9
February 2024
Bezant Resources
PLC
("Bezant Resources", "BZT" or
"the Company")
Update for the Hope &
Gorob Copper - Gold Project, Namibia
Bezant Resources Plc ("Bezant
Resources", "BZT" or the "Company") is
pleased to provide an update for Hope and Gorob copper-gold project
situated within EPL 5796 ("the "Project") in central Namibia, approximately
100km SW of Windhoek, the capital city, and 120km SE of the major
African port of Walvis Bay. BZT holds a 70% interest in the
Project.
The Company has undertaken a
Social and Environmental Impact
Assessment (ESIA), which has been submitted to interested
and affected parties for comments, in anticipation of a near-term
issue by the Namibian Government of a Mining Licence. In addition,
a significant amount of supplementary work has been completed that
will aid optimisation of the process flowsheet, final mine design
and eventual commencement of the operation.
Highlights
·
On 27 October,
2023 the company reported an updated JORC-2012 compliant Mineral
Resource Estimate (MRE) completed by Addison Mining Services (AMS)
of 15 Mt @ 1.2% Cu and a projected average grade of 0.4 g/t Au
amenable to a Phase 1 open-pit operation and Phase 2 underground
mine. The MRE includes 1.24 Mt @ 1.6% Cu and 0.4 g/t Au (Indicated)
and 14 Mt @ 1.2% Cu (Inferred) across Hope, Gorob Vendome and
Anomaly deposits within which lies 3 Mt @ 1.7% Cu and 0.4g/t Au at
the Hope project alone (gross*).
· AMS estimates 2.4Mt of ore as
potentially amenable to an initial, low-cost, open-pit
mine
·
Following the
completion of ore sorting, magnetic separation, and flotation test
work, it has been possible to advance workstreams for a variety of
different Project inputs with the express purpose of maintaining
momentum and preparing Hope & Gorob for rapid progression into
production.
·
Social
and Environmental Impact Assessment (ESIA) scoped, managed and
undertaken by EnviroNam Consultants and has been submitted to
interested and affected parties for comments.
·
Further studies
aimed largely at design optimisation and contract negotiations
linked to initial development are also underway including project
based financing.
*Gross representing 100% estimated
Resources - Bezant
has a 70% interest in the Hope and Gorob Project
Colin Bird, Executive Chairman of
Bezant, commented "We have continued to
advance the Project pending the anticipated award of the Mining
Licence. Our time has been well-spent confirming the suitability of
Hope & Gorob ore to dry sorting technologies together with the
optimisation of various aspects of the future operation. In the
interim we will continue with essential work largely linked to
project development and keep shareholders informed of
progress."
Location: The Hope and Gorob
project lies within (1) the Swakopmund District, Erongo Region, and
(2) the highly prospective Matchless Copper Belt that hosts
multiple high-grade copper-gold deposits. The historic Otjihase
mine (>16Mt @ 2.2% Cu & 1.2g/t Au) is located 200km NE of
the Hope sub-property. Bezant owns 70% of
Hope and Gorob Mining Pty Ltd
incorporated in Namibia. This in
turn owns EPL 5796 and also 80% of Hope Namibia Mineral Exploration
Pty Ltd which owns adjacent licences, EPL 6605 and EPL 7170 which
are under renewal. The balance of the Hope and Gorob project is
held by local Namibian partners.
Resources: The current JORC
2012-compliant Mineral Resource Estimate (MRE) for Hope and Gorob
(gross*), updated for Bezant by the independent consultants Addison
Mining Services (AMS) was announced on 27 October, 2023, believed
to be amenable to a Phase 1 open-pit operation and Phase 2
underground mine, is: 15 Mt @ 1.2% Cu and a projected average grade
of 0.4 g/t Au. The MRE includes 1.24 Mt @ 1.6% Cu and 0.4 g/t Au
(Indicated) and 14 Mt @ 1.2% Cu across Hope, Gorob and associated
deposits within which lies 3 Mt @ 1.7% Cu and 0.4g/t Au at the Hope
project alone. The MRE is equivalent to 190,000t of contained
copper. AMS have identified significant potential
for open pit extraction of 2.4Mt and the prospects for increasing
the size of the open pit resource for a further 700Kt to 1 Mt thus
postulating an initial open pit with 5 years mine life at an annual
rate of 500Kt per year.
*Gross representing 100% estimated
Resources - Bezant
has a 70% interest in the Hope and Gorob Project
The Company has been actively
working on developing a work programme to prepare the project for
rapid progression into execution. The early stages of the work
programme include:
Optimisation Metallurgical Test
Work: Final test work to confirm processing design
parameters is to be completed and will include Drilling of further
PQ sized core samples from selected positions in the Hope deposit
to generate a 1-tonne composite sample representative of material
to be recovered by open pit mining and processed.
·
Detailed ore sorter design test work on coarse
fraction (Steinert Sensor Sorting Systems, Germany).
·
Magnetic separation test work on fines fraction
(Steinert Sensor Sorting Systems, Germany).
·
Final process design flotation test work and
circuit optimization (SGS, South Africa).
