Toachi Mining Inc., (“Toachi” or the “Company”)
(TSX-V:TIM) (OTCQB:TIMGF) is pleased to announce the positive
results of the independent Preliminary Economic Assessment (“PEA”)
for the La Mina VMS Project (“Project”) located in the Province of
Cotopaxi, Ecuador. The PEA was prepared pursuant to National
Instrument 43-101 (“NI 43-101”) and has an effective date of March
30th, 2019. A NI 43-101 technical report summarizing the PEA (the
“Technical Report”) will be available on SEDAR no later than June
20th, 2019. All references to currencies herein are in U.S.
dollars.
This press release features multimedia. View
the full release here:
https://www.businesswire.com/news/home/20190430005522/en/
Figure 1 (Graphic: Business Wire)
PEA Highlights 1
- The underground mine produces diluted
polymetallic mine material for processing at an 800 tonne per day
capacity on-site flotation mill. The mill products (i.e. a Cu/Pb
concentrate and a Zn concentrate) are sold to smelters in
Asia.
- The mine plan encompasses 2 million
tonnes of potentially mineable mineralization, average head grade
10 Au Eq g/t.
- The Project would operate for 7.1 years
with a Net Present Value (“NPV”) (5%) of $52 million after tax, an
Internal Rate of Return (“IRR”) of 24% after tax, and an after tax
payback period of 3.5 years.
- The life of mine (LOM) Net Smelter
Return (NSR) is $402M which equates to 318,000 troy oz Eq. based on
2 Mt milled and the projected $1,264/ troy oz Au gold price. The
NSR does not include any revenue from lead contained in the Cu/Pb
and Zn concentrates.
- The LOM net direct cash costs (C1)
amount to $74/t milled. The Project’s C1 cash cost, on an
equivalent troy oz Au/t milled basis, is $470/troy oz Eq Au.
- The All-In Sustaining Cost (AISC) is
$101/t milled. The Project’s AISC, on an equivalent troy oz Au/t
milled basis, is $640/troy oz Eq Au.
- The results of metallurgical testing
completed to date indicate that there are opportunities for
improvement in the project economics.
- The Company reports local community
support for the Project with few dissenters and is engaging local
communities. Ecuador has a regulatory regime for the social and
environmental assessment and permitting of mines.
PEA Results Summary
IRR Before-Tax / After-Tax
38% / 24% NPV @ 5% - Before-Tax / After Tax
$100 M / $52 M NPV @ 8% - Before-Tax / After
Tax $81 M / $39 M NPV @ 10% - Before-Tax /
After Tax $70 M / $32 M Payback – after
starting mineral processing - After tax 3.5
years Nominal Production rate – dry metric tonnes/day (dmt/d)
800 tpd Total tonnes processed LOM (dmt)
2 million tonnes Average head grade over life
of mine (LOM) 10 g Au Eq /tonne Estimated Mine
Life 7.1 years Total Gold production (payable
oz) 112,000 oz Total Silver production
(payable oz) 1,228,000 oz Total Copper
production (payable lbs) 92 M lbs Total Zinc
production (payable lbs) 76 M lbs LOM net
direct cash cost (C1) ($/tonne) $74 / tonne
All-In Sustaining Cost (AISC) ($/tonne) $101 /
tonne Initial Capital Cost $70.3 M Sustaining
and Closure costs $47.6 M
Cautionary note: The PEA was prepared in
accordance with National Instrument 43-101 Standards of Disclosure
for Mineral Projects ("NI 43-101"). Readers are cautioned that the
PEA is preliminary in nature and includes the use of Inferred
Mineral Resources that are considered too speculative geologically
to have the economic considerations applied to them that would
enable them to be categorized as Mineral Reserves, and there is no
certainty that the results of the PEA will be realized.
