FINGRID GROUP’S HALF-YEAR REPORT 1.1.-30.6.2024
Stock exchange release 25 July 2024
FINGRID GROUP’S HALF-YEAR REPORT
1.1.-30.6.2024
Fingrid’s consolidated financial statements have been drawn up
in accordance with the International Financial Reporting Standards
(IFRS). This half-year report has been drawn up in accordance with
the IAS 34 Interim Financial Reporting standard and complies with
the same accounting principles as those presented in the Group’s
financial statements for 2023. This half-year report is unaudited.
Unless otherwise indicated, the figures in parentheses refer to the
same period of the previous year.
- The transmission reliability rate of Fingrid’s grid was 99.9995
(99.99991) per cent. Fingrid transmitted in its grid a total
of 82 (81) per cent of the total electricity transmission in
Finland. Electricity consumption in Finland grew to 42.7 (39.9)
terawatt hours.
- The company’s investment programme is moving forward as
planned, and investments were higher than in the previous year. The
company estimates that the gross capital expenditure over the next
four years will come to roughly EUR 2 billion, nearly half of which
is committed.
- The renewable electricity production capacity connected to the
main grid grew by 585 (772) MW. The number of main grid connection
enquiries for new projects continued to grow.
- Turnover for January–June was significantly higher than in the
previous year. The balance service’s share of the company’s
turnover was 57 (56) per cent. The grid investments and expansion
of the operations as well as the weather-dependency of the power
system have increased the company’s costs.
- Congestion income was used for the benefit of Fingrid’s
customers and grid service fees were waived in January, February
and June. This, and growing costs, were compensated by recognising
EUR 274.9 (139.0) million in congestion income in the company’s
result.
- Operating result, excluding the change in the fair value of
derivatives linked to operational activities, amounted to EUR 150.9
(87.1) million. The company’s allowed profit has risen due to the
higher interest rate level and extensive investment programme.
Profit before taxes was EUR 115.7 (-85.0) million. The company’s
financial position remained strong.
|
KEY FIGURES, MEUR |
1-6/24 |
1-6/23 |
change % |
1-12/23 |
|
Turnover |
746.7 |
554.8 |
34.6 |
1,193.2 |
|
Operating result * |
150.9 |
87.1 |
73.2 |
186.1 |
|
Earnings before taxes * |
147.4 |
85.3 |
72.8 |
186.0 |
|
Result for the period |
92.6 |
-67.9 |
236.2 |
1.2 |
|
Net cash flow from operations |
111.3 |
174.8 |
-36.3 |
219.3 |
|
Accumulated congestion income |
139.2 |
124.9 |
11.4 |
317.0 |
|
Capital expenditure, gross |
198.0 |
130.7 |
51.5 |
322.0 |
|
Interest-bearing net borrowings |
700.1 |
353.2 |
98.2 |
535.2 |
|
* Excluding the change in the fair value of derivatives |
|
|
|
Review by the President & CEO: The energy system
cleanup continues – investments in the green transition necessary
at all levels
“Based on Fingrid’s forecasts, the production and consumption of
electricity will continue to grow. Finland is an attractive
location for green investments. The number of grid connection
enquiries for new electricity production continues to grow,
amounting to roughly 50 GW in new enquiries during the first half
of 2024. Investments in electricity production, both wind and solar
power, have already been underway for a long time, but also several
electricity consumption-increasing investments have started up,
including electric boilers, data centres and energy storage
facilities.
The increasing need for electricity transmission capacity and
grid connections has become a topic of public debate. The
production and consumption of electricity is concentrated in
different areas of Finland, which increases the need for
transmission capacity. In addition to the transmission needs
arising from wind power production in western Finland, the
transmission and connection needs of eastern Finland, the capital
region and offshore wind power have also become topical. Fingrid
has collaborated with several stakeholders to find solutions both
in eastern Finland and around Helsinki, and published a technical
study on the possibilities to connect offshore wind power to the
main grid in June.
The main grid is being expanded at a record pace. During the
review period, Fingrid started up the work to reinforce the Lake
Line transmission connection between Vaala and Joroinen and decided
to build a 400-kilovolt transmission line named Lowlands Line. The
new transmission and connection capacity upgrades serving the
capital region also progressed, with the commencement of work on a
new underground cable connection in Helsinki and the investment
decision on the expansion of the Tammisto substation.
