RNS Number:2174R
BHP Billiton PLC
23 October 2003


Date                 23 October 2003
Number               31/03


                         BHP BILLITON PRODUCTION REPORT
                    FOR THE QUARTER ENDED 30 SEPTEMBER 2003

BHP Billiton today released its production report for the quarter ended 30
September 2003.

  * Record quarterly Western Australian Iron Ore production of 22.0 million 
    tonnes and record quarterly despatches of 21.5 million tonnes (100 per cent 
    basis).

  * Record quarterly Aluminium production resulting from early commissioning of 
    the Mozal 2 expansion in Mozambique.

  * Copper production lower than June 2003 quarter due to processing of higher 
    grade ore during the June 2003 quarter
    at Escondida (Chile) and a lower quantity of ore milled at Antamina (Peru).

  * Escondida to return to its normal mine plan and production profile 
    commencing January 2004.

  * Richards Bay Minerals (South Africa) sales volumes materially lower than the
    June 2003 quarter due to significantly weaker market conditions.


  * Total Petroleum Products - Total production for the September 2003 quarter
    was 32 million barrels of oil equivalent, six per cent higher than the June
    2003 quarter and three per cent lower than the September 2002 quarter.

      * Oil and Condensate - Production for the September 2003 quarter was
        15.5 million barrels, 16 per cent lower than the 18.6 million barrels
        produced in the September 2002 quarter, mainly due to natural field
        decline in Laminaria (Australia), Bass Strait and Griffin (Australia).
        This was partly offset by increased production at Liverpool Bay (UK) and
        the Bruce and Keith fields (UK) due to scheduled maintenance shutdowns
        in the September 2002 quarter. Production was in line with the 15.6
        million barrels produced in the June 2003 quarter, reflecting natural
        field decline across the portfolio which was largely offset by increased
        condensate production from Bass Strait (Australia) as a result of
        increased gas demand.

      * Natural Gas - Production for the September 2003 quarter was 85.2
        billion cubic feet, 19 per cent higher than the 71.9 billion cubic feet
        produced in the September 2002 quarter due to the commissioning of
        Zamzama Phase 1, along with increased production at Liverpool Bay and
        the Bruce and Keith fields due to scheduled maintenance shutdowns in the
        September 2002 quarter. Production for the quarter was 17 per cent
        higher than the 72.9 billion cubic feet produced in the June 2003
        quarter. This was due to seasonally driven increased demand for Bass
        Strait natural gas plus increased production from Zamzama (Pakistan)
        following the successful commissioning of the Phase 1 project. This was
        partly offset by seasonally lower demand of Liverpool Bay gas.

  * Alumina - Production for the September 2003 quarter was 1.1 million
    tonnes, in line with both the September 2002 and June 2003 quarters. Higher
    production at Alumar (Brazil) following scheduled maintenance during the
    June 2003 quarter, was offset by lower production at Worsley (Australia),
    where stockpiled hydrate was processed in the June 2003 quarter.
  * Aluminium - Production for the September 2003 quarter was a record 282,000
    tonnes, compared with 268,000 tonnes in the September 2002 quarter and
    273,000 tonnes in the June 2003 quarter. The increase mainly reflects the
    ramp up of production from the Mozal 2 (Mozambique) expansion, which reached
    full commissioning in August 2003, seven months ahead of schedule. This was
    partly offset by lower production at Alumar (Brazil) following an electrical
    outage in July 2003.
  * Copper - Production for the September 2003 quarter was 214,500 tonnes, 16
    per cent higher than in the September 2002 quarter, reflecting additional
    production from the Escondida (Chile) Phase IV expansion, which commenced
    commercial production in October 2002. This was partly offset by processing
    a lower quantity of material at Antamina (Peru) while access to ore is
    restricted to the flanks of the deposit. This situation is likely to
    continue for the next six to nine months. Production was six per cent lower
    than the June 2003 quarter, mainly a result of higher head grades at
    Escondida during the June 2003 quarter.
  * Silver - Silver sales volumes of 6.7 million ounces from Cannington
    (Australia) during the quarter, was 28 and 20 per cent lower than the
    September 2002 and June 2003 quarters respectively. This primarily reflects
    timing of lead concentrate shipments containing payable silver.
  * Iron Ore - Record quarterly Western Australian production of 22.0 million
    tonnes (100 per cent basis) was 14 per cent higher than the September 2002
    quarter and eight per cent higher than the June 2003 quarter, a reflection
    of ongoing strong customer demand in all Asian markets, particularly China.
    A new quarterly despatch record of 21.5 million tonnes (100% basis) was also
    set in Western Australia during the September 2003 quarter. Total iron ore
    production for the September 2003 quarter was 20.9 million tonnes (BHP
    Billiton share), 12 and eight per cent higher than the September 2002 and
    June 2003 quarters, respectively.

  * Metallurgical Coal - Production for the September 2003 quarter of 9.1
    million tonnes was five per cent higher than the September 2002 quarter due
    to increased customer demand from Queensland Coal (Australia), and adverse
    roof conditions at Crinum mine (Australia) in the September 2002 quarter.
    This was partly offset by lower production at Illawarra Coal (Australia)
    following the closure of Tower Colliery in December 2002. Production was in
    line with the June 2003 quarter.
  * Manganese alloys - Production for the September 2003 quarter of 147,000
    tonnes was 16 per cent lower than the September 2002 quarter and 25 per cent
    lower than the June 2003 quarter. This was due to an electrical fault at the
    Metalloys facility in South Africa in August 2003, which resulted in
    operations being suspended for a period of 48 days.
  * EkatiTM Diamonds - Production of 1.55 million carats was 63 per cent
    higher than the September 2002 quarter, which reflects the processing of a
    pocket of high grade but lower quality material from the Koala pit, along
    with sustained benefits from the processing plant de-bottlenecking program.
    Production was also 19 per cent higher than the June 2003 quarter for the
    same reasons.