The PEA was led by independent resources, mining, metallurgy,
processing and environmental consultants, with support from the
Toachi technical team. The principal consultants include: SGS
Canada Inc., Geological Services (“SGS”); SGS Lakefield, SGS
Bateman, Brian Wolfe and Dr. Simon Strickland Meik. A number of
other independent consulting firms and potential vendors also
provided information used in the PEA.
Alain Bureau, President & CEO, stated, “Today’s PEA
demonstrates the La Mina VMS Project is a high-return, capital
efficient and low-operating cost project. This evaluation is a
significant milestone, showing a polymetallic project with an
After-Tax IRR of 24% and NPV (5%) of US $52 million. The PEA is
based on the production of two marketable base metal concentrates
with high values in precious metals. This also brings a strong
foundation for Toachi to build on as the deposit is open at depth,
and recent exploration indicates the possible continuity of the
mineralised footprint to the north. It is important to mention the
present PEA does not include the recently discovered “Guatuza zone”
as well as Toachi’s plans to initiate further metallurgical and
processing tests to pursue the optimization of the Project.”
PEA Results
The cash flow model is based on developing the Upper North zone
of deposit, followed by the Lower North zone before mining the
South zone of the deposit. The cash flow model encompasses the
CAPEX and OPEX costs for mining, processing, tailing,
infrastructure, G&A, and environment. The Project has a
fifteen-month pre-production development period. Production ceases
in year 8. The economic criteria used in the cash flow model are
shown below.
Concentrate
Production LOM - dmt
Metal Recovery Payable
Copper
20.9% Cu content
218 dry kt Au
43.1% 96%
Ag 47.9% 90%
Cu 89.4%
96.5% Pb 71.6%
0% Zn
20.0% 0% Zinc
51.2% Zn content
94 dry kt Au 26.6%
65% Ag
26.1% 70% Cu
4.5% 0% Pb
13.4% 0%
Zn 70.5%
85%
Project income is derived from the sale of the copper/lead and
zinc concentrates and includes the following:
- Metal grades in each concentrate
- Logistic and transport costs
- Treatment charges
- Refining charges
- Projected 8% moisture in
concentrates
- Penalties
- Minimum deductions
- Payable rates
The after tax cashflow includes deductions for the
following:
- Amortization
- Ecuadorian royalty
- Income taxes
- Export duties
- Employees profit sharing
The cash flow includes the following operating costs and
G&A:
OPERATING COST
LOM average ($/t milled) MINE
- Stoping cost
$26.14
- Mine support operations cost
$20.01
- Mine equipment lease cost
in sustaining capex
- Sub-total mine OPEX
$46.15 PROCESSING
- Power
$4.22
- Labour
$4.70
- Reagents
$11.58
- Grinding media
$3.55
- Repair materials and operating
supplies
$1.60
- Liners and wear materials
$0.97
- Sub-Total Mill OPEX
$26.62 Tailings storage facility
& effluent treatment $1.23
TOTAL OPEX $74.00 G&A
$5.15 TOTAL
$79.15
PEA Pre-Production CAPEX
The mine CAPEX includes development, infrastructure, equipment
and G&A and indirect costs. The process CAPEX includes the
mill, general site infrastructure, tailings storage facility,
effluent treatment plant, General & Administration (G&A)
and Owners’ costs. The preproduction capital is shown below.
AREA
ITEM CAPEX Mine
Infrastructure $3.5 M
Development $5.3 M
Equipment $4.2 M
G&A and indirects
$4.0 M Sub-Total Mine
$17.0 M Mill and General Site Process
$40.2 M Tailings and effluent
Tailings & effluent treatment $ 3.1
M
Sub-Total Mill & General Site
$43.3 M Contingency
$10.0 M Total Preproduction CAPEX
$70.3 M
PEA Economic Analysis
IRR and NPV values were extracted from the cashflow model. Three
year trailing monthly average metal prices as of January 31st, 2019
were used in the Updated Mineral Resources Estimate and the PEA
cashflow model. The results of the PEA economic analysis are shown
below.