To enable new grid connections more rapidly and to more
effectively utilise the existing main grid, Fingrid has been
preparing a new service level model for grid services and proposed
modifications to the principles of the grid connection fees.
The extensive grid investment programme responding to the
customer’s and transmission needs and the increasingly
weather-dependent power system will increase Fingrid’s costs. Due
to this, Fingrid has decided to collect grid service fees from
customers between July and December 2024 in accordance with the
valid pricing.
The transformation of the power system needs the support of an
evolving electricity market. In June, Finland started to use the
energy marketplace for the automatic Frequency Restoration Reserve
(aFRR), enabling trading closer to the consumption hour and thereby
increasing the supply of these reserves. The go-live of a new
auction system updated three times a day, designed to support
continuous trading, also took place on the European intraday
markets in June.”
Financial result and financing
The Group’s turnover from January through June increased, while
Fingrid’s operational costs grew. The drivers of higher operational
costs included the extensive grid investment programme, expansion
of the power system, increasingly weather-dependent electricity
production and the measures needed for ensuring high-quality
electricity transmission amid the rapid transition. Balancing the
power system results in increasing fluctuations in Fingrid’s
turnover, which stems from the drastically increased
weather-dependency of electricity production, forecast uncertainty
in electricity production and consumption, and from the temporary
scarcity of balancing capacity. The pricing of Fingrid’s services
follows the cost development and the allowed regulatory profit set
for the operations over time. The use of accrued congestion income
to cover the increased costs of transmission grid operations and to
waive grid service fees has helped to balance out the seasonal
variations in the company’s result as well as customer pricing.
The turnover of the balance service grew from the comparison
period and amounted to 56 per cent of the Group’s total turnover.
Income from grid service fees and grod connection fees remained on
a par with the comparison period. Fingrid waived grid service fees
in January, February and June. Finland’s electricity consumption on
which grid service revenue is based was 42.7 (39.9) terawatt hours
in 2024. The congestion income accrued to Fingrid from cross-border
connections amounted to EUR 139.2 (124.9) million, of which
Fingrid’s share was EUR 112.9 (90.0) million. A total of EUR 234.2
(94.6) million in congestion income was recognised in turnover to
cover the waiving of grid service fees and increased operating
expenses, and EUR 40.7 (44.4) million in other operating income to
cover Financial Transmission Rights and cross-border capacity
costs.
The Group’s total costs, excluding the change in the fair value
of commodity derivatives, amounted to EUR 637.9 (513.0) million.
The costs of purchased imbalance power increased to EUR 307.1
(236.5) million due to increased imbalances and the higher price of
balancing power. Fingrid’s operational costs, excluding costs of
balancing power procurement and the FTR costs related to
cross-border capacity costs for the cross-border capacity between
Estonia and Finland, increased from the comparison period to EUR
304.5 (241.6) million. The factors driving the cost increase
include the expansion of operations necessitated by the power
system growht and change, the volatility in the price and
transmission of electricity which increases loss power costs, and
the growing need for reserves for securing the system security of
the grid and the power balance. The Group’s costs are presented in
more detail in the Costs table of half-year report.
In the review period, the company’s total investments grew to
EUR 198.0 (130.7) million due to increasing capital expenditure to
enable the growth of electricity production and consumption and the
green transition in Finland. The main grid development plan for the
next ten years envisages EUR 4 billion in capital expenditure. The
company estimates that gross investments will come to some EUR 2
billion over the next four years, including the current year. The
investment commitments concerning future expenditure items came to
EUR 848 million on 30 June 2024.
The Group’s operating profit excluding the change in the fair
value of derivatives was EUR 150.9 (87.1) million. The Group’s
profit before taxes was EUR 115.7 (-85.0) million. The result of
the review period improved compared with the comparison period due
to the increased capital expenditure and higher interest rates and
the consequently larger allowed regulatory profit as well as due to
the change in the fair value of electricity derivatives. Profit for
the review period was EUR 92.6 (-67.9) million and comprehensive
income was EUR 92.6 (-68.0) million. The equity ratio at the end of
the financial year was 18.7 (31 December 2023: 20.1) per cent.
The Group’s net financial costs from January through June were
EUR 9.4 (6.1) million. The net financial costs increased due to
increased debt. The increase in net financial costs was curbed by
the increased finance income from cash and cash equivalents and by
realised interest rate hedges. The change in the fair value of
financial derivatives was EUR 5.5 million negative (EUR 3.7 million
negative).
