Fortuna Silver Mines Inc. (NYSE: FSM)
(TSX: FVI) is pleased to provide an update on activities
at its Séguéla gold Project located in Côte d’Ivoire.
David Whittle, Chief Operating Officer - West
Africa, commented, “Construction activities are nearing completion
despite worldwide supply chain challenges. We are pleased to report
commissioning remains on schedule for Q2 2023.” Mr. Whittle added,
“Our operational teams are being assembled with an experienced core
leadership group already hired and preparing for first gold
production.” Mr. Whittle concluded, “This will mark a significant
milestone for Fortuna with Séguéla also exhibiting growth potential
given the quantity of Inferred Resources and the exploration
success on the property to date.”
Construction Highlights
- Overall project is approximately 90
percent complete as of the end of January and remains on-track and
on-budget for first gold pour in mid-2023
- SAG mill installation is nearing
completion
- Tailing storage facility (TSF)
earthworks and HDPE lining is almost complete
- Commissioning of the fuel depot is
complete
- Grid connection and energization of
the high voltage substation is complete
- Water storage dam (WSD) reserves at
levels above requirements for commissioning and processing plant
start-up
- Handovers of infrastructure from
construction to operations teams have commenced
Mining and Operational Readiness
Highlights
- Recruitment and onboarding of staff
well underway with an experienced core leadership team already in
place
- Mine fleet continues to arrive on
site and training of operators is underway
- Grade control drilling is underway
and mining activities are expected to commence in February
- Process plant commissioning plan is
on-track with commissioning teams and vendor representatives
expected to arrive throughout the first quarter of 2023
- Spare parts, first fills, reagents
and consumables have started to arrive at site
With the completion of construction rapidly
approaching, operational readiness has increasingly become the
focus in preparation for commissioning of the processing plant,
which is due to commence early in the second quarter of 2023. As a
result of the dedicated efforts of the Séguéla management and site
teams, the project is well positioned for this transition which
also represents a significant milestone for the Company.
Mota-Engil, the mining contractor, has established their temporary
facilities on site to support initial mining activities with
construction of the permanent mining services area infrastructure
progressing well. The mining fleet required for initial mining
activities is on site and has been commissioned.
The next tranche of mining equipment is
on-schedule for late-February availability:
- 6020B 230-ton hydraulic excavator
delivered and being assembled on-site
- 4 x 777E haul trucks being
assembled in Abidjan
- 1 x 50-ton excavator for
rock-breaker, hammer already on-site
- 1 x D9 dozer
- 2 x 988 front end loaders for
crusher feed
Mining preparations are underway with the
Antenna Stage 1 pit having been cleared and grade control drilling
in progress. The ROM pad and Antenna pit haul road areas have been
cleared in preparation for their construction which is scheduled to
begin in early February.
Upcoming key milestones include:
Q1
- Commencement of mining activities
in early February
- Commencement of drilling and
blasting in late February
- Commencement of processing plant
commissioning in March
- First ore to ROM pad at the end of
March
Q2
- Processing plant practical
completion in April
- First ore fed to the crusher in
April
- First gold pour
Negotiations with the Côte d’Ivoire government
are continuing in order to finalize the terms of the mining
convention.
Following the completion of the aforementioned
milestones, Lycopodium, EPC contractor, will conduct a rigorous
performance test of the processing plant before the end of the
third quarter.
SAG mill installation well advanced |
HV substation energized |
Fuel depot commissioned |
TSF earthworks and HDPE lining practically complete |
Initial mining fleet on site |
Grade control drilling underway |
Further updates on the Séguéla gold Project will
be provided as the development of the project proceeds. Séguéla´s
construction photo gallery can be accessed here.
Qualified Person
Raul Espinoza, Director of Technical Services
for the Company, is a Fellow member and Chartered Professional of
the Australasian Institute of Mining and Metallurgy (FAusIMM CP)
and a Qualified Person as defined by National Instrument 43-101,
Standards of Disclosure for Mineral Projects. Mr. Espinoza has
reviewed and approved the scientific and technical information
pertaining to the Séguéla Gold Project contained in this news
release and has verified the underlying data.
About Fortuna Silver Mines
Inc.
Fortuna Silver Mines Inc. is a Canadian precious
metals mining company with four operating mines in Argentina,
Burkina Faso, Mexico and Peru, and a fifth mine under construction
in Côte d'Ivoire. Sustainability is integral to all our operations
and relationships. We produce gold and silver and generate shared
value over the long-term for our stakeholders through efficient
production, environmental protection, and social responsibility.
For more information, please visit our website.
ON BEHALF OF THE BOARD
Jorge A. Ganoza President, CEO,
and DirectorFortuna Silver Mines Inc.