Before-tax
After-tax IRR 38%
24% NPV(5%) $100 M $52 M
NPV(8%) $81 M $39 M
NPV(10%) $70 M $32 M
PEA Results Sensitivity
The Project is most sensitive to changes in income and less
sensitive to changes in opex and capex as shown in Figure 1.
Ownership
The property is owned by Compania Minera La Plata S.A.
(restructured from Sultana Del Condor Minera S.A.) and entered into
an agreement with Ferrum (which later became Toachi Mining Inc.) on
October 28th, 2015. Ferrum announced the signing of a letter of
intent with Sultana on February 11, 2016, pursuant to which Ferrum
has been granted the option to acquire up to a 75% interest in the
Project over a period of four years. To earn a minimum of 60%
interest, Ferrum must make cash payments totalling US$2.0
million and incur expenditures totalling US$4.0 million.
Sensitivity Analysis of the Updated Mineral Resources
Estimate - Base case at 4.0 g/t Au cut-off grade
Cutoff(AuEq – g/t)
Tonnage(kt) Au(g/t)
Ag(g/t) Cu(%) Pb(%) Zn(%)
Au(koz) Ag(koz) Cu(kt)
Pb(kt) Zn(kt) 0 2,553
3.2 39.8 2.5
0.5 3.5 263 3,264
65 13 90 1
2,528 3.2 40.1 2.6
0.5 3.6 263 3,262
65 13 90 2
2,373 3.4 42.4 2.7
0.5 3.8 260 3,238
64 13 89 3
2,055 3.8 46.9 3.0
0.6 4.2 251 3,097
62 12 87
4
1,846 4.1
50.0 3.3 0.6
4.6 244
2,966 61 12
84 5 1,655 4.4
53.7 3.5 0.7 4.9
236 2,860 59
11 80 6 1,461 4.8
58.5 3.8 0.7
5.2 225 2,747 56
11 75 7 1,320
5.1 62.4 4.1 0.8
5.5 217 2,647
54 10 72 8 1,195
5.4 66.0 4.3
0.8 5.8 208 2,535
51 10 69 9
1,111 5.7 68.6 4.4
0.9 5.9 202 2,449
49 10 66 10
1,019 5.9 71.4 4.6
0.9 6.1 194 2,340
47 9 63
Updated Mineral Resources Estimate Notes:
- This Updated Mineral Resources Estimate
as of March 30, 2019 was prepared in accordance with NI 43-101 and
CIM Standards (2014).
- The Updated Mineral Resource Estimate
tonnages have been rounded to the nearest 10,000 and AuEq, Au, Ag,
Cu, Pb and Zn grades have been rounded to one decimal. Troy ounces
have been rounded to kilo troy ounces (koz), and tonnes of Cu, Pb,
and Zn have been rounded to kilo-tonnes (kt).
- The Updated Mineral Resources Estimate
for the La Mina VMS polymetallic deposit have been classified as
Inferred Mineral Resources.
- The Updated Mineral Resources has been
reported at various cut-off grades to demonstrate the grade-tonnage
relationship. The preferred reporting cut-off grade is 4 g AuEq / t
(4 gold equivalent grams / tonne) based on an in-situ gross value
of $165 per tonne. The AuEq / t formula is:AuEq ppm = Au ppm + (Cu
% * 1.454) + (Ag ppm * 0.013) + (Zn % * 0.654) +
(Pb %*0.532)
- The Updated Mineral Resources could be
accessed by developing a mine ramp and are considered reasonable
prospects for economic extraction in the foreseeable future.
- The Updated Mineral Resources Estimate
is based on the following three year trailing monthly average
prices of metal, as of January 31st, 2019:$1,264/ troy oz
Au$2.68/lb Cu - $5,909 / t Cu$1.21/lb Zn - $2,656 / t Zn$16.64/
troy oz Ag$0.98/lb Pb – $2,162 / t Pb
- This Updated Mineral Resources Estimate
was prepared by Brian R. Wolfe, BSc (Hons), MAIG.