  * Titanium Minerals - Sales volumes at Richards Bay Minerals were materially
    lower than both the September 2002 and June 2003 quarters due to
    significantly weaker market conditions. (Note: Due to confidentiality
    agreements with joint venture partners, production figures for Richards Bay
    Minerals are not contained in this report.)
  * Energy Coal - Production for the September 2003 quarter was 21.2 million
    tonnes, compared with 19.3 million tonnes in the September 2002 quarter. The
    increase mainly reflects higher production at Mount Arthur North (Australia)
    where deliveries to both the export and domestic thermal coal markets are in
    accordance with the ramp up plan, higher production at Cerrejon Coal
    (Colombia) largely reflecting stronger demand from the European market and
    maintenance on two draglines at New Mexico Coal in the September 2002
    quarter. Export sales from Ingwe decreased by five per cent, to 38 per cent
    of total sales volumes during the September quarter. This reflects lower
    export tonnage availability from Koornfontein following a fatal accident at
    that mine and subsequent safety interventions during the September 2003
    quarter, and shipment timing.
  * Nickel - Production for the quarter of 20,600 tonnes was eight per cent
    higher than the September 2002 quarter mainly reflecting scheduled
    maintenance activities in the September 2002 quarter, along with benefits in
    the current quarter of processing enhancements arising from operating
    excellence initiatives at both Cerro Matoso (Colombia) and Yabulu
    (Australia). Production was in line with the June 2003 quarter, although
    sales were 18 per cent lower as a result of timing of shipments.
  * Ferrochrome - Production of 227,000 tonnes for the quarter was five per
    cent lower than the September 2002 quarter and 12 per cent lower than the
    June 2003 quarter. This reduction is mainly due to scheduled maintenance
    shut downs in the current quarter, coinciding with the high winter
    electricity tariff period in South Africa.


                                        ****

Further information on BHP Billiton can be found on our Internet site: http://
www.bhpbilliton.com

Australia                                                     United Kingdom
Andrew Nairn, Investor Relations                              Mark Lidiard, Investor & Media Relations
Tel: +61 3 9609 3952 Mobile: +61 408 313 259                  Tel: +44 20 7802 4156
email: Andrew.W.Nairn@bhpbilliton.com                         email: Mark.Lidiard@bhpbilliton.com

Tania Price, Media Relations                                  Ariane Gentil, Media Relations
Tel: +61 3 9609 3815 Mobile: +61 419 152 780                  Tel: +44 20 7802 4177
email: Tania.Price@bhpbilliton.com                            email: Ariane.Gentil@bhpbilliton.com

United States                                                 South Africa
Francis McAllister, Investor Relations                        Michael Campbell, Investor & Media Relations
Tel: +1 713 961 8625 Mobile: +1 713 480 3699                  Tel: +27 11 376 3360 Mobile: +27 82 458 2587
email: Francis.R.McAllister@bhpbilliton.com                   email: Michael.J.Campbell@bhpbilliton.com




BHP BILLITON PRODUCTION SUMMARY
                                                        QUARTER ENDED               QUARTER ENDED         % CHANGE
                                                                                                     SEP Q03   SEP Q03
                                                   SEPT       JUNE       SEPT       SEPT       SEPT      vs        vs
                                                   2002       2003       2003       2003       2002    SEP Q02   JUN Q03
PETROLEUM
   Crude oil & condensate        ('000 bbl)       18,550     15,635     15,512     15,512     18,550      -16%       -1%
   Natural gas                      (bcf)          71.86      72.91      85.19      85.19      71.86       19%       17%
   LPG                          ('000 tonnes)     208.96     205.57     199.33     199.33     208.96       -5%       -3%
   Ethane                       ('000 tonnes)      27.67      24.97      27.32      27.32      27.67       -1%        9%
   Total Petroleum Products     (million boe)         33         30         32         32         33       -3%        6%

ALUMINIUM
   Alumina                      ('000 tonnes)      1,031      1,060      1,053      1,053      1,031        2%       -1%
   Aluminium                    ('000 tonnes)        268        273        282        282        268        5%        3%

BASE METALS
   Copper                       ('000 tonnes)      184.5      229.2      214.5      214.5      184.5       16%       -6%
   Lead                           (tonnes)        63,243     59,389     59,364     59,364     63,243       -6%        0%
   Zinc                           (tonnes)        48,542     54,396     49,094     49,094     48,542        1%      -10%
   Gold                           (ounces)        55,153     25,752     29,170     29,170     55,153      -47%       13%
   Silver                       ('000 ounces)     11,260      9,643     10,596     10,596     11,260       -6%       10%
   Molybdenum                     (tonnes)           314        301        325        325        314        4%        8%

CARBON STEEL MATERIALS
   Iron ore                     ('000 tonnes)     18,628     19,420     20,922     20,922     18,628       12%        8%
   Metallurgical coal           ('000 tonnes)      8,650      9,026      9,099      9,099      8,650        5%        1%
   Manganese ores               ('000 tonnes)      1,095      1,058      1,153      1,153      1,095        5%        9%
   Manganese alloys             ('000 tonnes)        175        195        147        147        175      -16%      -25%
   Hot briquetted iron          ('000 tonnes)        333        458        496        496        333       49%        8%

DIAMONDS AND SPECIALTY PRODUCTS
   Diamonds                     ('000 carats)        954      1,300      1,552      1,552        954       63%       19%

ENERGY COAL
   Energy coal                  ('000 tonnes)     19,329     21,991     21,156     21,156     19,329        9%       -4%

STAINLESS STEEL MATERIALS
   Nickel                       ('000 tonnes)       19.1       21.0       20.6       20.6       19.1        8%       -2%
   Ferrochrome                  ('000 tonnes)        238        259        227        227        238       -5%      -12%

Throughout this report fgures in italics indicate adjustments made since the 
figure was previously reported.