Investor Relations: Carlos Baca
| info@fortunasilver.com | Twitter:
@Fortuna_Silver | LinkedIn: fortunasilvermines |
YouTube: Fortuna Silver Mines
Forward looking Statements
This news release contains forward looking
statements which constitute “forward looking information” within
the meaning of applicable Canadian securities legislation and
“forward looking statements” within the meaning of the “safe
harbor” provisions of the Private Securities Litigation Reform Act
of 1995 (collectively, “Forward looking Statements”). All
statements included herein, other than statements of historical
fact, are Forward looking Statements and are subject to a variety
of known and unknown risks and uncertainties which could cause
actual events or results to differ materially from those reflected
in the Forward looking Statements. The Forward looking Statements
in this news release may include, without limitation, statements
about the Company’s plans for the construction of an open pit gold
mine at the Séguéla gold Project, including the timeline for
construction, commissioning, first gold pour and the ramp up to
design capacity; the costs of constructing the mine, the securing
of contracts necessary for the construction of the mine, the timing
of the delivery of equipment to the project; the signing of the
Mining Convention with the Government of Côte d’Ivoire, the ability
to sign contracts for outstanding equipment and services in line
with the estimates for same, the timing of the first gold pour; the
Company’s business strategy, plans and outlook; the merit of the
Company’s mineral properties; mineral resource and reserve
estimates; timelines; the future financial or operating performance
of the Company; expenditures; approvals and other matters. Often,
but not always, these Forward looking Statements can be identified
by the use of words such as “estimated”, “potential”, “open”,
“future”, “assumed”, “projected”, “used”, “detailed”, “has been”,
“gain”, “planned”, “reflecting”, “will”, “containing”, “remaining”,
“to be”, or statements that events, “could” or “should” occur or be
achieved and similar expressions, including negative
variations.
Forward looking Statements involve known and
unknown risks, uncertainties and other factors which may cause the
actual results, performance or achievements of the Company to be
materially different from any results, performance or achievements
expressed or implied by the Forward looking Statements. Such
uncertainties and factors include, among others, changes in general
economic conditions and financial markets; the duration and effects
of the COVID-19 pandemic on our operations and workforce and the
effects on the global economy and society; changes in prices for
silver, gold and other metals; changes in the prices of supplies
required for the construction at the Séguéla gold Project such as
equipment and services; the ability to sign the Mining Convention
on terms currently contemplated and acceptable to the Company;
technological and operational hazards in Fortuna’s mining and mine
development activities; risks inherent in mineral exploration;
fluctuations in prices for energy, labor, materials, supplies and
services; fluctuations in currencies; increases in inflation;
uncertainties inherent in the estimation of mineral reserves,
mineral resources, and metal recoveries; our ability to obtain all
necessary permits, licenses and regulatory approvals in a timely
manner; governmental and other approvals; political unrest or
instability in countries where Fortuna is active; labor relations
issues; as well as those factors discussed under “Risk Factors” in
the Company's Annual Information Form. Although the Company has
attempted to identify important factors that could cause actual
actions, events or results to differ materially from those
described in Forward looking Statements, there may be other factors
that cause actions, events or results to differ from those
anticipated, estimated or intended.
Forward looking Statements contained herein are
based on the assumptions, beliefs, expectations and opinions of
management, including but not limited to that the construction at
the Séguéla gold Project will continue on the time line and in
accordance with the budget as planned; that COVID-19 and the
current inflationary environment will not have an adverse effect on
the cost of construction of the mine at the Séguéla gold Project
and will not adversely affect the supply chain and delivery of
materials and equipment for the construction; expected trends in
mineral prices and currency exchange rates; that there will be no
adverse weather conditions that will delay work at the project;
that the Company’s activities will be in accordance with the
Company’s public statements and stated goals; that there will be no
material adverse change affecting the Company or its properties;
that all required approvals will be obtained; that there will be no
significant disruptions affecting operations, and such other
assumptions as set out herein. Forward looking Statements are made
as of the date hereof and the Company disclaims any obligation to
update any Forward looking Statements, whether as a result of new
information, future events or results or otherwise, except as
required by law. There can be no assurance that Forward looking
Statements will prove to be accurate, as actual results and future
events could differ materially from those anticipated in such
statements. Accordingly, investors should not place undue reliance
on Forward looking Statements.
Cautionary Note to United States Investors
Concerning Estimates of Reserves and Resources
Reserve and resource estimates included in this
news release have been prepared in accordance with National
Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI
43-101") and the Canadian Institute of Mining, Metallurgy, and
Petroleum Definition Standards on Mineral Resources and Mineral
Reserves. NI 43-101 is a rule developed by the Canadian Securities
Administrators that establishes standards for public disclosure by
a Canadian company of scientific and technical information
concerning mineral projects. Unless otherwise indicated, all
mineral reserve and mineral resource estimates contained in the
technical disclosure have been prepared in accordance with NI
43-101 and the Canadian Institute of Mining, Metallurgy and
Petroleum Definition Standards on Mineral Resources and
Reserves.
Canadian standards, including NI 43-101, differ
significantly from the requirements of the Securities and Exchange
Commission, and mineral reserve and resource information included
in this news release may not be comparable to similar information
disclosed by U.S. companies.
Photos accompanying this announcement are available
at:
https://www.globenewswire.com/NewsRoom/AttachmentNg/792fbb69-ec66-4ada-82eb-2c7503b443ad
https://www.globenewswire.com/NewsRoom/AttachmentNg/acca0bd7-12ef-4f9f-8008-72e5e36127a1
https://www.globenewswire.com/NewsRoom/AttachmentNg/013ac5af-623d-45f2-9be7-84e08f2fa017
https://www.globenewswire.com/NewsRoom/AttachmentNg/76982db0-e25f-4821-9df9-f7517ae0bafe
https://www.globenewswire.com/NewsRoom/AttachmentNg/f436752f-7699-4e6d-916a-c8bf85b85329
https://www.globenewswire.com/NewsRoom/AttachmentNg/c971d39b-6117-4f6e-b16e-1f8b587892c8
Fortuna Mining (TSX:FVI)
Historical Stock Chart
From Dec 2024 to Jan 2025
Fortuna Mining (TSX:FVI)
Historical Stock Chart
From Jan 2024 to Jan 2025