- Mineral Resources do not have
demonstrated economic viability.
- This Updated Mineral Resources Estimate
may be materially affected by environmental, permitting, legal
title, taxation, socio-political, marketing or other relevant
issues.
QA/QC Statement
Toachi implemented a concise QA/QC program for all their drill
hole assay data. Toachi completed a total of 80 diamond drill holes
for a total of 13,747 m between August 2016 and July 2017 under the
supervision of the project manager for Toachi. The drill holes were
drilled using diamond drill technique, with 12,557m HTW diameter
core (71.0mm), with 1,137m of NTW (56.2mm) and 53m of BTW (42.1mm)
diameter. Toachi implemented a strict QA/QC regiment related to all
aspect of core handling, sampling and logging.
Both labs (ALS and MSA) also completed their own internal
checks. This data, along with the Toachi Mining checks was
validated using QCAssure software. Toachi Mining also conducted
additional QA/QC checks on all their data by submitting
approximately 7% of their drilling database to an independent
laboratory. Samples selected covered the top 200 assay values, then
a mix of different assay values throughout each original lab job
returned.
PEA Metallurgy
Four composite samples representing the expected zones of the
‘La Mina’ VMS deposit mineralized horizons have been tested at SGS
Lakefield. Following a program of some 55 Rougher/Scavenger and
bulk cleaner tests, the results show that the La Mina VMS deposit
polymetallic mineralization responded well to a conventional
flotation flowsheet and produced saleable grade concentrates.
Locked cycle tests (LCT-1) were conducted on the composite sample
of zone 300 with primary grinding at P80 = 65 microns, copper and
zinc regrinds at P80 = 20 microns. The PEA is based on LCT-1 test
results.
The flotation test work showed good metal recoveries, creating
saleable Copper-Lead and Zinc concentrates. Copper-Lead concentrate
showed the following grades and recoveries:
Copper-Lead Concentrate Grade
Recovery Cu 20 -23 %
88 - 90 % Pb 4 - 5 %
70 - 72% Au 10 - 13 g/t
41 - 43 % Ag 140 - 145
g/t 45 - 50 %
Zinc concentrate showed the following grades and recoveries:
Zinc Concentrate Grade
Recovery Zn 50 - 52%
70 - 72% Au 11 - 13 g/t
25 - 27 % Ag 114 - 125 g/t
25 - 27 %
Figure 2 summarizes the results of the Locked Cycle Test
LCT-1.
The results from LCT-1 form the basis for the concentrator
preliminary design. Further metallurgical work can optimize the
process and test the benefit of adding a gravity circuit and pyrite
recovery on zinc flotation tailings.
Metallurgical test work was conducted by SGS Canada Inc. in
Lakefield, Ontario, Canada, under the direct supervision of Dan
Imeson, Manager, Mineral Processing. Dan Imeson has over 20 years
of experience in the mineral processing field with SGS Canada.
PEA Mining Plan
For mine planning purposes, the La Mina VMS deposit North block
was subdivided into two zones referred to as the “Upper North zone”
and the “Lower North zone”. The Upper North Zone and the Lower
North zone are scheduled to be mined between Years 1 to 3 and Years
2 to 8 respectively. The La Mina VMS deposit South block, referred
to as the “South zone” is scheduled to be mined in Years 3 to 8. A
ramp is developed to access the Upper North zone, and another ramp
is developed to access the Lower North zone and the South zone.
Deepest workings are approximately 350 metres below surface.
The Upper North zone and Lower North zone are mined using the
drift and slash with cemented rock fill (CRF) backfill method – a
variant of cut and fill mining. A 33 m high stope panel as an
example would be developed in 3 m high lifts and accessed by two
access ramps: an access decline serving the lower section of the
stope; and another ramp to access the lifts in the upper section of
the stope. The backs of an access ramp would be slashed after a
lift is backfilled in order to maintain access to the next lift.