Interest-bearing borrowings totalled EUR 1,308.0 (31 December
2023: 998.1) million, of which non-current borrowings accounted for
EUR 1,060.9 (654.7) million and current borrowings for EUR 247.1
(343.5) million.
During the review period, the company’s cash assets fell due to
the use of congestion income for waiving grid service fees and for
covering the rising costs of the grid operations. Cash and cash
equivalents and other financial assets totalled EUR 529.0 (387.0)
million on 30.6.2024. The company’s financial position remained
strong.
Customers
Fingrid published its production and consumption outlook, which
was updated during the spring, envisioning significant growth in
both electricity consumption and production in Finland by the end
of the decade. The biggest growth drivers are the electrification
of industrial processes and heating, and electricity consumption
based on hydrogen economy.
Compared with earlier forecasts, the forecasted growth of wind
power production is slightly lower for the next few years, whereas
the forecasted growth of solar power is higher, especially for the
next few years. The long-term growth trends for wind and solar
energy remain largely unchanged and support the strong growth of
the power system.
The volume of electricity production main grid connection
enquiries grew significantly since the corresponding period last
year, and their total capacity currently amounts to 411 GW, of
which 49 GW accounted for the enquiries received during the review
period. The majority of the enquiries concern onshore wind energy,
but connection enquiries for offshore wind energy and solar power
plants are also growing. In the first half of 2024, 585 MW (772 MW)
of new renewable production was connected to the grid.
The increased production of clean electricity and reliable
electricity transmission have had a significant impact on
industrial consumer demand. In various parts of Finland, numerous
projects related to clean electricity consumption are under
planning and under way in the hydrogen industry, in data centres,
and in the heating sector and the metals industry, and important
new investment plans were unveiled this past spring.
Fingrid released a study of the possibilities to connect
offshore wind power to the main grid during the review period. The
study identified five potential connection areas where linking
offshore wind farms to the main grid on the Finnish mainland is
technically possible: Ulvila, Närpiö, Vaasa, Raahe and Raisio. The
Inkoo area is another potential connection area if offshore wind
power development becomes feasible also in Finland’s southern sea
areas. Fingrid is seeking feedback from stakeholders on the
possibilities to connect offshore wind power, on the basis of which
the preliminary suggestions for connection points will be defined
during the autumn of 2024.
Fingrid proposed reforms to the structure of grid service fees
during the review period. The proposed new grid service fee
structure aims to increase the efficiency of grid operations to
support rapid grid connections of new electricity production and
consumption and to create new methods of main grid transmission
management. The grid fee reform will proceed with stakeholder
consultations and more details will be published during the second
half of 2024.
Main grid investments
A total of 560 kilometres of 400 kilovolt transmission lines and
roughly 150 kilometres of 110 kilovolt transmission lines are
currently under construction in the main grid. A total of 79
substation projects are being implemented. Finland’s main grid
consists of roughly 14,500 kilometres of transmission lines and 124
substations.
The grid investments will be record-high in 2024, which will
reinforce Finland’s competitiveness in attracting industrial
investments and promote the achievement of Finland’s carbon
neutrality goals by 2035. The investments in the main grid will
enable new customer connections, electricity system growth,
increased system security of the whole power system security as
well as electricity market operations.
During the review period, Fingrid decided on investments to
construct a 400-kilovolt transmission line named Lowlands Line and
to construct new substations and expand existing ones. The Lowlands
Line, running from Kalajoki to Jämsä, will be a new
400-kilometre-long 400-kilovolt main transmission line to support
the transmission of wind power, with production heavily
concentrated on Finland’s western coast, to the consumers. The
project is due for completion in 2027.
Fingrid started the construction of the 300-kilometre long Lake
Line from Vaala to Joroinen during the review period. The
construction of an underground cable connection for the main grid
was started in Helsinki during spring 2024. This joint project
between the City of Helsinki, Helen Sähköverkko and Fingrid will
meet the needs of growing electricity consumption in the capital
region. The new underground cable is due for completion in
2026.
The Tammisto substation in Vantaa, a key hub of electricity
transmission in the Helsinki region, will be expanded with a third
transformer. Fingrid will also expand a substation located in
Kajaani and build new substations in Kouvola and Hamina. A
substation located in Jyväskylä will be modernised to improve
system security. Fingrid also made an investment decision on the
procurement of 20 capacitors for nine of its substations to
increase the north–south transmission capacity.
