MAG Silver Corp. (TSX / NYSE American: MAG) (“MAG”
or the
“Company”) announces the Company’s audited
consolidated financial results for the year ended December 31,
2021. For details of the audited consolidated financial
statements, Management's Discussion and Analysis, Annual
Information Form and Annual Report on Form 40-F for the year ended
December 31, 2021, please see the Company’s filings on SEDAR
(www.sedar.com) or on EDGAR (www.sec.gov).
All amounts herein are reported in $000s
of United States dollars (“US$”) unless otherwise
specified.
HIGHLIGHTS – DECEMBER 31, 2021 AND
SUBSEQUENT TO YEAR END
OPERATIONAL
- Significant progress was achieved during the year ended
December 31, 2021 on the construction of the 4,000 tonnes per day
(“tpd”) Juanicipio processing plant as the Juanicipio project team
delivered the project for plant commissioning late in the fourth
quarter of 2021.
- The plant commissioning timeline was extended, however, by
approximately six months until the regulatory approval to tie into
the national power grid is obtained. The plant commissioning
timeline is now expected to commence in Q2 2022.
- As reported by the operator Fresnillo, the Juanicipio Project
is expected to come in on budget with the processing plant expected
to be ramped up to 85% to 90% of plant capacity by the end of
2022.
- A regularly updated photo gallery of construction progress at
Juanicipio is available at
https://magsilver.com/projects/photo-gallery/#photo-gallery.
- Campaign processing of mineralized material from development
headings continues through the nearby Fresnillo plant and starting
in Q4 2021 mineralized material also began to be campaign processed
at Fresnillo’s Saucito plant. Saucito’s flowsheet better resembles
that of the Juanicipio plant and will provide further valuable
metallurgical benefits as production commences at
Juanicipio.
- The campaign processing rate originally targeted at 16,000
tonnes per month increased significantly to an average of 37,983
tonnes per month in Q4 2021 and to an average of 44,963 tonnes per
month for the first two months of 2022.
- Processing at the Fresnillo plants is expected to continue
until the Juanicipio plant is commissioned, with Fresnillo making
available any unused plant capacity at its Minera Fresnillo and
Minera Saucito operations, and if possible matching commissioning
and ramp up tonnages that were previously expected at
Juanicipio.
- For the three months ended December 31, 2021, on a 100% basis:
- 113,950 tonnes of mineralized material were campaign processed
through the Fresnillo and Saucito plants, with 1,519,027 payable
silver ounces, 3,641 payable gold ounces, 563 tonnes of lead and
800 tonnes of zinc produced and sold;
- Average silver head grade was 542 grams per tonne (“g/t”);
and
- Pre-commercial production sales totaled $39,368 for the quarter
(net of treatment and processing costs), less $7,593 in mining and
transportation costs, netting $31,775 in gross profit by Minera
Juanicipio in the quarter.
- For the year ended December 31, 2021, on a 100% basis:
- 251,907 tonnes of mineralized material were campaign processed
through Fresnillo’s plants, with 2,974,524 payable silver ounces,
5,975 payable gold ounces, 1,065 tonnes of lead and 1,519 tonnes of
zinc produced and sold;
- Average silver head grade was 470 g/t; and
- Pre-commercial production sales of $75,393 (net of treatment
and processing costs) less $15,329 in mining and transportation
costs, netting $60,064 gross profit in Minera Juanicipio for the
year.
- Since commencing campaign processing of Juanicipio mineralized
material from development headings in August of 2020 through
February 2022, a total of 413,691 tonnes of mineralized development
material have been processed through the nearby Fresnillo plant and
starting in December 2021 in the Saucito plant:
- contributing cash-flow to offset some of the initial project
capital; and
- de-risking Juanicipio’s metallurgical performance, which is
expected to significantly speed up project ramp-up.
- A further 89,925 tonnes of mineralized development material
with a silver head grade of 529 g/t were processed in January and
February 2022 through the Fresnillo and Saucito plants.
EXPLORATION
- Results of the Juanicipio 2020 exploration program were
reported in the third quarter (see Press Release dated August 5,
2021), and the program successfully:
- Confirms, and allows modeling with greater detail and
confidence of the high-grade silver resource within the upper parts
of the Valdecañas Bonanza Zone (as defined in the 2017 PEA) where
the first several years of mining is expected to occur;
- Confirms, expands, and allows improved modeling of the
continuous wide mineralization of the Valdecañas Deep Zone (as
defined in the 2017 PEA); and
- Confirms, expands, and allows improved modeling of the
ever-growing Anticipada Vein.