Each lift would be developed by driving a 3 m high x 4 m wide pilot
drift in mineralization along strike, and then slashing the
mineralization on the footwall and hangingwall sides of the pilot
drift to the shanty wall stope limits. In areas where the
mineralization pinches, the pilot drift is widened to maintain a
minimum 4 m mining width. The proposed stope development sequence
including ground support and CRF backfill were selected based on
the mineralization, footwall and hangingwall characteristics and
geometry and geotechnical factors. The back and walls are supported
using pattern bolting and welded wire mesh. Once mined, each lift
would be backfilled using CRF.
Most lifts would be mined in an overhand manner. The cement
content of CRF placed in lifts that are scheduled to be under-mined
by another lift is increased to 8 wt%. The drift and slash with CRF
backfill method is also used to mine the majority of the stopes in
the South zone. The uppermost part of the South zone is mined using
room and pillar stopes with CRF backfill. Primary cut and fill
stopes are developed by driving 4.5 m high x 4.5 m wide drifts
transversely in mineralization and then CRF backfilling them.
Secondary cut and fill stopes are then developed between the
primary stopes. The ground support in the room and pillar stopes
includes cable bolts, pattern bolting, welded wire mesh and
shotcrete.
The break-even cut-off grade expressed in gold equivalent grams
per tonne milled terms is 4.24 g Au Eq / t milled. It represents
the gold equivalent grade of recovered diluted polymetallic mine
material where the revenue generated by mining and processing a
tonne of the material equals the costs incurred in producing that
revenue.
The mine development and stoping sequence was selected to reduce
upfront mine development time lines and cost; make a sufficient
number of stope faces available for stoping / backfilling over the
mine life; and to provide a flexible approach. The mine schedule is
shown in Figure 3.
PEA Processing Plant and Infrastructure
The following describes the process flow sheet for an 800 tonnes
per day copper, lead, zinc, gold and silver mineral processing
facility.
The crushing plant would process the run-of-mine (ROM) material
by using a primary jaw crusher to reduce the material from a
nominal 18 inches to a 100% passing (P100) of 249 mm (P80 of 114
mm). The grinding circuit is a semi-autogenous (SAG) mill - ball
mill grinding circuit with subsequent processing in a flotation
circuit. The SAG mill operates in closed circuit with a vibrating
screen. The ball mill operates in closed circuit with
hydrocyclones.
Cyclone overflow, the grinding circuit product, is fed to the
flotation plant. The flotation plant consists of copper/lead and
zinc flotation circuits. The copper/lead flotation circuit consists
of rougher flotation and three-stage cleaner flotation. The zinc
flotation circuit consists of rougher flotation and two-stage
cleaner flotation.
Both copper/lead and zinc concentrates are thickened, filtered,
and stored in concentrate storage facilities prior to loading onto
trucks for shipment. Zinc rougher flotation tailing and zinc first
cleaner scavenger tailing are the final tailing. Tailing thickener
underflow is pumped to a tailings storage facility (TSF). Plant
water stream types include copper/lead process water, zinc process
water, fresh water, and potable water.
The overall flowsheet is shown in Figure 4.
PEA Infrastructure
A power line would be constructed from the national grid to a
substation adjacent to the mill. An administration building would
be installed along with a mine office, health and safety, training
centre and change rooms complex. A shop / warehouse, CRF plant and
ancillary services and buildings would be constructed to service
the mine. The main mine ventilation fans would be installed on
surface. Explosive and detonators would be stored in secure
magazines located inside the mine. Tailing are placed in an
engineered TSF.