Fingrid is committed to the mitigation of any negative climate
impacts from grid construction. The transmission system operator is
taking a major step towards more sustainable construction methods
by procuring for the first time low-emission steel structures, made
from recycled steel, for three new substations, which will
significantly reduce the carbon footprint of construction work.
Another sustainability measure is the use of SF6-free technology
for the gas insulation of substations. Fingrid is committed to cut
back the use of the environmentally harmful SF6 gas at its
substations and to promote the adoption of new technologies.
Fingrid decided on the procurement of 7,300 kilometres of
transmission line conductors made from low-emission aluminium
during the review period. This will significantly reduce the carbon
footprint of the conductors to be installed.
Power system operations
The long and exceptionally cold spell during the first week of
2024, combined with failures in thermal power plants, resulted in
the most challenging period of the winter in terms of adequate
supply of electricity. Due to the strained power balance, Fingrid
raised its state of readiness on 4 January 2024. Despite the
challenging circumstances, there was enough electricity and Fingrid
cancelled the heightened state of readiness on 5 January 2024. A
significant factor was the price flexibility of consumers, which
also played a part in ensuring the availability of electricity.
Last winter’s consumption peak was reached on Wednesday 3
January 2024, between 7 and 8 pm. The average consumption during
that hour was 14,993 MWh. The production peak of the winter, also
Finland’s all-time high in electricity production, 14,246 MWh, was
measured on 26 January 2024 between 6 and 7 pm. This peak
production hour of the winter was comprised of large amounts of
wind power (roughly 80% of the installed capacity) and the nuclear
power plants running at full power.
In January–June, the system security of Fingrid’s grid system
was at a good level, despite several disturbances caused by
frequent thunderstorms early in the summer. The grid’s transmission
reliability rate during the review period was 99.9995 (99.99991)
per cent.
During the review period, disturbance-clearing readiness was
raised in southern and central Finland on 16 and 17 February due to
freezing rain.
The transmission capacity between Finland and Sweden operated
reliably, but the link with northern Sweden was constricted during
the review period, in May and June, due to construction and
maintenance work in the Finnish and Swedish main grids and due to
the construction of the new Aurora Line transmission
connection.
The transmission capacity between Finland and Estonia operated
under limitations since 26 January 2024 due to a failure of the
EstLink 2 connection. The location of the failure was pinpointed
off the Estonian coast and the repair work will continue until the
end of August 2024. Fingrid expended EUR 2.6 (0.2) million in
countertrade during the first half of 2024.
Electricity market
The price of electricity was affected during the review period
in particular by the exceptionally cold weather at the start of
2024, the failure of EstLink 2 in late January 2024 and by the
delays in the Olkiluoto 3 nuclear power plant’s annual
maintenance.
Regional price differences have levelled out compared to the
corresponding period of the previous year. Congestion income
between Finland and Sweden in January–June totalled EUR 172.8
(100.5) million, and between Finland and Estonia EUR 51.3 (104.7)
million. Fingrid’s share of the congestion income from those
cross-border connections is 50 per cent.
The importance of system balancing increases as the production
of renewable electricity grows. Fingrid lowered the balance service
fees for balance responsible parties to EUR 1.33/MWh starting from
1 March 2024. The lower fee is due to the lower-than-expected costs
of power system reserves.
The continuing development of the electricity market and new
solutions will transform the market in a more real-time and
market-driven direction. The increasing weather dependence of the
power system highlights the significance of the flexibility in
consumption and production and the related opportunities, as well
as a broad electricity market.
The go-live of the new auction system of the intraday energy
markets took place in June 2024. The Intraday Auctions provide more
adequate price formation and balance the demand and supply closer
to the time of production. The auctions system is part of the
common European intraday markets, which aim to promote the
effectiveness and integration of the internal energy market.
The new automatic Frequency Restoration Reserve (aFRR)
marketplace went live in Finland on 12 June 2024. The planned
extension of the Frequency Restoration Reserve to PICASSO, the
European platform for the exchange of aFRR energy, was postponed to
autumn 2024 due to technical challenges on the new marketplace.
Fingrid and Nord Pool started co-operation to impose regular
market surveillance on the aFRR energy market after the go-live of
the new aFRR energy market. Under this arrangement, Nord Pool’s
market surveillance department is in charge of regularly monitoring
the aFRR energy market and reporting any violations to Fingrid.
