Euro Manganese Inc. (TSX-V and ASX: EMN; OTCQX: EUMNF; Frankfurt:
E06) (the "Company" or "EMN") is pleased to announce it has awarded
the Engineering, Procurement, and Construction Management ("EPCM")
contract for its Chvaletice Manganese Project ("Chvaletice Project"
or the "Project") in the Czech Republic to Wood Australia Pty Ltd
("Wood").
The Company also provides an update on the
permit approval process for the Project.
EPCM Contract Award
The Company has selected Wood as its EPCM
partner following a rigorous selection process. Five high quality
bids were submitted by international EPCM firms in late 2022. Two
firms were shortlisted in early 2023 based on cost of service as
well as their proposed project schedule, technical and engineering
capability, EU experience, team skillset, and overall execution
strategy. The Company selected Wood as the preferred contractor in
April 2023 and has now concluded the contract negotiations and
received Board approval to award the contract to Wood.
The contract is cost reimbursable and is
structured in two phases (outlined below), with an approval stage
gate between each phase as well as after the gap analysis in Phase
1. Completion of Phase 1 is anticipated to take approximately 12
months, with a Final Investment Decision ("FID") to be made prior
to commencement of Phase 2. Receipt of FID from the Board requires
securing outstanding permits and project finance (debt and
equity).
Phase 1 – Front End Engineering Design
("FEED")
The FEED phase includes an initial two-month gap
analysis and in-depth review of the Definitive Feasibility Study
("DFS") deliverables, including the testwork and flowsheet
development conducted by the Company over the last 7 years.
Following completion of the gap analysis, other
key deliverables to be derived over the remaining 10 months during
Phase 1 include: completion of value engineering; identification of
long-lead time equipment; vendor engagement, selection and firm
pricing for major equipment items and packages; total installed
capital cost estimate to AACE Class 3 estimate accuracy (+/- 10%);
project implementation strategy; a baseline schedule for the EPCM
phase; and preparation of construction permit documentation.
Phase 2 - Engineering, Procurement and
Construction Management
Upon making the Final Investment Decision, the
Company will enter into the EPCM phase of the contract once
conditions precedent are satisfied. Wood will provide overall
project and construction management services throughout the EPCM
phase of the project, which includes detailed design, procurement,
construction, and commissioning.
Update on Permitting
The key outstanding permits for the Chvaletice
Project include: the Environmental Social Impact Assessment
("ESIA") approval, followed by the Land Planning Permit, and then
the Construction Permit.
ESIA
The Czech Ministry of Environment received
comments from 14 relevant authorities on the ESIA, which was
submitted in December 2022. All but one of the authorities approved
the relevant studies, signalling a positive perception of the
Project by regulators. The Ministry has returned the ESIA to the
Company to address comments from the authority yet to approve the
ESIA, related to noise abatement. The Company expects to address
these comments without an effect on the timeline to FID.
While the Chvaletice Project’s anticipated noise
levels are within legislative limits for an industrial project, as
neighbouring operations adjacent to the Project site have existing
noise emissions, the cumulative effect marginally exceeds permitted
noise levels at the measurement points, located at the closest
residential areas.
The revision of the noise study within the ESIA
has also been requested to consider new noise legislation related
to traffic noise coming into force in July 2023. The details of
this new legislation were released after the Project ESIA was
completed and submitted.
The necessary work to address the comments
related to noise have already begun, and the revised ESIA is
expected to be submitted in August 2023, when the ESIA process can
then continue. The Company anticipates the issuance of a positive
decision on the revised ESIA before the end of 2023.
Land Planning Permit
Upon approval of the ESIA, the Land Planning
Permit can be submitted. The documentation for this application is
substantially complete and will be finalised upon receipt of the
conditions in the approved ESIA. The Land Planning Permit approval
timeline is typically three months once submitted, resulting in an
anticipated approval by mid Q2 2024.
Construction Permit
As highlighted above, the Construction Permit documentation is a
deliverable of the FEED phase and is expected to be submitted at
the end of Q2 2024. The permit approval timeline for the
Construction Permit is three months, resulting in an anticipated
approval by Q3 2024.
Dr. Matthew James, President & CEO of Euro Manganese,
commented:
“Awarding the EPCM contract to Wood is another
key milestone for the Company. It is the result of an extensive and
robust selection process, and I am very pleased to be partnering
with such a high calibre, tier-one engineering firm. We look
forward to building a world-class facility to produce high-purity
manganese, an essential component in lithium-ion batteries for EV
vehicles. Together, we are working to advance the global energy
transition.
We fully respect the robustness of the ESIA
process and are committed to minimising project impacts to the
surrounding communities. I am confident that we will move forward
to a successful conclusion given the positive statements received
from the other stakeholders.”
About Euro Manganese
Euro Manganese is a battery materials company
focused on becoming a leading, competitive, and environmentally
superior producer of high-purity manganese for the electric vehicle
industry and other high-technology applications. The Company is
advancing development of the Chvaletice Manganese Project in the
Czech Republic, which is a unique waste-to-value recycling and
remediation opportunity involving reprocessing old tailings from a
decommissioned mine. The Chvaletice Project is the only sizable
resource of manganese in Europe, strategically positioning the
Company to provide battery supply chains with critical raw
materials to support the global shift to a circular, low-carbon
economy.