PEA Product Marketing
The NSR information used in the PEA was developed following a
review of publicly available NSR information including NI 43-101
reports and other public disclosures and information received from
metal concentrate traders. The NSR terms are based on information
received on or before March 30th, 2019. The PEA assumes that the Cu
/ Pb concentrate and the Zn concentrate would be exported and sold
to smelters in Asia. Metallurgical test results show the
concentrates are marketable.
PEA Environmental and Social Environmental aspects:
No significant adverse environmental impact is foreseen. The
conceptual level Project encompasses environmental protection
technologies. The mill products (Cu/Pb and Zn concentrates) are
exported for treatment. Mine waste rock is used to produce CRF
backfill. Clean non-acid producing waste rock is imported to
produce CRF when there is insufficient mine waste rock available.
Water from the mine and the TSF is collected and treated prior to
its recycle or release. The mill and mine process water are
obtained from the mine, water treatment plant and on-site wells.
Potable water is obtained from a well. The Project includes sewage
collection and treatment systems, double wall fuel storage tanks,
and spill kits as examples. The Company would also have procedures
to help it avoid producing hazardous wastes where possible and used
batteries or waste chemicals are properly disposed of using
licensed contractors. The Company’s environmental staff would
monitor and report on the environmental performance of the
Project.
The Project is closed and rehabilitated at the end of the mine
life. The closure works include the removal of un-used chemicals
from the mill, mill demolition, the removal of equipment and
consumables from the mine, the sealing of mine openings, the
removal and proper disposal of unused fuel, lubricants and
chemicals, infrastructure demolition, and the construction of an
engineered cap over the TSF. The effectiveness of the closure works
would be evaluated using a monitoring program.
Community consultation:
Ecuador has an established regulatory framework for social and
environmental assessment and mine permitting. The country is
encouraging and is open to mining sector investments as indicated
by the recent level of interest and investment in its mining
sector. It is widely recognized that obtaining social community
approval has proven challenging for some other mining projects in
the country. Toachi has fortunately been proactive in this area as
its Social Consultation Director has informed local people about
the Company’s vision. The Company reports that it has local public
support for a project with few dissenters, and that it plans to
continue to consult with local people and others who could be
potentially impacted by the Project. Census results indicate that
Indigenous persons account for 1% of the local Palo Quemado
township population. Recent official decisions including a decision
to cancel a referendum on another mine project in Ecuador indicate
the regulatory regime for mining is functioning.
Outlook:
The legal framework to license, develop and operate the Project
is in place. The Company’s success in this regard appears to
largely depend on the success of its future community social
consultation efforts. Delays in project permitting and
implementation may occur.
The Project requires that Toachi obtain a concession
registration for the property as a medium scale (301-1,000 tpd
throughput) mining property. It is currently a registered as a
small scale (up to 300 tpd throughout) mining property.
The Project has been designed to a conceptual level and may be
revised and improved. The PEA makes use of Inferred Resources which
are not mineral reserves and there is no guarantee that the Project
described in this PEA can be implemented.
Risk and Opportunity
Key potential risks:
- The Project could be materially
affected by social, political, environmental, permitting, legal
title, taxation, marketing and other relevant issues.
- The costs for acquiring surface access
/ surface land rights from local landowners are not known with
confidence at this point and are not included in the PEA, and the
time line to obtain them could delay the Project.
- Obtaining community social approval for
permitting, development and operations appears to be a crucial
aspect for the Project. There is a risk that the Company’s
community engagement program may need to be bolstered to maintain
wide local support for the Project. There is a latent risk of
project delays.
Key opportunities for improvement:
- The metallurgical testing completed to
date indicates that it may be possible to increase gold recovery to
the Cu/Pb concentrate which offers higher payables for gold by
initial grinding to 20 microns.
- It may be possible to optimize the mine
development and stoping sequence to improve the run of mine grade
to the mill in the initial years of the Project and improve the
project economics.
- The recommended technical studies may
lead to productivity improvements, mine operating cost savings
and/or improved environmental protection.