Personnel
The Group’s total headcount has increased as a result of the
expansion of Fingrid’s operations and the growth of the power
system. The number of employees averaged 577 (514), with an average
of 515 (460) in a permanent employment relationship. Personnel
costs amounted to EUR 24.1 (21.3) million. Wages and salaries
amounted to EUR 20.4 (17.9) million, which equals 2.7 (3.2) per
cent of the turnover.
Fingrid received an excellent employee net promoter score (eNPS)
of +68 (on a scale of -100 to +100) in the review period’s
personnel survey and a positive response to the content of jobs,
the company as an employer and supervisory work. MIELI Mental
Health Finland awarded Fingrid with its ‘A feel-good workplace’
(Hyvän mielen työpaikka) label for the efforts promoting mental
health and well-being.
This year, Fingrid is employing a total of 66 employees in
various summer jobs throughout Finland. As in previous years, the
company is part of the Responsible Summer Job campaign, which
challenges employers to offer young people successful and
high-quality summer job experiences.
Legal proceedings and proceedings by
authorities
The EU Agency for the Cooperation of Energy Regulators (ACER),
on 14 September 2022, made a decision on long-term price risk
hedging opportunities between Finland and Sweden. In its decision,
ACER requested that the Finnish and Swedish TSOs ensure the
availability of other long-term cross-zonal hedging products and
develop the necessary arrangements for providing hedging
products. Fingrid filed an appeal against the decision to
ACER’s Board of Appeal on 14 November 2022. The Board of Appeal
issued its resolution on the appeal on 24 October 2023, where it
confirmed ACER’s original decision. Fingrid submitted to the Energy
Authority on 22 December 2023 its proposal for improving the price
risk hedging opportunities between Finland and Sweden.
Fingrid received an expropriation permit for the widening of the
Torna–Lautakari right-of-way for the neutral line on 27 October
2022. In the kick-off meeting for the expropriation procedure on 1
December 2022, the expropriation committee decided that the
expropriating party is obligated to assume responsibility for the
tree stands within the scope of the rights and restrictions set in
the expropriation permit, unless otherwise agreed. The final
meeting of the expropriation procedure was held on 16 November
2023. Fingrid has appealed the decision concerning the
Torna–Lautakari tree stands’ expropriation to the Southwest Finland
District Court’s Land Rights Court on 22 December 2023.
On 20 December 2023, Fingrid Datahub Oy filed a proposal with
the Energy Authority to change the model concerning Fingrid Datahub
Oy’s financial regulation for the regulatory period 2024–2027 and
simultaneously proposed that the regulatory model be developed
further.
On 2 January 2024, Fingrid appealed the Energy Authority’s
decision on the terms and conditions of balance service at the
Market Court. The appeal mainly concerns the collateral model for
balance responsible parties presented in the decision. In November
2023, the Energy Authority issued a decision on the terms and
conditions for balance responsible parties, which include the
principles for how collateral requirements are determined, to enter
into force on 1 December 2024. The Energy Authority’s decision
includes major changes to the current collateral terms and
conditions and sets apart Finland’s collateral model from that used
in other Nordic countries. The most significant changes to the
current collateral model include a major reduction in the required
collaterals, elimination of the requirement to provide an adequate
additional collateral and a possible collateral ceiling.
On 29 January 2024, Fingrid appealed the Energy Authority’s
decision on the methods concerning the specification of the profit
for the electricity transmission grid operations for the sixth
regulatory period 1 January 2024–31 December 2027 and seventh
regulatory period 1 January 2028–31 December 2031 at the Market
Court. According to Fingrid’s assessment, the decision on the
regulatory methods is a significant weakening of the electricity
transmission grid operations’ reasonable profit regulatory method
that expired at year-end. In Fingrid’s view, the assessment of
impacts in preparing the regulatory model decision has been
deficient and there are still issues open to interpretation related
to the presented decision. Fingrid’s goal is a solution that would
also enable the future development of the grid, allowing the
hundreds of billions in green transition investments in Finland to
be implemented as planned.
On 15 February 2024, Fingrid appealed the decision given by the
Energy Authority on 11 January 2024 on the scope of the national
transmission system operator’s systems responsibility regarding the
grid connection of the Olkiluoto 3 nuclear power plant at the
Market Court. Teollisuuden Voima Oyj (“TVO”) lodged a request for
an investigation with the Energy Authority on 25 May 2022 related
to the claims by TVO that Fingrid has neglected its obligation to
develop the main grid as stated in the Finnish Electricity Market
Act and/or other applicable legislation, and that, as a result, it
has placed unlawful restrictions on connecting the Olkiluoto 3
nuclear power plant to the grid, and that Fingrid is in breach of
its administrative obligations linked to carrying out its public
administrative task. The Energy Authority states in its decision of
11 January 2024 that Fingrid fulfilled its development, connection
and transmission obligations in accordance with the Electricity
Market Act. The Energy Authority also found the 1,300 MW power
limit specified in Fingrid’s connection terms justified and did not
find Fingrid to have restricted Olkiluoto 3’s access to the grid.
