 14     31 Mar 13     31 Dec 13 
Earnings per share     EUR                  (0.01)       (0.09)         (0.48) 
Equity per share(1)    EUR                   -0.09         1.00          -0.19 
Development of share price at 
 London Stock Exchange 
Average trading 
 price(2)              EUR                    0.06         0.53           0.12 
 GBP                                          0.05         0.45           0.10 
Lowest trading 
 price(2)              EUR                    0.04         0.21           0.30 
 GBP                                          0.03         0.18           0.30 
Highest trading 
 price(2)              EUR                    0.08         1.33           1.34 
 GBP                                          0.07         1.14           1.14 
Trading price at the 
 end of the 
 period(3)             EUR                    0.04         0.25           0.08 
 GBP                                          0.04         0.21           0.07 
Change during the period                   -45.0 %      -79.7 %        -93.2 % 
Price-earnings ratio                          neg.         neg.           neg. 
Market capitalization 
 at the end of the 
 period(4)             EUR '000             84,928       66,821        159,759 
 GBP '000                                   70,338       56,504        133,622 
Development in trading volume 
Trading volume         1000 shares          87,344       42,435        776,597 
In relation to weighted average 
 number of shares                            4.6 %       15.6 %         54.2 % 
Development of share price at OMX 
 Helsinki 
Average trading price  EUR                    0.06         0.63           0.11 
Lowest trading price   EUR                    0.04         0.22           0.03 
Highest trading price  EUR                    0.08         1.39           1.39 
Trading price at the 
 end of the period     EUR                    0.04         0.23           0.08 
Change during the period                   -42.8 %      -81.7 %        -93.9 % 
Price-earnings ratio                          neg.         neg.           neg. 
Market capitalization 
 at the end of the 
 period                EUR '000             82,918       61,814        145,059 
Development in trading volume 
Trading volume         1000 shares         273,786      113,082      3,086,423 
In relation to weighted average 
 number of shares                           14.4 %       41.5 %        215.6 % 
Adjusted average number of shares    1,906,167,480  272,309,640  1,431,677,258 
Fully diluted average number of 
 shares                              1,903,899,480  271,205,640  1,530,295,193 
Number of shares at the end of the 
 period                              1,906,167,480  272,309,640  1,906,167,480 
 
   (1) The funds entered into share issue reserve are not included in the 
calculation. 
 
   (2) Trading price is calculated on the average of EUR/GBP exchange rates 
published by the European Central Bank during the period. 
 
   (3) Trading price is calculated on the EUR/GBP exchange rate published 
by the European Central Bank at the end of the period. 
 
   (4) Market capitalization is calculated on the EUR/GBP exchange rate 
published by the European Central Bank at the end of the period. 
 
 
 
 
Employee-related key figures 
                                            Three       Three       Twelve 
                                           months to   months to   months to 
                                           31 Mar 14   31 Mar 13   31 Dec 13 
Wages and salaries             EUR '000        5,092       4,204      23,274 
Average number of employees                      523         586         603 
Number of employees at the 
 end of the period                               516         583         549 
 
 
 
 
Other figures 
                                           Three       Three       Twelve 
                                          months to   months to   months to 
                                          31 Mar 14   31 Mar 13   31 Dec 13 
Share options outstanding at 
 the end of the period                            -  16,289,000   5,958,837 
Number of shares to be issued 
 against the outstanding share options            -  16,289,000   5,958,837 
Rights to vote of shares to be issued 
 against the outstanding share options            -       0.8 %       2.1 % 
 
 
 
 
Talvivaara Mining Company Plc 
Key financial figures of the Group 
 
Return on equity          Profit (loss) for the period 
                          (Total equity at the beginning of period + Total equity 
                           at the end of period)/2 
 
Equity-to-assets ratio    Total equity 
                          Total assets 
 
Net interest-bearing      Interest-bearing debt - Cash and cash equivalent 
debt 
 
Debt-to-equity ratio      Net interest-bearing debt 
                          Total equity 
 
Return on investment      Profit (loss) for the period + Finance cost 
                          (Total equity at the beginning of period + Total equity 
                           at the end of period)/2 + 
                           (Borrowings at the beginning of period + Borrowings 
                           at the end of period)/2 
 
Share-related key 
figures 
Earnings per share        Profit (loss) attributable to equity holders of the 
                           Company 
                          Adjusted average number of shares 
 
Equity per share          Equity attributable to equity holders of the Company 
                          Adjusted average number of shares 
 
Price-earnings ratio      Trading price at the end of the period 
                          Earnings per share 
 
Market capitalization at  Number of shares at the end of the period * trading 
 the end of the period     price at the end of the 
                           period 
 
 
   Talvivaara Interim Report for January March 2014: 
http://hugin.info/136227/R/1789013/614835.pdf 
 
   This announcement is distributed by NASDAQ OMX Corporate Solutions on 
behalf of NASDAQ OMX Corporate Solutions clients. 
 
   The issuer of this announcement warrants that they are solely 
responsible for the content, accuracy and originality of the information 
contained therein. 
 
   Source: Talvivaaran Kaivososakeyhtiö Oyj via Globenewswire 
 
   HUG#1789013 
 
 
  http://www.talvivaara.com 
 

Talvivaara (LSE:TALV)
Historical Stock Chart
From Sep 2024 to Oct 2024 Click Here for more Talvivaara Charts.
Talvivaara (LSE:TALV)
Historical Stock Chart
From Oct 2023 to Oct 2024 Click Here for more Talvivaara Charts.