- The Juanicipio 2021 exploration program was completed in Q4
2021 with $6,296 spent on a 100% basis and was focused on continued
step-out and infill drilling of the Valdecañas Vein System
(including independent targeting of the Venadas Vein family and the
Anticipada Vein).
- The Juanicipio 2022 exploration program is currently in
process, with five drill rigs presently on surface running
concurrently with continued underground definition and geotechnical
drilling, and one rig testing the new Cesantoni target in the
northwest part of the Juanicipio concession.
- Deer Trail Project in Utah:
- Assays were released in Q3 2021 for the Phase I drill program
(see Press Release dated September 7, 2021), which successfully
fulfilled all three of its planned objectives by:
- Confirming the presence of a thick section of more favorable
carbonate host rocks (the predicted “Redwall Limestone” or
“Redwall”) below the Deer Trail mine;
- Confirming and projecting two suspected mineralization feeder
structures to depth; and
- Intercepting high-grade mineralization related to those
structures in host rocks below what was historically known.
- A follow up 5 hole/5,000 metre Phase II drill program commenced
in Q3 2021 and is in process with all assays pending.
- Subsequent to the year end, the Company entered into a
Definitive Arrangement Agreement with Gatling Exploration Inc.
(TSXV:GTR, OTCOB:GATGF) (“Gatling”) pursuant to which the Company
will acquire all of the issued and outstanding common shares of
Gatling in an all-share transaction. The Company and Gatling have
also entered into a loan agreement pursuant to which the Company
has agreed to provide Gatling with a C$3 million secured
convertible bridge loan to finance Gatling’s accounts payable and
operating expenses.
LIQUIDITY AND CAPITAL
RESOURCES
- As at December 31, 2021, MAG held cash of $56,748 while Minera
Juanicipio had cash on hand of $18,972 on a 100% basis.
- According to the operator Fresnillo, the Juanicipio Project
construction is expected to be delivered on budget at $440,000.
- With the current ramp up of underground mine production and
given hiring restrictions on contractors arising from new 2021
labour reform legislation, the timing of various sustaining capital
expenditures has been brought forward:
- These sustaining capital costs are included in current
Juanicipio development costs but are not considered by the operator
as part of the $440,000 initial project capital; and
- The costs incurred are expected to reduce future sustaining
capital costs and totaled approximately $41,388 on a 100% basis in
the second half of 2021 in preparation for the legislation to come
into effect.
- The expected cash flow from the ongoing campaign processing
until the Juanicipio plant is commissioned, along with the cash
held by Minera Juanicipio at December 31, 2021 of $18,972, are
projected to substantially fund the remaining capital expenditures
in the $440,000 initial capex (a cash call has not been needed
since mid-December 2021 which was $21,000 on a 100% basis).
- Should there be additional funding requirements in excess of
the cashflow generated, related to further commissioning delays or
to additional sustaining capital that is being brought forward
prior to attaining commercial production, there may still be
further cash calls required from Fresnillo and MAG.
- In Q4 2021, MAG closed a bought deal share offering and issued
2,691,000 common shares, including 15,700 common shares issued to
an officer and two directors of MAG and 351,000 common shares
issued upon the full exercise of the over-allotment option, at
$17.15 per share for gross proceeds of $46,151. The Company paid
commission of $2,301 to the underwriters and legal and filing costs
totaled an additional $608 resulting in net proceeds of
$43,242.
COVID-19
- Fresnillo, the Juanicipio operator implemented a range of
safety measures and monitoring procedures, consistent with World
Health Organization and Mexican Government COVID-19
directives.
- COVID-19 had an impact on the Juanicipio plant commissioning
timeline however during the course of the year:
- In Q1 2021, Fresnillo, as operator, reported that commissioning
was pushed out a few months to Q4 2021 as some infrastructure
contracts were delayed related to COVID-19; and,
- In Q4 2021, approval to complete the tie-in to the national
power grid was extended as noted above related to knock-on effects
of the pandemic.
CORPORATE
- MAG continued to refresh its board during the year with three
new appointments:
- Ms. Susan Mathieu was appointed to the board on January 13,
2021 increasing the size of the board to eight members;
- Mr. Tim Baker was appointed to the board on March 31, 2021
replacing Mr. Richard Clark who resigned from the board to focus on
other professional responsibilities; and,
- Mr. Dale Peniuk was appointed to the board on August 3, 2021
replacing Mr. Derek White who did not stand for re-election at the
Company’s Annual General and Special Meeting on June 21,
2021.