Opencast mine design: A
southern African specialist group has been appointed to provide
final mine design and production profiles that are to be used for
tendering of the mining contract as well as implementation. This
will also include detailed geotechnical evaluations based on the
drilling that is to be conducted.
Opencast mining contract: Several contract mining contractors that have offered their
services have been approached with a view to supplying an
outsourced mining solution. These include contractors that have
expressed interest in providing a total logistics solution
(including pre-concentrate transport). Final contract mining quotes
will be obtained on completion of the final project production
plan.
Underground mine design: On
completion of the opencast mine design, the decline access and
underground mine design are to be completed and external
consultants have been approached to assist with this work stream.
An underground mining engineer has been appointed to supervise mine
design, the application of optimised mining methods leading to
detailed scheduling and production planning.
Bulk renewable energy supply: A
potential provider has been approached to supply a design and
costing for a hybrid renewable energy solution for the mine site.
As part of the early works programme a detailed evaluation, design
and costing of the energy supply solution is to be conducted based
on final plant design parameters. The supplier has also indicated
interest in funding and supplying the solution on an IPP basis that
can be concluded once final design and costing have been completed.
This detailed design will also form the basis of licensing and
permitting applications for the bulk energy supply
solution.
Infrastructure: A potential
supplier has submitted a budget, design and costing for the supply
of major infrastructure (accommodation, workshops, offices etc.).
On the completion of detailed engineering design, final
requirements can be established and the design adjusted
accordingly.
Update on other Bezant projects
At Kanye manganese project in
Botswana the Company focus is on a preliminary in-house Mineral
Resource estimation and planning for follow-up drilling. In the
meantime, the Company's environmental management plan has been
renewed through to 29 January 2025.
IDM International Ltd through
Crescent Mining Development Corporation ("Crescent") is continuing to work on
initial Pre-Feasibility Studies on the Mankayan copper-gold project
in the Philippines which they anticipate completing later in 2024
with the aim of presenting the Mankayan Project as a globally
significant copper-gold project. In the meantime, Crescent is
continuing with its community development program in the Mankayan
area.
At Eureka project in Argentina the
Company is maintaining licence holding costs and has continued
dialogue with third parties interested in acquiring or earning into
the project.
Bezant Resources Plc
Colin Bird
Executive Chairman
|
+44 (0) 20 3416
3695
|
Beaumont Cornish Limited (Nominated Adviser)
Roland Cornish / Asia Szusciak
|
+44 (0) 20 7628 3396
|
Novum Securities Limited (Joint
Broker)
Jon Belliss
|
+44 (0) 20 7399 9400
|
Shard Capital Partners LLP
(Joint Broker)
Damon Heath
|
+44 (0) 20 7186 9952
|
https:
www.bezantresources.com
The information contained within this
announcement is deemed by the Company to constitute inside
information as stipulated under the Market Abuse Regulation (EU)
No. 596/2014 as it forms part of UK Domestic Law by virtue of the
European Union (Withdrawal) Act 2018 ("UK MAR").
Beaumont Cornish Limited ("Beaumont Cornish")
is the Company's Nominated Adviser and is authorised and regulated
by the FCA. Beaumont Cornish's responsibilities as the Company's
Nominated Adviser, including a responsibility to advise and guide
the Company on its responsibilities under the AIM Rules for
Companies and AIM Rules for Nominated Advisers, are owed solely to
the London Stock Exchange. Beaumont Cornish is not acting for and
will not be responsible to any other persons for providing
protections afforded to customers of Beaumont Cornish nor for
advising them in relation to the proposed arrangements described in
this announcement or any matter referred to in it.
Qualified Person:
The technical information contained
in this announcement has been reviewed, verified, and approved by
Colin Bird, CC.ENG, FIMMM, South African and UK Certified Mine
Manager and Director of African Pioneer plc, with more than 40
years' experience mainly in hard rock mining.
Glossary
A 'Mineral Resource' is a
concentration or occurrence of solid material of economic interest
in or on the Earth's crust in such form, grade (or quality), and
quantity that there are reasonable prospects for eventual economic
extraction. The location, quantity, grade (or quality), continuity
and other geological characteristics of a Mineral Resource are
known, estimated or interpreted from specific geological evidence
and knowledge, including sampling. Mineral Resources are
sub-divided, in order of increasing geological confidence, into
Inferred, Indicated and Measured categories.
An 'Indicated Mineral Resource' is
that part of a Mineral Resource for which quantity, grade (or
quality), densities, shape and physical characteristics are
estimated with sufficient confidence to allow the application of
Modifying Factors in sufficient detail to support mine planning and
evaluation of the economic viability of the deposit.
An 'Inferred Mineral Resource' is
that part of a Mineral Resource for which quantity and grade (or
quality) are estimated on the basis of limited geological evidence
and sampling. Geological evidence is sufficient to imply but not
verify geological and grade (or quality) continuity. It is based on
exploration, sampling and testing information gathered through
appropriate techniques from locations such as outcrops, trenches,
pits, workings and drill holes.
"Au"
Gold
"Cu"
Copper
"g/t" grammes per
tonne
"Kt"
thousand tonnes
"Mt" million
tonnes
"IPP" Independent Power
Provider