BHP BILLITON ATTRIBUTABLE PRODUCTION
                                                                   QUARTER ENDED                          QUARTER ENDED
                              BHP Billiton        SEPT        DEC       MARCH       JUNE       SEPT      SEPT      SEPT
                                Interest          2002        2002      2003        2003       2003      2003      2002
PETROLEUM
Production
  Crude oil & condensate       (000 bbl)           18,550   16,398      15,310      15,635    15,512    15,512    18,550
  Natural gas                    (bcf)              71.86    69.41       66.99       72.91     85.19     85.19     71.86
  LPG                            ('000             208.96   167.97      160.62      205.57    199.33    199.33    208.96
                                tonnes)
  Ethane                         ('000              27.67    19.91       22.35       24.97     27.32     27.32     27.67
                                tonnes)
  Total Petroleum Products      (million               33       30          28          30        32        32        33
                                  boe)
ALUMINIUM
ALUMINA
Production ('000 tonnes)
  Worsley                         86%                 698      662         658         724       699       699       698
  Suriname                        45%                 221      213         222         223       227       227       221
  Alumar                          36%                 112      123         123         113       127       127       112
  Total                                             1,031      998       1,003       1,060     1,053     1,053     1,031

ALUMINIUM
Production ('000 tonnes)
  Hillside                        100%                135      134         133         132       135       135       135
  Bayside                         100%                 46       45          48          46        47        47        46
  Alumar                         46.3%                 44       44          45          45        31        31        44
  Valesul                        45.5%                 11       11          10          11        11        11        11
  Mozal                           47%                  32       32          31          39        58        58        32
  Total                                               268      266         267         273       282       282       268

BASE METALS (a)
COPPER
Payable metal in concentrate ('000 tonnes)
  Escondida (b)                  57.5%               68.4    105.6       118.5       126.6     115.9     115.9      68.4
  Tintaya (b)                     100%                  -        -           -           -         -         -         -
  Antamina                       33.8%               25.7     26.4        23.6        21.2      16.9      16.9      25.7
  Alumbrera (c)                   25%                11.1     13.4         9.9           -         -         -      11.1
  Highland Valley Copper         33.6%               14.9     14.3        13.2        13.8      14.1      14.1      14.9
  Selbaie                         100%                2.8      2.1         1.7         1.8       1.6       1.6       2.8
  Total                                             122.9    161.8       166.9       163.4     148.5     148.5     122.9

Cathode ('000 tonnes)
  Escondida                      57.5%               17.9     19.1        20.4        21.1      21.4      21.4      17.9
  Cerro Colorado                  100%               32.5     33.1        32.5        33.0      33.1      33.1      32.5
  Tintaya (b)                     100%                8.4      8.9         9.0         9.1       9.0       9.0       8.4
  Pinto Valley                    100%                2.8      2.7         2.5         2.6       2.5       2.5       2.8
  Total                                              61.6     63.8        64.4        65.8      66.0      66.0      61.6

LEAD
Payable metal in concentrate (tonnes)
  Cannington                      100%             61,676   57,651      58,711      59,389    59,364    59,364    61,676
  Pering (d)                      100%              1,567      694         354           -         -         -     1,567
  Total                                            63,243   58,345      59,065      59,389    59,364    59,364    63,243

  Refer footnotes on page 4.

BASE METALS (continued)
ZINC
Payable metal in concentate
(tonnes)
  Cannington                      100%             15,182   14,721      15,480      18,479    14,850    14,850    15,182
  Antamina                       33.8%             18,189   15,424      20,519      28,553    27,933    27,933    18,189
  Selbaie                         100%              9,840    6,540       6,421       7,364     6,311     6,311     9,840
  Pering (d)                      100%              5,331    7,430       4,335           -         -         -     5,331
  Total                                            48,542   44,115      46,755      54,396    49,094    49,094    48,542

GOLD
Payable metal in concentrate (ounces)
  Escondida (b)                  57.5%             10,074   15,936      17,458      20,664    25,016    25,016    10,074
  Tintaya (b)                     100%                  -        -           -           -         -         -         -
  Alumbrera (c)                    25%             39,279   46,940      35,084           -         -         -    39,279
  Selbaie                         100%              4,486    5,069       4,146       4,081     3,129     3,129     4,486
  Highland Valley Copper         33.6%              1,314    1,230       1,114       1,007     1,025     1,025     1,314
  Total                                            55,153   69,175      57,802      25,752    29,170    29,170    55,153

SILVER
Payable metal in concentrate ('000 ounces)
  Cannington                      100%              9,612    8,326       8,773       8,161     9,177     9,177     9,612
  Escondida                      57.5%                304      387         471         538       561       561       304
  Antamina                       33.8%                536      557         617         517       435       435       536
  Alumbrera (c)                  25.0%                 53       72          75           -         -         -        53
  Highland Valley Copper         33.6%                162      159         140         143       160       160       162
  Selbaie                         100%                593      369         279         284       263       263       593
  Total                                            11,260    9,870      10,355       9,643    10,596    10,596    11,260

MOLYBDENUM
Payable metal in concentrate (tonnes)
  Antamina                       33.8%                 94      115         113          21        25        25        94
  Highland Valley Copper         33.6%                220      250         260         280       300       300       220
  Total                                               314      365         373         301       325       325       314

CARBON STEEL MATERIALS
IRON ORE
Production ('000 tonnes)
  Mt Newman Joint Venture          85%              5,486    5,287       4,964       6,221     6,639     6,639     5,486
  Goldsworthy Joint Venture (e)    85%              1,891    1,808       1,497       1,497     1,633     1,633     1,891
  Area C Joint Venture (f)         85%                  -        -           -          19       341       341         -
  Yandi Joint Venture              85%              7,796    8,187       7,452       8,353     8,679     8,679     7,796
  Jimblebar                       100%              1,433    1,186       1,371       1,428     1,622     1,622     1,433
  Samarco                          50%              2,022    1,979       1,953       1,902     2,008     2,008     2,022
  Total                                            18,628   18,447      17,237      19,420    20,922    20,922    18,628

METALLURGICAL COAL (g)
Production ('000 tonnes)
  BMA                              50%              4,652    5,032       5,838       5,769     5,591     5,591     4,652
  BHP Mitsui Coal (h)              80%              1,863    1,472       1,200       2,033     1,926     1,926     1,863
  Illawarra                       100%              2,135    1,886       1,518       1,224     1,582     1,582     2,135
  Total                                             8,650    8,390       8,556       9,026     9,099     9,099     8,650

  Refer footnotes on page 4.

