Interim Management Statement
April 28 2009 - 2:00AM
UK Regulatory
TIDMTALV
RNS Number : 2542R
Talvivaara Mining Company PLC
28 April 2009
Talvivaara Mining Company Plc
Stock Exchange Release 28 April 2009
Interim Management Statement for the period of 1 January - 27 April 2009
First nickel sulphides delivered to Norilsk Nickel Harjavalta
Materials handling systems to be upgraded to deal with delays with crushing
and to facilitate production expansion
Highlights
* First shipment of nickel sulphide to Norilsk Nickel Harjavalta was sent on 19
February 2009
* Mining, leaching and metals recovery processes are functioning well
* Crushing capacity has continued to remain substantially below budgeted levels
for the year to date, but is expected to significantly improve during the second
half of the year
* Our most recent analysis leads us to believe that it is unlikely that previously
stated nickel production targets for 2009 are met, reflecting the reduced levels
of crushing to date
* Agreement has been reached with Sandvik for the delivery and financing of
additional crushing equipment to increase crushing capacity from September 2009
by approximately 45% to 22 million tonnes per annum
* Safety at the mine site remained good with 5 minor lost time injuries during the
period; there have been no LTI's since the launch of the Work Group Safety
Challenge at the beginning of February 2009
* The number of employees at Talvivaara increased from 239 at the end of 2008 to
272 on 27 April 2009; recruitment will continue throughout the ramp-up period
during the remainder of the year
* First EUR 20 million of the EUR 50 million investment and working capital loan
from Finnvera Plc was drawn down in two instalments on 17 and 23 April 2009
* The Company continues to have sufficient facilities in place to execute its
original ramp up plans despite the delay
* The production target for 2010 of 30,000t remains unchanged; plans for
production expansion to 45 thousand tonnes of nickel in 2011 and 50 thousand
tonnes in 2012 are under preparation
Talvivaara's CEO, Pekka Perä comments:
"I am very pleased to have seen our first shipment of nickel and zinc sulphides
been made, which is a major milestone. Having received invoices for several
years now, it is gratifying to now be able to send them ourselves.
With
all the other main areas of work on the production ramp-up functioning well, it
has been frustrating to have our production ramp-up delayed by difficulties with
crushing capacity. With regard to the crushing issue, we have now come to the
conclusion that in order to secure our overall production capacity in the long
term, it is time to invest in additional crushing capacity as soon as possible.
We are working on the expansion of crushing in close partnership with Sandvik
with whom we have agreed a detailed implementation timetable.
Our main focus remains the ramp-up process and maintaining Talvivaara's position
as a low cost metal producer. We intend to ensure we are in a position to catch
up by the summer of 2010 on the crushing volumes lost this year. However, due to
the process related delay from crushing to the actual metals production, the
production target for 2010 of 30,000t remains unchanged. Our plans for
production expansion now include output of 45 thousand tonnes of nickel in 2011
increasing to 50 thousand tonnes in 2012, with final decisions on the expansion
pending financing arrangements, but expected still this year."
Key events during the reporting period:
First nickel sulphides shipped to Norilsk Nickel - ramp-up continues
The first shipment of approximately 100 tonnes of nickel product was sent on 19
February 2009 from the Talvivaara mine to the Norilsk Nickel Harjavalta
refinery, marking the beginning of saleable quantity and quality metals
production at Talvivaara. The 450 tonnes of zinc sulphide obtained from the
first production campaign was sold as a spot sale.
The second metal sulphide production campaign started on 22 April 2009 and is
estimated will continue until mid to late May.
Mining and bioheapleaching processes progressed as planned during the period.
The increase in overall production volumes continued to be limited by crushing
capacity.
Materials handling systems to be upgraded to catch up on delay with crushing
and to facilitate production expansion
Further amendments to Talvivaara's fine crushing circuit were made during the
first quarter of the year in order to achieve the name plate capacity of the
system. As a result, the performance of the circuit has improved and around 80%
of the targeted capacity can now be consistently achieved. However, the first
quarter of 2009 fell approximately 50% short of the production target due to
deficient system performance and production stoppages for the amendment works.
In order to secure sufficient capacity in the long term and to catch up the
already incurred crushing delay by Q3 2010, Talvivaara has decided to redesign
the entire crushing system and to acquire additional crushing equipment with
expected availability for use in September 2009. The Company has reached
agreement with Sandvik Mining and Construction Oy on corrective actions required
for the original crushing and screening line, the delivery of additional
crushing capacity, and on financing of the additional supply. The scope of the
additional supply will be such that, together with the existing gear in a
redesigned circuit, it enables steady state crushing capacity at approximately
22 million tonnes per annum. This represents a 45% increase over the presently
planned capacity and functions therefore as a first step towards the planned
overall production expansion.
Modifications required for the increased capacity in the subsequent process
stages, agglomeration and stacking, have already been defined and are under
preparation.
Personnel and safety
Talvivaara Group's personnel increased from 239 at the start of the reporting
period to 272 by the date of this statement. The growth in personnel stemmed
primarily from the recruitment of maintenance personnel and operators for
various production processes. Recruitment of personnel will continue throughout
the ramp-up period during the remainder of the year.
