Dwyka Resources Limited ("Dwyka or the "Company")
Work programme commences at Ethiopian Gold Projects
Highlights
* Work programme has commenced, with focus on the Tulu Kapi and Yubdo gold
prospects alongside Dwyka's existing assets
* Results of Minerva's 34 hole drilling programme at Tulu Kapi to be used with the
intention of rapidly establishing a JORC resource and fast tracking the project
to development
* Short term three pronged approach adopted: Venmyn Rand commissioned to undertake
an independent review of the assets to assist the Board in determining its
future work programme; drilling done to date to be converted to a maiden JORC
compliant resource; trench work being undertaken to identify suitable drill
targets for the drilling season which will commence in September 2009
* Plan to expand Tulu Kapi project through further exploration and investigate
possibility that Tulu Kapi is part of a new gold province
* Dwyka to use in-house platinum processing expertise to progress Yubdo platinum
asset from current pilot plant phase. Dwyka will immediately undertake a
detailed review of the mineralogy and plant design and has budgeted for further
exploration
Following the announcement made by the Company last week that its takeover offer
to acquire the entire issued share capital of Minerva Resources Plc ("Minerva")
has been declared unconditional in all respects (following receipt of valid
acceptances representing approximately 80.9% of Minerva's issued share capital),
the Board of Minerva has now been replaced by Dwyka Directors Melissa Sturgess,
Terry McConnachie and Evan Kirby. Dwyka has assumed immediate management
control of the Minerva assets, chief amongst which are two gold exploration
licences and one platinum mining licence, all situated in Ethiopia,
approximately 530km west of Addis Ababa. The Dwyka management team has extensive
experience developing gold and platinum projects and the Company will now use
its cash reserves to fast track these key assets to development, whilst also
progressing its existing portfolio of assets including its Muremera Nickel
project in Burundi.
Speaking today in relation to the acquisition of Minerva, Melissa Sturgess, CEO
of Dwyka commented:
"This acquisition represents a significant transaction for Dwyka, expanding our
existing resource base whilst maintaining our regional focus in Africa.
Considerable exploration and resource definition drilling has already been
completed on a number of targets within the Minerva project areas. Dwyka has
significant cash reserves, allowing us to quickly advance these projects to
development alongside our existing assets. We also believe there is potential to
expand the existing gold resource meaning that subject to ongoing exploration,
there is an opportunity for Dwyka to establish substantial gold, platinum and
nickel resources, delivering significant short, medium and long term revenue
opportunities".
Minerva's Key Projects
To view a map showing Minerva's Key Projects, please click on the following web
link:
http://www.rns-pdf.londonstockexchange.com/rns/0995W_1-2009-7-22.pdf
Tulu Kapi Exploration Licence
The Tulu Kapi Project is an advanced exploration prospect where a 34 drill hole
programme has recently been completed by Minerva. Drilling has to date
intersected five gold bearing veins, reporting significant gold values.
Peak gold assay intersections made during the 34 hole drill programme include
the following:
+--------+--------+--------+--------+----------+
| | Depth |Depth | | |
+--------+--------+--------+--------+----------+
| Hole | From | To |Metres | Grade |
| No | | | | |
+--------+--------+--------+--------+----------+
| | (m) | (m) | (m) | (g/t |
| | | | | Au) |
+--------+--------+--------+--------+----------+
|TKBH04 | 46.41 | 84.33 | 37.92 |4.61 (1) |
+--------+--------+--------+--------+----------+
|TKBH09 | 28 | 36.3 | 8.3 | 8.55 |
+--------+--------+--------+--------+----------+
|TKBH12 | 0.5 | 19 | 18.5 | 4.34 |
+--------+--------+--------+--------+----------+
| | 56.63 | 68.4 | 11.77 | 4.62 |
+--------+--------+--------+--------+----------+
|TKBH14 | 59 | 63 | 4 | 10.24 |
+--------+--------+--------+--------+----------+
|TKBH26 | 161 | 167.6 | 6.6 | 5.1 |
+--------+--------+--------+--------+----------+
|TKBH29 | 9.68 | 14 | 4.32 | 20 |
+--------+--------+--------+--------+----------+
|TKBH20 | 200 | 205 | 5 | 9.04 |
+--------+--------+--------+--------+----------+
|TKBH21 | 0 | 31.26 | 31.26 | 4 (2) |
+--------+--------+--------+--------+----------+
|TKBH33 | 202 |209.64 | 7.64 | 8 |
+--------+--------+--------+--------+----------+
Notes:
(1) Previously reported by Minerva as a grade of 1.61g/t in error
(2) Represents an alternative interpretation of this drill hole which was
previously reported as an intersection of
15.3m within this package
of 31.26m
Work has now commenced to define a maiden JORC compliant resource from the
completed drill data. Preliminary metallurgical test work undertaken by Wardell
Armstrong International has been completed on representative core samples from
the recent drill programme. These tests indicate that the gold recovery rate
will be in excess of 94%.