CARBON STEEL MATERIALS (cont'd)
MANGANESE ORES
Saleable production ('000 tonnes)
  South Africa (i)                 60%                581      560         534         574       600       600       581
  Australia (i)                    60%                514      499         356         484       553       553       514
  Total                                             1,095    1,059         890       1,058     1,153     1,153     1,095

MANGANESE ALLOYS
Saleable production ('000 tonnes)
  South Africa (i)                 60%                124      125         117         137        93        93       124
  Australia (i)                    60%                 51       65          60          58        54        54        51
  Total                                               175      190         177         195       147       147       175

HOT BRIQUETTED IRON
Production ('000 tonnes)
  BoodarieTM Iron                 100%                333      414         465         458       496       496       333

DIAMONDS AND SPECIALTY PRODUCTS
DIAMONDS
Production ('000 carats)
  EkatiTM                          80%                954    1,071       1,015       1,300     1,552     1,552       954

ENERGY COAL
Production ('000 tonnes)
  South Africa                    100%             13,838   13,333      13,256      13,812    13,782    13,782    13,838
  USA                             100%              2,800    4,339       3,147       3,877     3,582     3,582     2,800
  Australia                       100%              1,244    1,234       1,922       2,041     1,756     1,756     1,244
  Indonesia (j)                    80%                216       29          28           -         -         -       216
  Colombia                         33%              1,231    1,713       1,382       2,261     2,036     2,036     1,231
  Total                                            19,329   20,648      19,735      21,991    21,156    21,156    19,329

STAINLESS STEEL MATERIALS
NICKEL
Production ('000 tonnes)
  CMSA                           99.8%               11.7     11.9        11.1        12.2      12.4      12.4      11.7
  Yabulu                          100%                7.4      7.5         7.5         8.8       8.2       8.2       7.4
  Total                                              19.1     19.4        18.6        21.0      20.6      20.6      19.1

FERROCHROME
Saleable production ('000 tonnes)
  South Africa (i)                 60%                238      230         263         259       227       227       238

  (a) Metal production is reported on the basis of payable metal.
  (b) Sulphide production at Escondida and Tintaya was temporarily reduced in 
      November 2001 and January 2002 respectively due to weak market conditions.
      Sulphide mining operations recommenced at Tintaya during August 2003.
      The Escondida Phase IV expansion was commissioned in October 2002.
      Commercial production of copper cathode commenced at Tintaya in June 2002.
  (c) BHP Billiton announced the sale of its interest in Alumbrera in March 
      2003. The sale transaction reached closure in June 2003.
  (d) Production ceased, ahead of mine closure, in February 2003.
  (e) Includes bulk sample production from Area C prior to May 2003.
  (f) Production commenced in May 2003.
  (g) Coal production is reported on the basis of saleable product. Production 
      figures include some thermal coal.
  (h) Shown on 100% basis before 20% outside equity interest.
  (i) Shown on 100% basis. BHP Billiton interest in saleable production is 60%.
  (j) Production shown on 86.5% basis after allowing for Indonesian state owned 
      corporation's 13.5% share of production.
      Mining operations at Petangis ceased in October 2002.

PRODUCTION AND SHIPMENT REPORT
                                                              QUARTER ENDED                            QUARTER ENDED
                                            SEPT       DEC       MARCH       JUNE        SEPT        SEPT        SEPT
                                            2002       2002       2003       2003        2003        2003        2002
PETROLEUM
BHP Billiton attributable production unless
otherwise stated.

CRUDE OIL & CONDENSATE ('000 barrels)
   Bass Strait                              6,799      5,799      5,391       5,643       5,872       5,872       6,799
   North West Shelf - condensate            1,602      1,510      1,566       1,560       1,491       1,491       1,602
   North West Shelf - Wanaea/Cossack        1,876      1,655      1,679       1,606       1,604       1,604       1,876
   Laminaria                                2,914      1,869      1,419       1,161       1,151       1,151       2,914
   Griffin                                  1,281      1,089        831         708         742         742       1,281
   Pakistan                                    18         17         16          14          53          53          18
   Typhoon/Boris (a)                        1,233        654        852       1,430       1,214       1,214       1,233
   Americas                                   718        652        816         715         608         608         718
   Liverpool Bay                            1,838      2,463      2,174       2,344       2,324       2,324       1,838
   Bruce/Keith                                271        690        566         454         453         453         271
   Total                                   18,550     16,398     15,310      15,635      15,512      15,512      18,550

NATURAL GAS (billion cubic feet)
   Bass Strait                              33.07      21.07      17.51       25.37       33.04       33.04       33.07
   North West Shelf -                        3.62       3.82       3.81        4.07        3.99        3.99        3.62
   Domestic
   North West Shelf - LNG                   16.55      14.93      15.11       15.41       16.74       16.74       16.55
   Griffin                                   0.95       1.03       0.81        0.81        0.96        0.96        0.95
   Pakistan                                  2.83       2.76       2.57        2.33        7.86        7.86        2.83
   Typhoon/Boris (a)                         1.38       0.71       2.03        2.03        1.58        1.58        1.38
   Americas                                  3.91       3.80       3.34        3.42        3.25        3.25        3.91
   Bruce                                     4.59      10.55      10.04        8.17        8.77        8.77        4.59
   Keith                                     0.07       0.15       0.15        0.14        0.11        0.11        0.07
   Liverpool Bay                             4.89      10.59      11.62       11.16        8.89        8.89        4.89
   Total                                    71.86      69.41      66.99       72.91       85.19       85.19       71.86