- The recommended study into the use of
battery-powered mine and surface haulage equipment could lead the
use of this equipment and provide an opportunity to reduce mine
ventilation power costs.
PEA Key Recommendations
Key recommendations are summarized below along with estimated
costs.
Recommendation
Estimated cost Conduct a surface diamond drilling program to
convert where possible Inferred Mineral Resources to the Indicated
Mineral Resources and/or Measured Mineral Resources categories and
explore a possible deeper extension of the La Mina VMS deposit
South block. 15,900 m @ $250/m $4,000k Conduct
a mine geotechnical characterization and design study.
$240k Conduct a tailings / waste rock storage options
study. Possible options are to: use cemented and uncemented rock
fill in stopes; use cemented paste to backfill stopes; co-dispose
waste rock and hydraulic/filtered/paste tailings in a TSF; and
combinations of the above. $400k Conduct a
hydrological / hydrogeological study to evaluate the mill water
balance and process water supply options, and TSF water pond
storage and final effluent treatment plant capacity requirements.
$250k Carry out a study to expand the
Company’s socio-economic baseline. $250k
Conduct additional metallurgical testwork to optimize metal
recoveries, concentrate grades and mill process.
$250k Total cost to implement key recommendations
$5,390k
Qualified Persons and NI 43-101 Disclosure
Independent Qualified Person David Orava, P.Eng. of SGS
Geological Services / Services Géologiques SGS, has supervised the
preparation, prepared, revised and approved the technical contents
of this news release.
This PEA is preliminary in nature and includes Inferred Mineral
Resources that are too speculative geologically to have economic
considerations applied to them to be categorized as Mineral
Reserves. Mineral Resources are not Mineral Reserves and do not
have demonstrated economic viability.
About Toachi Mining Inc.
Toachi brings a disciplined and veteran team of project managers
together with one of the industry’s highest grade polymetallic
projects at the La Mina VMS deposit in Ecuador. Toachi is focused
on and committed to the development of advanced stage mineral
projects throughout the Americas using industry best practices
combined with a strong social license from local communities.
Toachi Mining has 81,166,435 shares issued and outstanding.
Forward Looking Statements
Certain statements contained in this news release may constitute
“forward-looking information” as such term is used in applicable
Canadian securities laws. Forward-looking information is based on
plans, expectations and estimates of management at the date the
information is provided and is subject to certain factors and
assumptions, including, that the Company’s financial condition and
development plans do not change as a result of unforeseen events
and that the Company obtains regulatory approval. Forward-looking
information is subject to a variety of risks and uncertainties and
other factors that could cause plans, estimates and actual results
to vary materially from those projected in such forward-looking
information. Factors that could cause the forward-looking
information in this news release to change or to be inaccurate
include, but are not limited to, the risk that any of the
assumptions referred to prove not to be valid or reliable, that
occurrences such as those referred to above are realized and result
in delays, or cessation in planned work, that the Company’s
financial condition and development plans change, and delays in
regulatory approval, as well as the other risks and uncertainties
applicable to the Company as set forth in the Company’s continuous
disclosure filings filed under the Company’s profile at
www.sedar.com. The Company undertakes no obligation to update these
forward-looking statements, other than as required by applicable
law.
Neither TSX Venture Exchange nor its Regulation Services
Provider (as that term is defined in the policies of the TSX Venture
Exchange) accepts responsibility for the adequacy or accuracy of
this release.
View source
version on businesswire.com: https://www.businesswire.com/news/home/20190430005522/en/
Alain BureauPresident and CEOCandace Di VitoManager, Investor
RelationsTelephone: 416 365 7043Email: cdivito@toachimining.com
Toachi Mining (TSXV:TIM)
Historical Stock Chart
From Feb 2025 to Mar 2025
Toachi Mining (TSXV:TIM)
Historical Stock Chart
From Mar 2024 to Mar 2025