Trench excavation and sampling has commenced at the Tulu Kapi Project with a
series of excavations planned to extend from the limit of the existing drill
grid in an easterly direction with a view to intersecting the expected up dip
extensions of gold mineralisation previously intersected in the recent diamond
drilling programme.
Dwyka believes the Tulu Kapi prospect has to date been underexplored and that
potential upside exists to establish a sizeable gold resource. As a result,
Dwyka plans to extend the drill programme beyond its current focus. The Company
considers that this a low risk exploration strategy with a strong possibility of
intersecting further gold mineralisation and increasing the resource base.
Yubdo Exploration Licence
Three priority targets have been identified within the Yubdo Licence; Guji,
Gudeya Guji and Dina.
Soil geochemistry, trenching and scout drilling by Minerva at the Guji Prospect
has indicated a prominent mineralised structure 1,200m in length with a peak
trench intersection of 9.6g/t Au over 68m and a drill intercept of 3g/t Au over
17m. Subject to the interpretation of planned geophysical surveys, the target is
considered drill ready. Located only 3km from Tulu Kapi, the Guji Prospect could
potentially represent a satellite mining operation providing feedstock to any
future processing plant at Tulu Kapi.
Scout drilling at the Gudeya Guji Prospect located 7km from Tulu Kapi has
intersected two mineralised quartz veins with a strike length of 200m. At
surface, rock sampling has returned peak values of 8.7g/t Au and trenching has
returned a peak intersection of 2.8g/t Au over 6m.
Scout drilling at the Dina Prospect returned peak values of 9.4g/t Au over 7.1m
from a depth of 69.6m to 76.7m and 2.4g/t au over 3.8m from a depth of 136.2m to
140m.
Dwyka plans to continue with exploration and resource definition of these
prospects.
Yubdo Platinum Mining Licence
The Yubdo Platinum Licence is held by Yubdo Platinum & Gold Development plc
("YPGD"), an Ethiopian registered subsidiary of Minerva. Minerva holds a 51%
interest in YPGD, the balance being held by Ethiopian investors.
The Yubdo platinum deposit has been known for its laterite platinum
mineralisation since the beginning of the 19th century. Several foreign and
government owned companies have successfully mined platinum and gold from the
deposit.
Minerva has operated a pilot plant scale operation, however only low platinum
recoveries have been made to date. Dr Evan Kirby, who has joined the Minerva
Board along with other Dwyka appointees, is a metallurgist with over 30 years'
experience, and has worked for Impala Platinum, Rand Mines, Rustenburg Platinum
Mines, Aquarius Platinum Limited and Sylvania Resources Limited. Dwyka will use
Dr Kirby's experience and its further in-house platinum processing expertise to
undertake a detailed review of the mineralogy and plant design. In addition,
the Company has budgeted for exploration to evaluate potential alluvial and hard
rock mineralisation that may be associated with the prospect.
Doing Business in Ethiopia
Ethiopia's economy has seen significant growth in recent years, driven by the
second largest population in Africa, the development of a free market oriented
economy and the collapse of the former military regime in the 1990s. Government
is actively privatising businesses across all sectors with many positive
initiatives including guarantees for foreign direct investment and full
repatriation of capital and profits.
Takeover of Minerva
Dwyka's takeover offer for Minerva remains open for acceptance until 1.00 p.m.
(London time) on 28 July 2009. The Company announced on 15 July 2009 that it
had received valid acceptances in respect of 80.9% of the issued shares in
Minerva. Should valid acceptances be received for 90% or more of Minerva's
shares, Dwyka will be entitled to compulsorily acquire the remaining Minerva
shares and thereby become the 100% owner of Minerva. In the meantime,
application has been made for the cancellation of the admission of Minerva's
shares to trading on AIM with effect from 23 July 2009.
For further information please contact:
Melissa Sturgess
Dwyka Resources Limited
(+44) (0)78 2555 1397 or
melissa@dwyresources.com
In United Kingdom
Richard Brown
Richard Greenfield
Ambrian Partners Limited
(+44) (0)20 7634 4700
Press enquiries
Charlie Geller or Leesa Peters
Conduit PR
+44 (0)20 7429 6604/ +44 (0)79 7006 7320
Or visit: http://www.dwyresources.com
Qualified Person
The information in this release which relates to exploration results is based on
information compiled by Tim
Craske, BSc(Hons), MAIG, AFAIM. Mr. Craske has over 25 years experience in gold
and base metals exploration and resource estimation and is the Exploration
Manager for Minerva Resources Plc. Mr. Craske is a Competent Person as defined
in the Australian Code for Reporting of Exploration Results, Mineral Resources
and Ore Reserves and has reviewed and approved this release
Wardell Armstrong International has consented to the inclusion of its name in
this announcement in the form and context in which it appears.
This information is provided by RNS
The company news service from the London Stock Exchange
END
MSCEAFXAASPNEFE
Minerva Res (LSE:MVA)
Historical Stock Chart
From Jun 2024 to Jul 2024
Minerva Res (LSE:MVA)
Historical Stock Chart
From Jul 2023 to Jul 2024