LPG ('000 tonnes)
   Bass Strait                             149.66     115.23     111.74      135.18      150.19      150.19      149.66
   North West Shelf                         36.32      31.04      32.67       32.39       34.21       34.21       36.32
   Bruce                                    22.45      20.47      15.10       37.24       14.12       14.12       22.45
   Keith                                     0.53       1.23       1.11        0.76        0.81        0.81        0.53
   Total                                   208.96     167.97     160.62      205.57      199.33      199.33      208.96

ETHANE ('000 tonnes)                        27.67      19.91      22.35       24.97       27.32       27.32       27.67

TOTAL PETROLEUM PRODUCTS                     33.1       30.0       28.4        30.3        32.1        32.1        33.1
(million barrels of oil equivalent)(b)
   (a) Boris commenced production in February 2003.
   (b) Total barrels of oil equivalent (boe) conversions based on the
   following:
       6000 scf of natural gas equals 1 boe
       1 tonne of LPG equals 11.6 boe
       1 tonne of ethane equals 4.4667 boe

PRODUCTION AND SHIPMENT REPORT
                                                              QUARTER ENDED                           QUARTER ENDED
                                             SEPT       DEC       MARCH       JUNE       SEPT       SEPT        SEPT
                                             2002       2002       2003       2003       2003       2003        2002
ALUMINIUM
BHP Billiton attributable production and 
sales unless otherwise stated.
('000 tonnes)

ALUMINA
   Production
   Worsley, Australia                          698        662        658        724        699         699         698
   Paranam, Suriname                           221        213        222        223        227         227         221
   Alumar, Brazil                              112        123        123        113        127         127         112
   Total                                     1,031        998      1,003      1,060      1,053       1,053       1,031

   Sales
   Worsley, Australia                          758        606        751        636        697         697         758
   Paranam, Suriname                           253        201        243        228        221         221         253
   Alumar, Brazil                              130        125        124        107        120         120         130
   Total                                     1,141        932      1,118        971      1,038       1,038       1,141


ALUMINIUM
   Production
   Hillside, South Africa                      135        134        133        132        135         135         135
   Bayside, South Africa                        46         45         48         46         47          47          46
   Alumar, Brazil                               44         44         45         45         31          31          44
   Valesul, Brazil                              11         11         10         11         11          11          11
   Mozal, Mozambique                            32         32         31         39         58          58          32
   Total                                       268        266        267        273        282         282         268

   Sales
   Hillside, South Africa                      124        135        133        143        134         134         124
   Bayside, South Africa                        47         45         48         48         54          54          47
   Alumar, Brazil                               38         52         38         51         38          38          38
   Valesul, Brazil                               9         12          9         10         11          11           9
   Mozal, Mozambique                            27         35         33         41         61          61          27
   Total                                       245        279        261        293        298         298         245


PRODUCTION AND SHIPMENT REPORT
                                                               QUARTER ENDED                            QUARTER ENDED
                                             SEPT       DEC       MARCH       JUNE        SEPT        SEPT        SEPT
                                             2002       2002       2003       2003        2003        2003        2002
BASE METALS
BHP Billiton attributable production and 
sales unless otherwise stated. Metals 
production is payable metal unless
otherwise stated.

Escondida, Chile (a)
   Material mined (100%)  ('000 tonnes)     74,671     74,303     73,466      74,665      69,342      69,342      74,671
   Sulphide ore milled    ('000 tonnes)     10,142     14,632     16,744      16,416      18,888      18,888      10,142
   (100%)
   Average copper grade   (%)                1.45%      1.59%      1.49%       1.62%       1.33%       1.33%       1.45%
   Production ex Mill     ('000 tonnes)      125.6      191.8      210.8       230.9       208.2       208.2       125.6
   (100%)

   Production
   Payable copper         ('000 tonnes)       68.4      105.6      118.5       126.6       115.9       115.9        68.4
   Payable gold           (fine ounces)     10,074     15,936     17,458      20,664      25,016      25,016      10,074
   concentrate
   Copper cathode (SXEW)  ('000 tonnes)       17.9       19.1       20.4        21.1        21.4        21.4        17.9
   Payable silver         ('000 ounces)        304        387        471         538         561         561         304
   concentrate

   Sales
   Payable copper         ('000 tonnes)       77.0      104.8      113.5       128.9       116.2       116.2        77.0
   Payable gold           (fine ounces)     11,689     16,709     17,166      20,138      25,335      25,335      11,689
   concentrate
   Copper cathode (SXEW)  ('000 tonnes)       18.1       19.5       19.3        20.3        18.1        18.1        18.1
   Payable silver         ('000 ounces)        269        400        484         584         574         574         269
   concentrate

   (a) Includes production from the Escondida Phase IV expansion which 
       commissioned in October 2002.

Tintaya, Peru (a) (b)
   Material mined         ('000 tonnes)          -          -          -           -       4,151       4,151           -
   Ore milled             ('000 tonnes)          -          -          -           -           -           -           -
   Average copper grade   (%)                    -          -          -           -           -           -           -

   Production
   Payable copper         ('000 tonnes)          -          -          -           -           -           -           -
   Payable gold           (fine ounces)          -          -          -           -           -           -           -
   concentrate
   Copper cathode (SXEW)  ('000 tonnes)        8.4        8.9        9.0         9.1         9.0         9.0         8.4

   Sales
   Payable copper         ('000 tonnes)          -          -          -           -           -           -           -
   Payable gold           (fine ounces)          -          -          -           -           -           -           -
   concentrate
   Copper cathode (SXEW)  ('000 tonnes)        8.0        8.7        8.7         9.5         8.9         8.9         8.0

   (a) Sulphide production at Tintaya was temporarily suspended in January 2002 
       due to weak market conditions.
       Sulphide mining operations recommenced during August 2003.
   (b) Commercial production of copper cathode commenced in June 2002.

