RNS Number:3460T
Talvivaara Mining Company Ltd
29 April 2008


Talvivaara Mining Company Plc

Stock Exchange Release 29 April 2008



Interim Management Statement for the period of 1 January - 28 April 2008


Talvivaara Group's main activity during the period was the construction of the
Talvivaara nickel mine in Sotkamo, Finland. The project progressed according to
plan both as regards its timetable and budget. Capital expenditure during the
period of 1 January - 31 March 2008 amounted to Euro62 million. Total investment in
the project through to 31 March 2008 amounted to Euro187 million.


Key events during the reporting period:

Connection to the Finnish national main grid


The 110 kV power line constructed from the Vuolijoki substation to the
Talvivaara mine was connected to the Finnish national main grid on 18 January
2008. The 43 km power line was constructed and connected ahead of schedule.
Talvivaara Project Ltd and Fingrid Oyj have entered into an agreement over
Talvivaara's access to the main grid for the years 2008 - 2011.


Resolution by the Vaasa Court of Appeal on the environmental permit and starting
order


The Vaasa Court of Appeal issued its ruling on the appeals made against the
environmental permit and starting order on 15 February 2008. The Court of Appeal
upheld the Company's original permit and the starting order, and rejected all
demands for the revocation of the permit and the starting order. All
compensations issued by the permitting authorities remained in force. The Court
of Appeal made a few amendments and specifications to the terms of the permit,
all of which in the opinion of the management are immaterial in terms of changes
to the projected costs for, or the conduct of, the mining and metals recovery
operations at the site.


The ruling was open to appeal to the Supreme Administrative Court until 17 March
2008. By the end of the appeal period, four appeals against the environmental
permit and starting order had been made. It is expected that the Supreme
Administrative Court will issue its ruling on the permit in the coming months,
after which the environmental permit will be final and binding. Talvivaara does
not anticipate that the terms of the permit will change materially as a result
of the appeal process.


Annual General Meeting on 14 March 2008


The Annual General Meeting of Talvivaara Mining Company was held on 14 March
2008 in Sotkamo. The AGM approved the adoption of the Company's and the Group's
annual accounts for the period ended 31 December 2007 and granted discharge of
liability to the members of the Board and the Managing Director / CEO. It was
determined that no dividend will be paid for the year ended 31 December 2007.


The AGM approved the Board of Directors' proposal to change the corporate form
of the

Company from a private limited company to a public limited company. It was
resolved that the new name of the Company is Talvivaara Mining Company Plc.


The AGM authorised the Board of Directors to issue up to a maximum of 11,495,000
shares through issuance of shares against consideration and/or special rights
entitling to shares (including stock options) in one or more issues. The
authorisation is valid until 13 March 2013. Should the Board of Directors
utilize this authorisation in full, the number of the Company's shares issued
and outstanding would increase from 222,896,178 to 234,391,178 shares.


Commencement of mining


Talvivaara Project Ltd had its first operational blast of ore on 1 April 2008.
The first blast marked the beginning of the extraction of ore at the Talvivaara
mine according to the project timetable.


Railroad project and rail transport


Talvivaara Infrastructure Oy and VR-Track Ltd signed an agreement on 31 January
2008 for the construction and maintenance of a 25 kilometre railroad connection
between the Talvivaara mine and the national railroad network. The beginning of
rail operation is anticipated in August 2009.


On 11 March 2008, Talvivaara Infrastructure Oy and the Finnish Rail
Administration signed an agreement for the redemption of the Talvivaara railroad
by the Finnish Rail Administration after two years of operation. Talvivaara
Infrastructure Oy will be responsible for the maintenance of the railroad for
this initial two-year period. Thereafter, the railroad will become part of the
national rail network.


On 29 February 2008, Talvivaara Project Ltd and VR-Group Ltd signed a multi-year
general and partnership agreement regarding the Talvivaara mine railroad
transport. VR Cargo will be responsible for the railroad transport of raw
materials and metal sulphides to and from the mine. When in full production, the
required transportation capacity will reach an estimated 1.5 million tonnes
annually.

Personnel and safety


Talvivaara Group's number of personnel increased from 64 at the start of the
reporting period to 146 by the date of this statement. The growth in personnel
stemmed primarily from the completion of several tailored training programmes
for the Talvivaara mine and processing plant operators. Students who have
successfully completed these training programmes are employed by Talvivaara.
There are currently approximately 1,200 persons working daily at the site.


During 2008, there have been altogether six lost-time-injuries, none of them
serious. The company will continue to place a special emphasis on safety issues
at the site.


Short-term outlook


The Talvivaara mine project has progressed according to plan during the
reporting period and the Company considers its next key milestones, being the
start of stacking and bioheapleaching in July and the start of metal sulphide
production in October, to be realistic.


Enquiries:


Talvivaara Mining Company Plc             Tel: +358 20 7129 800
Pekka Pera
Saila Miettinen-Lahde


Merlin                                    Tel: +44 207 653 6620
Tom Randell
Anca Spiridon


Note: The information presented in this release is unaudited.

Talvivaara aims to become an internationally significant base metals producer
with its primary focus on nickel and zinc using a technology known as
bioheapleaching to extract metal out of low grade ore. Bioheapleaching makes
extraction of metals from low grade ore economically viable. The Talvivaara
deposits comprise one of the largest known sulphide nickel resources in Europe.
The ore body is sufficient to support anticipated production for a minimum of 24
years and production is expected to start in late 2008. The Company has secured
a 10-year off-take agreement for 100 per cent. of its main output of nickel and
cobalt to Norilsk Nickel.




                      This information is provided by RNS
            The company news service from the London Stock Exchange

END
IMSPUUUWCUPRGPB

Talvivaara (LSE:TALV)
Historical Stock Chart
From Jul 2024 to Aug 2024 Click Here for more Talvivaara Charts.
Talvivaara (LSE:TALV)
Historical Stock Chart
From Aug 2023 to Aug 2024 Click Here for more Talvivaara Charts.