In its decision, the Energy Authority sees, however, that Olkiluoto
3’s grid load limitation falls under Fingrid’s responsibility based
on a transmission system operator’s special protection system as
intended by legislation and that Fingrid is in breach of Article 9
of the Commission Regulation (EU) 2017/1485 establishing a
guideline on electricity transmission system operation and its
obligation in line with Section 10, Subsection 1 of the Act on the
Control of the Electricity and Natural Gas Market (2013/590) to
bring the determination principles for fees it applies before the
Energy Authority for approval prior to their implementation.
Fingrid delivered the above-mentioned determination principles for
fees, the related memorandum of justifications and terms &
conditions, and the statements received during stakeholder
consultation to the Energy Authority on 30 April 2024. Fingrid
proposes that the costs of the Olkiluoto 3 grid load limitation be
in their entirety born by TVO because the Olkiluoto 3 grid load
limitation only benefits the company itself and because TVO is the
only party capable of controlling Olkiluoto 3’s output in relation
to the costs of the Olkiluoto 3 grid load limitation.
HiQ Finland Oy (name changed on 6 February 2024 to Frends
Technology Oy) presented a claim for a revised decision and filed
an appeal with the Market Court on Fingrid’s procurement decision
related to the procurement of the user license for an integration
platform on 6 February 2024. On 16 February 2024, Fingrid revoked
its procurement decision and reported on 19 February 2024 to the
Market Court that the procurement decision had been revoked.
Following the revoking of the procurement decision, the Market
Court will decide on the claim for legal costs presented by HiQ
Finland Oy. The Market Court issued its decision on 21 May 2024 and
adjusted Frends Technology Oy’s claim for legal costs downwards.
The remaining legal costs to be paid by Fingrid are EUR 4,500. No
appeals against the Market Court’s decision have been filed.
Fingrid filed a complaint at the District Court of Oulu on 24
May 2024 concerning a decision on an expropriation procedure issued
on 25 April 2024 in a compensation case due to the loss of a rock
material extraction site. Fingrid finds no grounds for awarding
compensation in this case because the extraction site was located,
at the time when Fingrid assumed control of the right-of-way, far
from the right-of-way and the possibility to expand rock material
expansion to the vicinity of the right-of-way will be available for
several decades according to the estimations presented at the
expropriation meeting. The rock material extraction site remaining
within the right-of-way therefore cannot be regarded to have any
unambiguous compensable value.
Events after the review period and outlook for the rest
of the year
On 25 July 2024, the Board of Directors decided, in compliance
with the authorisation granted by the AGM, that the second
instalment of dividends shall be paid after the half-year report
has been approved and the Board has assessed the company’s
solvency, financial position and financial performance. Based on
the authorisation received by the Board, the second dividend
instalment of EUR 18,100.00 for each Series A share and EUR
6,600.00 for each Series B share, totalling EUR 45,842,000.00 in
dividends, will be paid on 30 July 2024.
Increasing weather dependence in electricity production makes it
more difficult to forecast electricity transmission and increases
fluctuations in the national power balance, resulting in an
increasing need for resources to balance power system and more
advanced operating models. The availability of flexible power
production and power system flexibility will influence the cost of
the reserves necessary for managing the power balance and
safeguarding system security. Fluctuations in the electricity
market prices and availability of flexibility will increase
uncertainty in the company’s market-based costs. The extensive need
for investments meeting customer needs as well as the expansion and
transformation of the power system will increase Fingrid’s costs.
The recognition of congestion income accrued to Fingrid in the
company’s turnover and other operating income will be continued.
The company’s debt service capacity is expected to remain stable.
The company has not changed its earnings guidance from what is
stated in the financial statements of 27 February 2024.
- Fingrid Group Half-Year Report 2024
Fingrid 29 (LSE:38FE)
Historical Stock Chart
From Nov 2024 to Dec 2024
Fingrid 29 (LSE:38FE)
Historical Stock Chart
From Dec 2023 to Dec 2024