Cerro Colorado, Chile
   Material mined         ('000 tonnes)     17,963     15,027     16,564      16,458      20,332      20,332      17,963
   Ore milled             ('000 tonnes)      3,759      3,942      3,916       4,130       4,346       4,346       3,759
   Average copper grade   (%)                0.97%      1.03%      1.00%       0.96%       0.99%       0.99%       0.97%

   Production
   Copper cathode         ('000 tonnes)       32.5       33.1       32.5        33.0        33.1        33.1        32.5

   Sales
   Copper cathode         ('000 tonnes)       27.2       29.1       39.3        31.5        28.9        28.9        27.2

Antamina, Peru
   Material mined (100%)  ('000 tonnes)     30,235     25,797     25,290      28,353      30,174      30,174      30,235
   Ore milled (100%)      ('000 tonnes)      6,794      6,395      6,424       6,697       6,018       6,018       6,794
   Average head grades
   - Copper               (%)                1.33%      1.41%      1.32%       1.09%       1.17%       1.17%       1.33%
   - Zinc                 (%)                1.28%      1.15%      1.54%       1.97%       2.17%       2.17%       1.28%

   Production
   Payable copper         ('000 tonnes)       25.7       26.4       23.6        21.2        16.9        16.9        25.7
   Payable zinc           (tonnes)          18,189     15,424     20,519      28,553      27,933      27,933      18,189
   Payable silver         ('000 ounces)        536        557        617         517         435         435         536
   Payable molybdenum     ('000 tonnes)       0.09       0.11       0.11        0.02        0.03        0.03        0.09

   Sales
   Payable copper         ('000 tonnes)       30.6       25.8       22.4        21.2        18.6        18.6        30.6
   Payable zinc           (tonnes)          19,184     14,407     15,400      31,034      26,781      26,781      19,184
   Payable silver         ('000 ounces)        590        530        575         435         420         420         590
   Payable molybdenum     ('000 tonnes)       0.02       0.17       0.10        0.10        0.01        0.01        0.02

Alumbrera, Argentina (a)
   Material mined (100%)  ('000 tonnes)     29,356     28,730     26,400           -           -           -      29,356
   Ore milled (100%)      ('000 tonnes)      8,034      8,703      8,376           -           -           -       8,034
   Average head grades
   - Copper               (%)                0.62%      0.69%      0.54%           -           -           -       0.62%
   - Gold                 (g/t)                0.8        0.9        0.7           -           -           -         0.8

   Production
   Payable copper         ('000 tonnes)       11.1       13.4        9.9           -           -           -        11.1
   Payable gold           (fine ounces)     35,935     42,594     30,730           -           -           -      35,935
   Payable gold - dore    (fine ounces)      3,344      4,346      4,354           -           -           -       3,344
   Payable silver         ('000 ounces)         53         72         75           -           -           -          53

   Sales
   Payable copper         ('000 tonnes)       10.3       13.3       10.8           -           -           -        10.3
   Payable gold           (fine ounces)     33,957     42,381     33,438           -           -           -      33,957
   Payable gold - dore    (fine ounces)      3,082      4,409      4,159           -           -           -       3,082
   Payable silver         ('000 ounces)         53         72         75           -           -           -          53

   (a) BHP Billiton announced the sale of its interest in Alumbrera in
   March 2003.
   Participation in the joint venture ceased on 2nd April 2003.

Highland Valley, Canada
   Material mined (100%)  ('000 tonnes)     20,455     18,682     16,642      18,186      16,892      16,892      20,455
   Ore milled (100%)      ('000 tonnes)     12,941     12,924     11,602      12,565      12,261      12,261      12,941
   Average copper grade   (%)                0.40%      0.39%      0.40%       0.39%       0.40%       0.40%       0.40%

   Production
   Payable copper         ('000 tonnes)       14.9       14.3       13.2        13.8        14.1        14.1        14.9
   Payable molybdenum     ('000 tonnes)       0.22       0.25       0.26        0.28        0.30        0.30        0.22
   Payable silver         ('000 ounces)        162        159        140         143         160         160         162
   Payable gold           (fine ounces)      1,314      1,230      1,114       1,007       1,025       1,025       1,314
   concentrate

   Sales
   Payable copper         ('000 tonnes)       14.4       17.5       10.0        10.7        16.7        16.7        14.4
   Payable molybdenum     ('000 tonnes)       0.19       0.22       0.26        0.23        0.28        0.28        0.19
   Payable silver         ('000 ounces)        153        189        106         116         177         177         153
   Payable gold           (fine ounces)      1,240      1,644        843         793       1,505       1,505       1,240
   concentrate

Cannington, Australia
   Material mined         ('000 tonnes)        631        573        601         588         637         637         631
   Ore milled             ('000 tonnes)        599        564        589         560         589         589         599
   Average head grades
   - Silver               (g/t)                564        535        550         525         564         564         564
   - Lead                 (%)                11.7%      11.9%      11.8%       12.1%       11.5%       11.5%       11.7%
   - Zinc                 (%)                 4.3%       4.3%       4.3%        5.3%        4.0%        4.0%        4.3%

   Production
   Payable silver         ('000 ounces)      9,612      8,326      8,773       8,161       9,177       9,177       9,612
   Payable lead           (tonnes)          61,676     57,651     58,711      59,389      59,364      59,364      61,676
   Payable zinc           (tonnes)          15,182     14,721     15,480      18,479      14,850      14,850      15,182

   Sales
   Payable silver         ('000 ounces)      9,401      9,081      8,956       8,412       6,765       6,765       9,401
   Payable lead           (tonnes)          59,856     62,735     57,961      58,742      43,953      43,953      59,856
   Payable zinc           (tonnes)          12,077     14,849     18,056      13,288      16,223      16,223      12,077