By the end of the reporting period, the number of contractor personnel at the
mine site had reduced to approximately 200, indicating that the construction
project is nearing its completion. During the summer of 2009 the preparations
for and installation of the additional crushing circuit will temporarily
increase the number of contractor workforce. At steady state production, the
number of contractor personnel on site is anticipated to be approximately 100.
During the reporting period there were 5 lost time injuries on site. Of these,
three occurred to Talvivaara's own personnel. No lost time injuries have been
reported after the Company launched a continuous Work Group Safety Challenge in
the beginning of February 2009.
Investment and working capital loan from Finnvera Plc
The first EUR 20 million of the EUR 50 million investment and working capital
loan from Finnvera Plc was drawn down in two instalments on 17 and 23 April
2009.The loan is intended to cover Talvivaara's financing needs during the
ramp-up period in 2009. Repayments of the loan are scheduled to start in
December 2013.
Talvivaara continues to have facilities in place to finance the original ramp-up
despite the production delays caused by technical difficulties in materials
handling.
Market environment
The base metals markets have continued to be challenging during the first months
of 2009. The spot prices of nickel and zinc have recently been around USD
11,000-12,000 per tonne and USD 1,300-1,500 per tonne, respectively, which is
20-30% above the prices seen in the early part of the year. The demand for base
metals has not yet markedly improved, however, indicating that no significant
improvement in market prices can be expected in the short term.
Short term outlook
Crushing problems have affected production levels in the early part of the year
but the upcoming installation of additional crushing capacity should mean that
whilst output during the first half of the year will be substantially below the
budgeted level, production levels will significantly improve during the latter
half. The exact timing and length of the production stoppage required for the
installation of the new crushing gear is not yet known. However, overall, it is
unlikely that the previously stated production targets for 2009 will be
achieved. Crushing volumes lost this year are anticipated to be caught up by Q3
2010, while metals production potentially lost this year is anticipated to be
caught up in 2011 at the latest.
Due to the technical challenges experienced in crushing, the Company has
continued to review both capital and operational expenditure with the goal of
minimising costs during 2009. Operational expenditure is largely dependent on
the eventual production volume, but savings are in any case expected to be
achieved through lower than budgeted consumables prices. Some freight costs will
also be deferred, as Norilsk Nickel has informed Talvivaara of a delay in the
completion of the facilities being built for the Talvivaara product. Due to this
delay, it has been agreed that Talvivaara will only ship further amounts of
nickel sulphide to Norilsk Nickel from August 2009 onwards. All amounts produced
prior to that time will however be invoiced upon production and paid by Norilsk
Nickel in accordance with the terms of the off-take agreement.
With the additional crushing capacity already committed, Talvivaara continues to
investigate possibilities to also commit to an overall capacity increase of
40-45% over the presently planned level of 33,000 tonnes of nickel per annum.
Negotiations are ongoing relating to the supply and financing of the necessary
modifications to the metals plant and of the required earth works. Subject to
financing arrangements being available, the Company is prepared to pursue the
capacity increase during the current year.
There will be a conference to discuss the statement on 28 April 2009 at 11.00
(UK)/13.00 (Finland).
Details to access the conference call are as follows:
UK Free Call: 0800 694 0257
UK Standard International: +44 (0) 1452 555 566
USA Free Call: 1866 966 9439
Finland Free Call: 0800 112 363
and the conference ID is 97353284
A replay facility will be available on the following numbers until 5 May 2009:
Replay Access Number: 97353284#
International Dial in: +44 (0) 1452 55 00 00
UK Free Call Dial In: 0800 953 1533
UK Local Dial In: 0845 245 5205
USA Free Call Dial In: 1866 247 4222
Enquiries:
Talvivaara Mining Company Plc Tel. +358 20 7129 800
Pekka Perä
Saila Miettinen-Lähde
Merlin Tel: +44 207 653 6620
Tom Randell
Anca Spiridon
Note: The information presented in this release is unaudited.
About Talvivaara Mining Company Plc.
Talvivaara is a Finnish mining company operating a large open pit nickel mine in
Sotkamo, Finland. Talvivaara aims to become an internationally significant base
metals producer with its primary focus on nickel and zinc using a technology
known as bioheapleaching to extract metals out of ore. Bioheapleaching makes
extraction of metals from low grade ore economically viable. The Talvivaara
deposits comprise one of the largest known sulphide nickel resources in Europe.
The ore body is sufficient to support anticipated production for over 60 years.
The Company has secured a 10-year off-take agreement for 100 per cent of its
main output of nickel and cobalt to Norilsk Nickel. Talvivaara is listed on the
London Stock Exchange Main Market and is included in the FTSE 250 Index. Further
information can be found at www.talvivaara.com
This information is provided by RNS
The company news service from the London Stock Exchange
END
IMSPUUUGCUPBPWM
Talvivaara (LSE:TALV)
Historical Stock Chart
From May 2024 to Jun 2024
Talvivaara (LSE:TALV)
Historical Stock Chart
From Jun 2023 to Jun 2024