DOW JONES NEWSWIRES
The following table lists unplanned and planned production
outages at U.S. refineries as reported by Dow Jones Newswires. The
information is compiled from both official and unofficial refining
sources and doesn't purport to be a comprehensive list.
Motiva Enterprises LLC's newly-commissioned crude unit at its
Port Arthur, Texas, refinery will be shut for up to three more days
before restarting it, a source familiar with the refinery said on
June 6. The 325,000-b/d unit was taken off-line early on June 4
after leaks occurred because of loose valves.
BP PLC (BP) on June 5 said gasoline-making FCCU No. 3 had been
restarted after going off-line, unplanned, on May 24. The unit had
just been restarted on May 21 following five months of
maintenance.
Phillips 66 (PSX) on June 5 said recent maintenance at its
Rodeo, Calif., refinery had been concluded; no other details were
provided. The refinery reported flaring associated with a unit
restart on May 31.
Several units, including a coker, pretreater and hydrogen unit,
are scheduled for several weeks of planned maintenance at Exxon
Mobil's (XOM) Torrance, Calif., refinery, the co. said on June 4.
The plant filed a planned flaring report to Calif. regulators on
June 1 stating flaring may be visible between June 4 and 13.
BP Plc has restarted production at its Cherry Point refinery in
Blaine, Washington, after months of maintenance work, a source
familiar with the refinery said May 29.
For more detailed information, search Dow Jones Newswires using
the code N/REF.
Operator Refinery Capacity Description Restart
(in 000s
bbl/day)
UNPLANNED
CANADA
CARIBBEAN
EAST COAST
MIDWEST
Delek El Dorado 70.0 Rates reduced by 10K b/d due
crude oil delivery suspension
by Exxon Mobil. Additional
supply has been secured, the
co. said on May 15.
GULF COAST
Delek Tyler, TX 62.0 Rates reduced to 45k-50K b/d
until end-May while repairs
continue at FCCU shut by May
7 power failure, the co.said
on May 15.
Motiva Port Arthur 600.0 Newly-commissioned 325,000-b/d
TX crude unit shut on June 4; re-
pairs could take up to three
more days, a source said on June
6.
Phillips Borger, TX 146.0 Company reported flaring on May
66 25 because of a hole in furnace.
BP Texas City, 475.0 FCCU No. 3 restarted on June 5 June 5
TX after shutting down unplanned
during the restart process on
May 24. The unit was returning
from 5 months of maintenance.
MIDWEST
ROCKIES
Suncor Commerce 94.0 FCCU down because of problem
City, CO. with compressor. No restart date
given.
WEST COAST
BP Ferndale, 230.0 Restart process concluded
WA at the end of May. The
refinery shut on Feb 17
due to crude unit fire.
Phillips Rodeo, CA 76.0 Recent maintenance has been
66 concluded the co. said on June
5. Flaring due to restart of
unspecified unit was reported
on May 31.
PLANNED
CANADA
Husky Saskatchewan 21-days maintenance set in 1stH
Upgrader first half 2012 at hydrogen 2012
plant, the co. said on Feb 9.
Husky Saskatchewan Major turnaround to take place Spring
Refinery in spring of 2013. Plant-wide 2013
shutdown for inspection and
equipment repairs.
CARIBBEAN
HOVENSA St. Croix 350.0 Refinery shutdown completed, the Feb 21
co. said on Feb. 21. The facility 2012
will be operated as a products
storage terminal.
Valero Aruba 235.0 Operations will be suspended
at the end of March due to eco-
nomics, the co. said on Mar 19.
EAST COAST
Phillips Trainer, PA 185.0 Delta Airlines buys refinery
66 on April 30, 2012.
Operations were idled on Sept.
30, 2011 for economic reasons.
PBF Delaware City 190.0 Planned work currently under way
Energy DE the co. said on May 7. Scope and
duration not disclosed.
Sunoco Philadelphia 335.0 Energy Partners buys Sunoco Inc.;
PA deal to close 4Q 2012.