- On October 16, 2021 MAG announced that Mr. W.J. (Jim) Mallory
joined the Company as its Chief Sustainability Officer (“CSO”)
highlighting the Company’s commitment to environmental, social,
governance (“ESG”) betterment.
- On March 28, 2022, MAG announced the appointment of Fausto Di
Trapani as Chief Financial Officer (“CFO”) effective May 20, 2022.
Mr. Di Trapani is a finance executive with experience in the
natural resources sector spanning two decades, most recently having
served as the Chief Financial Officer at Galiano Gold Inc. Mr. Di
Trapani replaces Mr. Larry Taddei, who, after 12 years of service
with the Company, will step down from the CFO role to pursue other
opportunities. Mr. Taddei will assist in the orderly transition of
his duties following Mr. Di Trapani’s appointment.
JUANICIPIO PROJECT UPDATE
Underground Mine Production
As of August 2020, mineralized development
material from the Juanicipio Project is being campaign processed,
refined and sold on commercial terms at a targeted rate through Q3
2021 of 16,000 tonnes per month at the nearby Fresnillo plant 12
kilometres away. The processing rate increased to an average of
37,983 tonnes per month in Q4 2021 and subsequent to the year end
to an average of 44,963 tonnes per month for the first two months
of 2022. In December 2021, for the first time, 8,725 tonnes were
processed at Fresnillo’s Saucito beneficiation plant (also 100%
owned by Fresnillo). The Saucito plant flowsheet better resembles
that of the Juanicipio plant and will provide further valuable
metallurgical information as processing commences at Juanicipio.
This preproduction toll processing of Juanicipio mineralized
development material plus some initial stope production is expected
to continue until the Juanicipio plant is commissioned
In the three months and year ended December 31,
2021, 113,950 and 251,907 tonnes of mineralized development
material respectively, were processed through the Fresnillo plants,
realizing commercial and operational de-risking opportunities for
the Juanicipio Project. The resulting payable metals sold and
processing details on a 100% basis are summarized in Table
1 (three months ended December 31, 2021) and in
Table 2 (year ended December 31, 2021) below.
Table 1: Q4 2021 Development Material
Processed at Fresnillo’s Processing Plants (100%
basis)
Three Months Ended December 31, 2021 (113,950 tonnes
processed) |
|
Payable Metals |
Quantity |
Average Per Unit (1) |
$Amount |
Q4 2020$Amount |
Silver |
1,519,027 ounces |
$22.96 per oz |
$ 34,877 |
$ 5,866 |
Gold |
3,641 ounces |
$1,793.67 per oz |
6,531 |
876 |
Lead |
563 tonnes |
$1.05 per lb |
1,300 |
80 |
Zinc |
800 tonnes |
$1.55 per lb |
2,729 |
220 |
Treatment and refining charges (“TCRCs”) and other processing
costs |
(6,069) |
(1,232) |
Net Sales |
39,368 |
5,810 |
Mining and transportation costs |
(7,593) |
(2,342) |
Gross Profit |
$ 31,775 |
$ 3,468 |
(1) Ounces (“oz”) for silver and gold and, pounds (“lb”)
for lead and zinc.
Table 2: Year 2021 Development Material
Processed at Fresnillo’s Processing Plants (100%
basis)
Year Ended December 31, 2021 (251,907 tonnes
processed) |
|
Payable Metals |
Quantity |
Average Per Unit (1) |
$Amount |
2020$Amount (2) |
Silver |
2,974,524 ounces |
$23.99 per oz |
$ 71,369 |
$ 15,403 |
Gold |
5,975 ounces |
$1,791.22 per oz |
10,702 |
1,941 |
Lead |
1,065 tonnes |
$1.02 per lb |
2,387 |
301 |
Zinc |
1,519 tonnes |
$1.45 per lb |
4,849 |
575 |
TCRCs and other processing costs |
(12,768) |
(2,885) |
Provisional sales adjustment related to 2020 sales (3) |
(1,146) |
- |
Net Sales |
75,393 |
15,335 |
Mining and transportation costs |
(15,329) |
(3,873) |
Gross Profit |
$ 60,064 |
$ 11,462 |
(1) Ounces (“oz”) for silver and gold and, pounds (“lb”)
for lead and zinc.(2) Processing of Juanicipio mineralized
development material at the Fresnillo plant commenced in August of
2020, with no prior processing.(3) Provisional sales for 2020
were finalized in Q1 2021 resulting in negative adjustment to net
sales revenue of $1,146.