Selbaie, Canada
   Ore milled             ('000 tonnes)      1,049        999        919         982         858         858       1,049
   Average head grades
   - Zinc                 (%)                1.37%      1.09%      1.11%       1.18%       1.13%       1.13%       1.37%
   - Copper               (%)                0.33%      0.28%      0.25%       0.24%       0.25%       0.25%       0.33%
   - Gold                 (g/t)               0.23       0.25       0.23        0.23        0.22        0.22        0.23
   - Silver               (g/t)              35.10      22.75      22.15       20.62       22.38       22.38       35.10

   Production
   Payable zinc           (tonnes)           9,840      6,540      6,421       7,364       6,311       6,311       9,840
   Payable copper         (tonnes)           2,789      2,111      1,654       1,768       1,606       1,606       2,789
   Payable gold           (ounces)           4,486      5,069      4,146       4,081       3,129       3,129       4,486
   concentrate
   Payable silver         ('000 ounces)        593        369        279         284         263         263         593

   Sales
   Payable zinc           (tonnes)           9,861      7,245      6,649       6,812       6,209       6,209       9,861
   Payable copper         (tonnes)           2,823      2,107      2,751       1,612       1,918       1,918       2,823
   Payable gold           (ounces)           5,932      3,082      5,508       4,280       4,384       4,384       5,932
   concentrate
   Payable silver         ('000 ounces)        527        478        444         355         292         292         527

Pering, South Africa (a)
   Ore milled             ('000 tonnes)        320        288        151           -           -           -         320
   Average head grades
   - Zinc                 (%)                2.21%      3.34%      3.47%           -           -           -       2.21%
   - Lead                 (%)                0.66%      0.40%      0.33%           -           -           -       0.66%
   Production
   Payable zinc           (tonnes)           5,331      7,430      4,335           -           -           -       5,331
   Payable lead           (tonnes)           1,567        694        354           -           -           -       1,567

   Sales
   Payable zinc           (tonnes)           3,701      6,179      5,343       4,466           -           -       3,701
   Payable lead           (tonnes)           1,367      1,327        995         117           -           -       1,367

   (a) Production ceased, ahead of mine closure, in February 2003.

Pinto Valley, USA
   Production
   Copper cathode (SXEW)  ('000 tonnes)        2.8        2.7        2.5         2.6         2.5         2.5         2.8

   Sales
   Copper cathode (SXEW)  ('000 tonnes)        2.7        2.6        2.6         2.6         2.5         2.5         2.7

PRODUCTION AND SHIPMENT REPORT
                                                               QUARTER ENDED                            QUARTER ENDED
                                            SEPT       DEC        MARCH       JUNE        SEPT        SEPT        SEPT
                                            2002       2002       2003        2003        2003        2003        2002
CARBON STEEL MATERIALS
BHP Billiton attributable production and 
sales unless otherwise stated.
('000 tonnes)

IRON ORE (a)
Pilbara, Australia
   Production
   Mt Newman Joint                          5,486      5,287       4,964       6,221       6,639       6,639       5,486
   Venture
   Goldsworthy Joint Venture (b)            1,891      1,808       1,497       1,497       1,633       1,633       1,891
   Area C Joint Venture                         -          -           -          19         341         341           -
   (c)
   Yandi Joint Venture                      7,796      8,187       7,452       8,353       8,679       8,679       7,796
   Jimblebar                                1,433      1,186       1,371       1,428       1,622       1,622       1,433
   Total (BHP Billiton                     16,606     16,468      15,284      17,518      18,914      18,914      16,606
   share)
   Total production                        19,284     19,165      17,739      20,359      21,965      21,965      19,284
   (100%)

   Shipments
   Lump                                     4,335      4,290       4,352       4,193       4,898       4,898       4,335
   Fines                                   11,842     13,896      12,144      13,187      13,334      13,334      11,842
   Total (BHP Billiton                     16,177     18,186      16,496      17,380      18,232      18,232      16,177
   share)
   Total shipments (100%)                  19,033     21,396      19,407      20,448      21,450      21,450      19,033

   (a) Iron ore production and shipments are reported on a wet tonnes basis.
   (b) Includes bulk sample production from Area C prior to May 2003.
   (c) Mining commenced in May 2003.

Samarco, Brazil
   Production                               2,022      1,979       1,953       1,902       2,008       2,008       2,022

   Shipments                                2,034      2,004       2,049       2,153       2,013       2,013       2,034

METALLURGICAL COAL (a)
Queensland, Australia
   Production
   BMA
   Blackwater                               1,633      1,603       1,668       1,937       1,578       1,578       1,633
   Goonyella                                  734        812       1,191       1,075         994         994         734
   Peak Downs                                 789        757       1,009       1,076       1,004       1,004         789
   Saraji                                     427        629         599         666         747         747         427
   Norwich Park                               573        451         610         527         524         524         573
   South Blackwater                             -          -           -           -           -           -           -
   Gregory Joint Venture                      496        780         761         488         744         744         496
   BMA total                                4,652      5,032       5,838       5,769       5,591       5,591       4,652

   BHP Mitsui Coal (b)
   Riverside                                  927        400         300       1,014         969         969         927
   South Walker Creek                         936      1,072         900       1,019         957         957         936
   BHP Mitsui Coal total                    1,863      1,472       1,200       2,033       1,926       1,926       1,863
   Queensland total                         6,515      6,504       7,038       7,802       7,517       7,517       6,515

   Shipments
   Coking coal                              4,165      4,034       4,707       4,395       4,838       4,838       4,165
   Weak coking coal                         1,739      1,503       1,569       1,525       1,617       1,617       1,739
   Thermal coal                             1,022        800         852         943         801         801       1,022
   Total                                    6,926      6,337       7,128       6,863       7,256       7,256       6,926

   (a) Coal production is reported on the basis of saleable product. Production 
       figures include some thermal coal.
   (b) BHP Mitsui Coal production shown on 100% basis before 20% outside equity
       interest.