Sunoco Marcus Hook 190.0 Marcus Hook shut Dec. 1 ahead of
schedule due to poor refining econo-
economics.
GULF COAST
BP Texas City 406.6 FCCU No. 3 and Alkylation unit N/A
TX down for routine maintenance that
began around Jan. 5 continues, a
person familiar with the refinery
said on May 11. Restart estimate
not available.
Flint Corpus 300.0 Coker unit maintenance combined
Hills Christi TX with hydrocracker unit restart
to cause emissions and flaring
on May 12.
Holly Artesia, NM 100.0 Crude runs will be reduced by Early
Frontier 50% during 30 days of major turn- 2012
maintenance in early 2012, the Co.
said on Aug. 5.
Phillips Belle Chasse 247.0 Refinery up for sale a
66 LA Nov. 29 Bloomberg News
report said.
Valero McKee TX 170.0 FCCU in restart after turnaround May 11
that began on Mar 31 the co. said
on May 11.
Vacuum unit turnaround planned in
first half of 2012, company said.
Expansion project announced
March 2011 to increase crude oil
throughput by 25,000 b/d to
195,000 b/d.
Valero Meraux, LA 135.0 Co. on May 16 said the alky and June 1
FCCU shut Jan 2 for turnaround
are restarting and at normal rates
by June 1.
Valero Norco, LA 185.0 Hydrocracker project will pro- 2013
ceed and be completed in late
2013, the co. said on 7/27/10.
Upgrade project to build 2012
a new diesel hydrotreater
unit moved from 2010 to
4Q 2012.
Valero Port Arthur 325.0 Hydrocracker project will pro- 2012
TX ceed and be completed in late
2012.
MIDWEST
Citgo Lemont, IL 167.0 FCCU restarted on May 17; unclear May 17
when unit shut down. Equipment
failure and emissions reported
on May 10.
Portion of refinery shut for May 29
30 days of planned maintenance,
on Apr 29 the co. said. No
details provided.
CVR Wynnewood 54.0 30-40 days maintenance planned Q3
OK in 3rd Q 2013, the co. said on 2013
Nov. 3, 2011.
Holly Tulsa, OK 125.0 The entire refinery will be shut Late
Frontier while West Plant section under- 2012
goes major turnaround maintenance
in late 2012, the Co. said on
Aug. 5, 2011.
Husky Lima, OH 160.0 15-days of maintenance at diesel 4Q
Energy hydrotreater; 29-day at aromatics 2012
unit set for 4Q 2012, the co.
on Feb 9.
New 20,000-b/d kerosene hydro- 1stH
treater will start up in 1st 2013
half 2013, to co. said on Feb 9,
2012.
45-days of major turnaround
scheduled in 2014; 70% of units
involved. Remaining 30% will under
go major turnaround in 2015, the
co. said on Feb 9, 2012.
Husky Toledo, OH 140.0 Minor turnaround planned in mid- mid-2012
Energy 2012; the partial outage will
last about 21 days, the co. said
on Feb. 9.
Tesoro Mandan, ND 58.0 Total crude-oil processing capa- 2nd Q
city to increase by 17% to 68,000 2012
b/d by 2nd quarter 2012.
ROCKIES
WEST COAST
Alon Bakersfield 14.5 Hydrocraker Unit to restart Mid-May
CA mid-May traders said on May 4.
BP Carson, CA 265.0 Planned flaring may occur
May 15-21; not associated with
equipment breakdown- filing.
Chevron Richmond 246.0 Source on May 14 said units in- May 28
CA volved in May 12 planned shutdown
include FCCU and hydrotreater.
Work to last for two weeks.
Exxon Torrance 155.0 Several units will be shut for
Mobil CA planned maintenance, including
hydrogen, coker and pretreater
starting June 4. Work will take
several weeks to complete, the
co. said on June 4.
Shell Martinez 156.4 Scheduled work (unspecified)
CA is underway, the co. said on
Apr 27. Traders said crude and
coker unit involved; end date
not provided.
Tesoro Martinez 166.0 Hydrocracker has been shut for May 11-
two weeks of maintenance, traders 13
said on May 2.