The average silver head grade for the
mineralized development material and initial stope material
processed in the three months and year ended December 31, 2021 was
542 g/t and 470 g/t (three months and year ended December 31, 2020
was 300 g/t and 328 g/t) respectively. This increased grade in the
last quarter of 2021 reflects less diluted development material and
more stoped vein material being processed.
Processing Plant Construction & Outlook
The Juanicipio project team delivered the
Juanicipio plant for commissioning in the fourth quarter of 2021.
However, according to the operator Fresnillo, the state-owned
electrical company (Comision Federal de Electricidad “CFE”),
notified Fresnillo late in December 2021 that the regulatory
approval to complete the tie-in to the national power grid could
not yet be granted, and the projected commissioning timeline has
therefore been extended by approximately six months, with
commissioning of the Juanicipio processing plant now expected to
commence in Q2-2022 with ramp up to 85 to 90% of the nameplate
4,000 tpd capacity by the end of 2022, according to Fresnillo.
In order to minimize any potential adverse
economic effect of the revised commissioning timeline, Fresnillo
has indicated it will make available any unused plant capacity at
its Minera Fresnillo and Minera Saucito operations to process
mineralized material produced at Juanicipio during this period, and
if possible match commissioning and ramp up tonnages that were
previously expected. The effect on cashflow generation from
Juanicipio therefore will also be mitigated while power connection
approvals are pending.
With the plant ready to commence commissioning
once connected to the power grid, final construction costs are
expected to wind down until final commissioning and testing
commence. Meanwhile, as noted above, the amount of mineralized
development material being processed at the two Fresnillo plats
since Q4 2021 has been significantly higher than the original
targeted rate of 16,000 tonnes per month. The cash flow from this
processing, along with the cash held by Minera Juanicipio at
December 31, 2021 of $18,972 and the expected cash flows from
continued processing until the Juanicipio plant is commissioned are
projected to substantially fund the remaining capital expenditures
in the $440,000 initial project capital (a cash call has not been
needed since mid-December 2021 which was $21,000 on a 100%
basis).
With the current ramp up of underground mine
production and given hiring restrictions on contractors arising
from new 2021 labour reform legislation, the timing of various
sustaining capital expenditures has been brought forward. Labour
reform on subcontracting and outsourcing in Mexico was published on
April 23, 2021 and came into effect on September 1, 2021. With
various restrictions on hiring contractors, Fresnillo, as operator,
has indicated a need to internalize a significant portion of its
contractor workforce and perform much of the development work
directly rather than outsourcing it to contractors. This requires
investment in equipment to be utilized in underground operations,
either not previously in the project scope or not envisaged to be
required until later in the mine life. As well, certain underground
development expenditures related to processing development material
and some small items brought forward from project investments
planned in the future are considered sustaining capital by
Fresnillo. The costs incurred are expected to reduce future
sustaining capital costs and totaled approximately $41,388 on a
100% basis in the second half of 2021 in preparation for the
legislation to come into effect. These costs are included in the
current Juanicipio development costs but are not considered by the
operator as part of the $440,000 initial project capital. Should
there be additional funding requirements in excess of the cashflow
generated related to further commissioning delays or to additional
sustaining capital that is being brought forward, there may still
be further cash calls required from Fresnillo and MAG.
Juanicipio Exploration Update
The planned expenditures for the 2022
Exploration Program total $7,000 with the programs designed to
expand and convert the Inferred Mineral Resources included in the
Deep Zone into Indicated Mineral Resources, and to explore other
parts of the Juanicipio concession. All aspects of the exploration
work continue to be done under strict COVID-19 protocols.
Subsequent to the year-end in mid-January, 2022, drilling began on
the first hole on the “Cesantoni Kaolinite Pits”(Cesantoni) target
(assay pending). Cesantoni lies in the northwestern corner of the
Juanicipio concession, roughly 6 km west of the Valdecañas Vein and
related underground and surface infrastructure.
The 2021 Juanicipio exploration program was
completed in late 2021, with an actual spend of $6,296 on a 100%
basis and was focused on continued step-out and infill drilling of
the Valdecañas Vein System (including independent targeting of the
Venadas Vein family and the Anticipada Vein). In total, 23 targets
(holes) were successfully tested with 21 being deep infill holes
and two exploration holes on other parts of the Juanicipio
concession, resulting in 29,421 metres drilled. The program results
will be released in Q2 2022 pending receipt of all
assays.