Illawarra, Australia
   Production                               2,135      1,886       1,518       1,224       1,582       1,582       2,135

   Shipments
   Coking coal                              1,515      1,900       1,611       1,571       1,513       1,513       1,515
   Thermal coal                               134         95         242         179          91          91         134
   Total                                    1,649      1,995       1,853       1,750       1,604       1,604       1,649

MANGANESE ORES
South Africa
   Saleable production(a)                     581        560         534         574         600         600         581
   
   (a) Shown on 100% basis, BHP Billiton interest in saleable production is 60%.

Australia
   Saleable production(a)                     514        499         356         484         553         553         514

   (a) Shown on 100% basis, BHP Billiton interest in saleable production is 60%.

MANGANESE ALLOYS
South Africa
   Saleable production(a)                     124        125         117         137          93          93         124

   (a) Shown on 100% basis, BHP Billiton interest in saleable production is 60%.

Australia
   Saleable production(a)                      51         65          60          58          54          54          51
 
   (a) Shown on 100% basis, BHP Billiton interest in saleable production is 60%.

HOT BRIQUETTED IRON
BoodarieTM Iron,
Australia
   Production                                 333        414         465         458         496         496         333

   Shipments                                  202        464         416         487         435         435         202

PRODUCTION AND SHIPMENT REPORT
                                                              QUARTER ENDED                           QUARTER ENDED
                                             SEPT       DEC       MARCH       JUNE       SEPT       SEPT        SEPT
                                             2002       2002       2003       2003       2003       2003        2002
DIAMONDS AND SPECIALTY PRODUCTS
BHP Billiton attributable production and 
sales unless otherwise stated.

DIAMONDS
EkatiTM, Canada
   Ore Processed (100%)   ('000 tonnes)        996      1,045      1,087      1,182      1,064       1,064         996

   Production             ('000 carats)        954      1,071      1,015      1,300      1,552       1,552         954

PRODUCTION AND SHIPMENT REPORT
                                                               QUARTER ENDED                           QUARTER ENDED
                                             SEPT       DEC       MARCH       JUNE       SEPT        SEPT        SEPT
                                             2002       2002       2003       2003       2003        2003        2002
ENERGY COAL
BHP Billiton attributable production and 
sales unless otherwise stated.
('000 tonnes)

Ingwe, South Africa
   Production                               13,838     13,333     13,256     13,812      13,782      13,782      13,838

   Sales
   Export                                    5,648      6,609      5,696      6,339       5,274       5,274       5,648
   Local utility                             7,836      7,263      7,160      7,926       8,215       8,215       7,836
   Inland                                      471        412        340        337         338         338         471
   Total                                    13,955     14,284     13,196     14,602      13,827      13,827      13,955

New Mexico, USA
   Production
   Navajo Coal                               1,602      2,154      1,797      2,497       2,262       2,262       1,602
   San Juan Coal (a)                         1,198      2,185      1,350      1,380       1,320       1,320       1,198
   Total                                     2,800      4,339      3,147      3,877       3,582       3,582       2,800

   Sales - local utility                     3,546      3,348      3,316      3,643       3,713       3,713       3,546

   (a) Includes production from longwall operations which commenced at San Juan 
       in October 2002.

Hunter Valley, Australia
   Production                                1,244      1,234      1,922      2,041       1,756       1,756       1,244

   Sales
   Export                                      783        881      1,036      1,301         952         952         783
   Inland                                      366        276        704      1,285         873         873         366
   Total                                     1,149      1,157      1,740      2,586       1,825       1,825       1,149

Kalimantan, Indonesia
   Production (a)
   Petangis (b)                                216         29         28          -           -           -         216
   Total                                       216         29         28          -           -           -         216

   Sales - export                              189         49         56          -           -           -         189

   (a) Reported on 86.5% basis after allowing for the Indonesian state-owned 
       corporation's 13.5% share of all production.
   (b) Mining operations at Petangis ceased in October 2002.

Cerrejon Coal, Colombia
   Production                                1,231      1,713      1,382      2,261       2,036       2,036       1,231

   Sales - export                            1,246      1,851      1,971      2,247       1,966       1,966       1,246

PRODUCTION AND SHIPMENT REPORT
                                                               QUARTER ENDED                            QUARTER ENDED
                                             SEPT       DEC       MARCH       JUNE        SEPT        SEPT        SEPT
                                             2002       2002       2003       2003        2003        2003        2002
STAINLESS STEEL MATERIALS
BHP Billiton attributable production and 
sales unless otherwise stated.
('000 tonnes)

NICKEL
CMSA, Colombia
   Production                                 11.7       11.9       11.1        12.2        12.4        12.4        11.7

   Sales                                      10.5       12.8       10.3        13.5        11.1        11.1        10.5

Yabulu, Australia
   Production
   Nickel                                      7.4        7.5        7.5         8.8         8.2         8.2         7.4
   Cobalt                                      0.5        0.5        0.4         0.5         0.4         0.4         0.5

   Sales
   Nickel                                      7.1        8.3        8.1         9.5         7.8         7.8         7.1
   Cobalt                                      0.5        0.5        0.5         0.5         0.4         0.4         0.5


FERROCHROME
South Africa
   Saleable production(a)                      238        230        263         259         227         227         238
 
   (a) Shown on 100% basis, BHP Billiton interest in saleable production is 60%.


BHP Billiton Limited ABN 49 004 028 077                     BHP Billiton Plc Registration number 3196209
Registered in Australia                                     Registered in England and Wales
Registered Office: Level 27, 180 Lonsdale Street Melbourne  Registered Office: Neathouse Place London SW1V 1BH United
Victoria 3000                                               Kingdom
Telephone +61 1300 554 757 Facsimile +61 3 9609 3015        Telephone +44 20 7802 4000 Facsimile +44 20 7802 4111

            The BHP Billiton Group is headquartered in Australia




                      This information is provided by RNS
            The company news service from the London Stock Exchange
END