About Wood
Wood is a global leader in consulting and
engineering, helping to unlock solutions to critical challenges in
energy and materials markets. The Company provides consulting,
projects and operations solutions in 60 countries, employing around
35,000 people. www.woodplc.com
Authorized for release by the CEO of Euro
Manganese Inc.
Neither TSX Venture Exchange nor its Regulation
Services Provider (as that term is defined in the policies of the
TSX Venture Exchange) or the ASX accepts responsibility for the
adequacy or accuracy of this release.
Inquiries
Dr. Matthew JamesPresident & CEO+44 (0)747
229 6688
Louise BurgessSenior Director, Investor
Relations & Communications+1 (604) 312-7546lburgess@mn25.ca
Company Address: #709 -700 West Pender St.,
Vancouver, British Columbia, Canada, V6C
1G8Website: www.mn25.ca
Forward-Looking Statements
Certain statements in this news release
constitute “forward-looking statements” or “forward-looking
information” within the meaning of applicable securities laws. Such
statements and information involve known and unknown risks,
uncertainties and other factors that may cause the actual results,
performance or achievements of the Company, its Chvaletice Project,
or industry results, to be materially different from any future
results, performance or achievements expressed or implied by such
forward-looking statements or information. Such statements can be
identified by the use of words such as “may”, “would”, “could”,
“will”, “intend”, “expect”, “believe”, “plan”, “anticipate”,
“estimate”, “scheduled”, “forecast”, “predict” and other similar
terminology, or state that certain actions, events or results
“may”, “could”, “would”, “might” or “will” be taken, occur or be
achieved.
Such forward-looking information or statements
also include, but are not limited to, statements regarding the
Company’s intentions regarding the development of the Chvaletice
Project, the timing for completion and expected outcomes of each
phase of the EPCM contract, the Company’s ability to raise the
necessary financing, timing of the Final Investment Decision for
the Project, the Company’s ability to meet new legislative
requirements applicable to the ESIA, acceptability of the revised
ESIA documentation by the Czech Ministry of Environment and the
anticipated timing of its the approval, and the timing of the
anticipated submissions and approvals of the Land Planning Permit
and Construction Permits.
Readers are cautioned not to place undue
reliance on forward-looking information or statements.
Forward-looking statements are subject to a number of risks and
uncertainties that may cause the actual results of the Company to
differ materially from those discussed in the forward-looking
statements and, even if such actual results are realized or
substantially realized, there can be no assurance that they will
have the expected consequences to, or effects on, the
Company.
Factors that could cause actual results or
events to differ materially from current expectations include,
among other things: a delay or inability to get the revised ESIA
approved by relevant authorities; risks and uncertainties related
to the ability to obtain, amend, or maintain necessary licenses, or
permits, risks related to acquisition of surface rights; timing and
amount of production and total costs of production; the potential
for unknown or unexpected events to cause contractual conditions to
not be satisfied; unexpected results from the Gap Analysis and the
FEED stages of the EPCM contract; risks and uncertainties related
to the accuracy of mineral resource and reserve estimates; changes
in project parameters as plans continue to be refined; risks
related to global epidemics or pandemics and other health crises;
availability and productivity of skilled labour; risks and
uncertainties related to interruptions in production; unforeseen
technological and engineering problems; the adequacy of
infrastructure; risks related to project working conditions,
accidents or labour disputes; social unrest or war; the possibility
that future results will not be consistent with the Company's
expectations; developments in EV battery markets and chemistries;
and risks related to fluctuations in currency exchange rates,
changes in laws or regulations; and regulation by various
governmental agencies. For a further discussion of risks relevant
to the Company, see "Risk Factors" in the Company's annual
information form for the year ended September 30, 2022, available
on the Company's SEDAR profile at www.sedar.com.
All forward-looking statements are made based on
the Company's current beliefs as well as various assumptions made
by the Company and information currently available to the Company.
Generally, these assumptions include, among others: the presence of
and continuity of manganese at the Chvaletice Project at estimated
grades; the ability of the Company to obtain all necessary land
access rights; the ability of the Company obtain all required
environmental and other permits; successful completion of the
various stages of the EPCM contract, the availability of personnel,
machinery, and equipment at estimated prices, in good order, and
within estimated delivery times; currency exchange rates; manganese
sales prices; growth in the manganese market; the availability of
acceptable financing for the Chvaletice Project and for
continued operations; success in realizing proposed operations in
the Czech Republic and demand for the Company’s
products.
Although the forward-looking statements
contained in this news release are based upon what management of
the Company believes are reasonable assumptions, the Company cannot
assure investors that actual results will be consistent with these
forward-looking statements. These forward-looking statements are
made as of the date of this news release and are expressly
qualified in their entirety by this cautionary statement. Subject
to applicable securities laws, the Company does not assume any
obligation to update or revise the forward-looking statements
contained herein to reflect events or circumstances occurring after
the date of this news release.
Euro Manganese (TSXV:EMN)
Historical Stock Chart
From Oct 2024 to Nov 2024
Euro Manganese (TSXV:EMN)
Historical Stock Chart
From Nov 2023 to Nov 2024