Assays for the Juanicipio 2020 drill program
were released in the Q3 2021 (see Press Release dated August 5,
2021). The 2020 drill program successfully:
- Confirmed, and allowed modeling with greater detail and
confidence of the high-grade silver resource within the upper parts
of the Valdecañas Bonanza Zone where the first several years of
mining will occur;
- Confirmed, expanded, and allowed improved modeling of the
continuous wide mineralization of the Valdecañas Deep Zone;
and,
- Confirmed, expanded, and allowed improved modeling of the
ever-growing Anticipada Vein.
DEER TRAIL PROJECT UPDATE
Phase I drilling commenced in November 2020 and
was completed in Q2 2021 with assays and interpretations released
in the third quarter of 2021 (see Press Release September 7, 2021).
Phase I saw the completion of three holes and 3,927 metres drilled
from surface and successfully fulfilled all three of its planned
objectives by:
- Confirming the presence of a thick section of more favorable
carbonate host rocks (the predicted “Redwall Limestone” or
“Redwall”) below the Deer Trail mine;
- Confirming and projecting two suspected mineralization feeder
structures to depth; and
- Intercepting high-grade mineralization related to those
structures in host rocks below what was historically known.
Phase II drilling commenced at the Deer Trail
Project on August 20, 2021 and is in process, planned for 5,000
metres of drilling over 5 holes. Deviation/directional drilling is
being used in Phase II to make the drilling more efficient and
accurate. In part to facilitate the directional drilling, drilling
contractors were changed in Q1 2022, with the new contractor on
site and preparing to resume drilling.
GATLING ACQUISITION
Subsequent to the year end, the Company entered
into a Definitive Arrangement Agreement with Gatling pursuant to
which the Company will acquire all of the issued and outstanding
common shares of Gatling in an all-share transaction. The Company
and Gatling have also entered into a loan agreement pursuant to
which the Company has agreed to provide Gatling with a C$3 million
secured convertible bridge loan to finance Gatling’s accounts
payable and operating expenses.
Gatling is a Canadian gold exploration company
focused on advancing the Larder Gold Project, located in the
prolific Abitibi greenstone belt in Northern Ontario, Canada. The
3,370 ha Larder Project hosts three high-grade gold deposits along
the Cadillac-Larder Lake Break, 35 km east of Kirkland Lake and 7
kilometers west of the Kerr Addison Mine. The project is 100% owned
by Gatling and is comprised of patented and unpatented claims,
leases and mining licenses of occupation within the McVittie and
McGarry Townships. All parts of the Larder property are readily
accessible and MAG expects to engage the existing exploration team
going forward.
Qualified Person: Dr. Peter
Megaw, Ph.D., C.P.G., has acted as the Qualified Person as defined
in National Instrument 43-101 for this disclosure and supervised
the preparation of the technical information in this release. Dr.
Megaw has a Ph.D. in geology and more than 40 years of relevant
experience focused on ore deposit exploration worldwide. He is a
Certified Professional Geologist (CPG 10227) by the American
Institute of Professional Geologists and an Arizona Registered
Geologist (ARG 21613). Dr. Megaw is not independent as he is Chief
Exploration Officer and a Shareholder of MAG.
FINANCIAL RESULTS – YEAR ENDED DECEMBER
31, 2021
As at December 31, 2021, the Company had working
capital of $57,761 (December 31, 2020: $94,513) including cash of
$56,748 (December 31, 2020: $94,008) and no long-term debt. As at
December 31, 2021, Minera Juanicipio had cash of $18,972 (MAG’s
attributable 44% share $8,348). The Company makes cash advances to
Minera Juanicipio as ‘cash called’ by the operator Fresnillo, based
on approved joint venture budgets. In the year ended December 31,
2021, the Company funded advances to Minera Juanicipio, which
combined with MAG’s Juanicipio expenditures on its own account,
totaled $74,136 (December 31, 2020: $64,270).
The Company’s net income for year the ended
December 31, 2021 amounted to $6,025 (December 31, 2020: $7,097 net
loss) or $0.06/share (December 31, 2020: loss of $(0.08)/share).
MAG recorded its 44% income from its equity accounted Investment in
Juanicipio of $15,686 (December 31, 2020: $2,214) which included
MAG’s 44% share of net income from the sale of pre-production
development material (see Table 3 below). Share
based payment expense, a non-cash item, recorded in the year ended
December 31, 2021 amounted to $4,256 (December 31, 2020: $3,122),
and is determined based on the fair value of equity incentives
granted and vesting in the year.
Table 3: MAG’s income from its equity
accounted Investment in Juanicipio
|
December 31,2021 |
December 31,2020 |
Gross Profit from processing development material
(see Table 2 above) |
$ 60,064 |
$ 11,462 |
Administrative expenses |
(1,929) |
(239) |
Extraordinary mining duty |
(337) |
(76) |
Foreign exchange and other |
(1,363) |
(623) |
Net Income before tax |
56,435 |
10,524 |
Income tax expense (including deferred income tax) |
(20,784) |
(5,492) |
Net Income for the year (100% basis) |
$ 35,651 |
$ 5,032 |
MAG’s 44% share of income from equity accounted Investment
in Juanicipio |
$ 15,686 |
$ 2,214 |
Shareholders may receive, upon request and free
of charge, a hard copy of the Company’s Audited Financial
Statements. The Company’s 40-F has also been filed with the United
States Securities and Exchange Commission.
About MAG Silver Corp.
(www.magsilver.com )
MAG Silver Corp. is a Canadian development and
exploration company focused on becoming a top-tier primary silver
mining company by exploring and advancing high-grade, district
scale, silver-dominant projects in the Americas. Its principal
focus and asset is the Juanicipio Project (44%), being developed
with Fresnillo Plc (56%), the operator. The Project is located in
the Fresnillo Silver Trend in Mexico, the world's premier silver
mining camp, where the operator is currently developing an
underground mine and constructing a 4,000 tonnes per day processing
plant. Underground mine production of mineralized development
material commenced in Q3 2020, and an expanded exploration program
is in place targeting multiple highly prospective targets at
Juanicipio. MAG is also executing a multi-phase exploration program
at the Deer Trail 100% earn-in project in Utah.
This release includes certain statements that
may be deemed to be “forward-looking statements” within the meaning
of the US Private Securities Litigation Reform Act of 1995. All
statements in this release, other than statements of historical
facts are forward looking statements, including statements that
address our expectations with respect to the timing and success of
plant pre-commissioning and commissioning activities, processing
rates of development materials, future mineral production, and
events or developments. Forward-looking statements are often, but
not always, identified by the use of words such as "seek",
"anticipate", "plan", "continue", "estimate", "expect", "may",
"will", "project", "predict", "potential", "targeting", "intend",
"could", "might", "should", "believe" and similar expressions.
These statements involve known and unknown risks, uncertainties and
other factors that may cause actual results or events to differ
materially from those anticipated in such forward-looking
statements. Although MAG believes the expectations expressed
in such forward-looking statements are based on reasonable
assumptions, such statements are not guarantees of future
performance and actual results or developments may differ
materially from those in the forward-looking statements. Factors
that could cause actual results to differ materially from those in
forward-looking statements include, but are not limited to, impacts
(both direct and indirect) of COVID-19, timing of receipt of
required permits, changes in applicable laws, changes in
commodities prices, changes in mineral
production performance, exploitation and exploration
successes, continued availability of capital and financing, and
general economic, market or business conditions, political risk,
currency risk and capital cost inflation. In addition,
forward-looking statements are subject to various risks, including
that data is incomplete and considerable additional work will be
required to complete further evaluation, including but not limited
to drilling, engineering and socio-economic studies and
investment. The reader is referred to the MAG Silver’s filings
with the SEC and Canadian securities regulators for disclosure
regarding these and other risk factors. There is no certainty that
any forward-looking statement will come to pass, and investors
should not place undue reliance upon forward-looking
statements.Neither the Toronto Stock Exchange nor the NYSE American
has reviewed or accepted responsibility for the accuracy or
adequacy of this press release, which has been prepared by
management.
Please Note: Investors are urged to consider
closely the disclosures in MAG's annual and
quarterly reports and other public filings, accessible through
the Internet at www.sedar.com and www.sec.gov LEI:
254900LGL904N7F3EL14
For further information on behalf of MAG Silver Corp.
Contact Michael J. Curlook, VP Investor Relations and Communications
Phone: (604) 630-1399
Toll Free:(866) 630-1399
Email: info@magsilver.com
Website: www.magsilver.com
MAG Silver (TSX:MAG)
Historical Stock Chart
From Nov 2024 to Dec 2024
MAG Silver (TSX:MAG)
Historical Stock Chart
From Dec 2023 to Dec 2024